Accelerating Wireless and Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment, 51867-51886 [2018-22234]
Download as PDF
51867
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
Energy Supply, Distribution, or Use’’ (66
FR 28355, May 22, 2001) or Executive
Order 13045, entitled ‘‘Protection of
Children from Environmental Health
Risks and Safety Risks’’ (62 FR 19885,
April 23, 1997); or Executive Order
13771, entitled ‘‘Reducing Regulations
and Controlling Regulatory Costs’’ (82
FR 9339, February 3, 2017). This action
does not contain any information
collections subject to OMB approval
under the Paperwork Reduction Act
(PRA) (44 U.S.C. 3501 et seq.), nor does
it require any special considerations
under Executive Order 12898, entitled
‘‘Federal Actions to Address
Environmental Justice in Minority
Populations and Low-Income
Populations’’ (59 FR 7629, February 16,
1994).
Since tolerances and exemptions that
are established on the basis of a petition
under FFDCA section 408(d), such as
the tolerance in this final rule, do not
require the issuance of a proposed rule,
the requirements of the Regulatory
Flexibility Act (RFA) (5 U.S.C. 601 et
seq.), do not apply.
This action directly regulates growers,
food processors, food handlers, and food
retailers, not States or tribes, nor does
this action alter the relationships or
distribution of power and
responsibilities established by Congress
in the preemption provisions of FFDCA
section 408(n)(4). As such, the Agency
has determined that this action will not
have a substantial direct effect on States
or tribal governments, on the
relationship between the national
government and the States or tribal
governments, or on the distribution of
power and responsibilities among the
various levels of government or between
the Federal Government and Indian
tribes. Thus, the Agency has determined
that Executive Order 13132, entitled
‘‘Federalism’’ (64 FR 43255, August 10,
1999) and Executive Order 13175,
entitled ‘‘Consultation and Coordination
with Indian Tribal Governments’’ (65 FR
67249, November 9, 2000) do not apply
to this action. In addition, this action
does not impose any enforceable duty or
contain any unfunded mandate as
described under Title II of the Unfunded
Mandates Reform Act (UMRA) (2 U.S.C.
1501 et seq.).
This action does not involve any
technical standards that would require
Agency consideration of voluntary
consensus standards pursuant to section
12(d) of the National Technology
Transfer and Advancement Act
(NTTAA) (15 U.S.C. 272 note).
VII. Congressional Review Act
Pursuant to the Congressional Review
Act (5 U.S.C. 801 et seq.), EPA will
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
submit a report containing this rule and
other required information to the U.S.
Senate, the U.S. House of
Representatives, and the Comptroller
General of the United States prior to
publication of the rule in the Federal
Register. This action is not a ‘‘major
rule’’ as defined by 5 U.S.C. 804(2).
Parts per
million
Commodity
*
*
*
*
Plum subgroup 12–12C ..............
*
*
*
*
*
*
*
*
*
0.15
*
*
List of Subjects in 40 CFR Part 180
Environmental protection,
Administrative practice and procedure,
Agricultural commodities, Pesticides
and pests, Reporting and recordkeeping
requirements.
[FR Doc. 2018–22279 Filed 10–12–18; 8:45 am]
Dated: October 2, 2018.
Michael L. Goodis,
Director, Registration Division, Office of
Pesticide Programs.
47 CFR Part 1
Therefore, 40 CFR chapter I is
amended as follows:
Accelerating Wireless and Wireline
Broadband Deployment by Removing
Barriers to Infrastructure Investment
Federal Communications
Commission.
ACTION: Final rule.
AGENCY:
1. The authority citation for part 180
continues to read as follows:
■
Authority: 21 U.S.C. 321(q), 346a and 371.
2. Amend the table in § 180.593(a) as
follows:
■ a. Add alphabetically the entries for
‘‘Cherry subgroup 12–12A’’; ‘‘Corn,
sweet, forage’’; ‘‘Corn, sweet, kernel
plus cob with husks removed’’; ‘‘Corn,
sweet, stover’’; ‘‘Cottonseed subgroup
20C’’; ‘‘Fruit, pome, group 11–10’’;
‘‘Nut, tree group 14–12’’; Peach
subgroup 12–12B’’; and ‘‘Plum subgroup
12–12C’’.
■ b. Remove the entries for ‘‘Cotton,
undelinted seed’’; ‘‘Fruit, pome, group
11’’; ‘‘Fruit, stone, group 12, except
plum’’; ‘‘Nut, tree, group 14’’;
‘‘Pistachio’’; and ‘‘Plum.’’
■
§ 180.593 Etoxazole; tolerances for
residues.
(a) * * *
Parts per
million
*
*
*
*
Cherry subgroup 12–12A ...........
*
*
*
*
*
Corn, sweet, forage ....................
Corn, sweet, kernel plus cob
with husks removed ................
Corn, sweet, stover .....................
*
0.01
5.0
*
*
*
*
Cottonseed subgroup 20C .........
Fruit, pome, group 11–10 ...........
*
0.05
0.20
*
*
*
*
Nut, tree group 14–12 ................
*
0.01
*
*
*
*
Peach subgroup 12–12B ............
*
PO 00000
Frm 00053
Fmt 4700
Sfmt 4700
FEDERAL COMMUNICATIONS
COMMISSION
[WT Docket No. 17–79, WC Docket No. 17–
84; FCC 18–133]
PART 180—[AMENDED]
Commodity
BILLING CODE 6560–50–P
1.0
1.5
1.0
In this document, the Federal
Communications Commission
(‘‘Commission’’ or ‘‘FCC’’) issues
guidance and adopts rules to streamline
the wireless infrastructure siting review
process to facilitate the deployment of
next-generation wireless facilities.
Specifically, in the Declaratory Ruling,
the Commission identifies specific fee
levels for the deployment of Small
Wireless Facilities, and it addresses
state and local consideration of aesthetic
concerns that effect the deployment of
Small Wireless Facilities. In the Order,
the Commission addresses the ‘‘shot
clocks’’ governing the review of wireless
infrastructure deployments and
establishes two new shot clocks for
Small Wireless Facilities.
DATES: Effective January 14, 2019.
FOR FURTHER INFORMATION CONTACT:
Jiaming Shang, Deputy Chief (Acting)
Competition and Infrastructure Policy
Division, Wireless Telecommunications
Bureau, (202) 418–1303, email
Jiaming.shang@fcc.gov.
SUPPLEMENTARY INFORMATION: This is a
summary of the Commission’s
Declaratory Ruling and Third Report
and Order (Declaratory Ruling and
Order), WT Docket No. 17–79 and WC
Docket No. 17–84; FCC 18–133, adopted
September 26, 2018 and released
September 27, 2018. The full text of this
document is available for inspection
and copying during business hours in
the FCC Reference Information Center,
Portals II, 445 12th Street SW, Room
CY–A257, Washington, DC 20554. Also,
it may be purchased from the
Commission’s duplicating contractor at
SUMMARY:
E:\FR\FM\15OCR1.SGM
15OCR1
51868
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
Portals II, 445 12th Street SW, Room
CY–B402, Washington, DC 20554; the
contractor’s website, https://
www.bcpiweb.com; or by calling (800)
378–3160, facsimile (202) 488–5563, or
email FCC@BCPIWEB.com. Copies of
the Declaratory Ruling and Order also
may be obtained via the Commission’s
Electronic Comment Filing System
(ECFS) by entering the docket number
WT Docket 17–79 and WC Docket No.
17–84. Additionally, the complete item
is available on the Federal
Communications Commission’s website
at https://www.fcc.gov.
Synopsis
khammond on DSK30JT082PROD with RULES
I. Declaratory Ruling
1. In the Declaratory Ruling, the
Commission notes that a number of
appellate courts have articulated
different and often conflicting views
regarding the scope and nature of the
limits Congress imposed on state and
local governments through Sections 253
and 332. In light of these diverging
views, Congress’s vision for a
consistent, national policy framework,
and the need to ensure that the
Commission’s approach continues to
make sense in light of the relatively new
trend towards the large-scale
deployment of Small Wireless Facilities,
the Commission takes the opportunity
to clarify and update the FCC’s reading
of the limits Congress imposed. The
Commission does so in three main
respects.
2. First, the Commission expresses its
agreement with the views already stated
by the First, Second, and Tenth Circuits
that the ‘‘materially inhibit’’ standard
articulated in 1997 by the Clinton-era
FCC’s California Payphone decision is
the appropriate standard for
determining whether a state or local law
operates as a prohibition or effective
prohibition within the meaning of
Sections 253 and 332.
3. Second, the Commission notes, as
numerous courts have recognized, that
state and local fees and other charges
associated with the deployment of
wireless infrastructure can effectively
prohibit the provision of service. At the
same time, courts have articulated
various approaches to determining the
types of fees that run afoul of Congress’s
limits in Sections 253 and 332. The
Commission thus clarifies the particular
standard that governs the fees and
charges that violate Sections 253 and
332 when it comes to the Small Wireless
Facilities at issue in this decision.
Namely, fees are only permitted to the
extent that they represent a reasonable
approximation of the local government’s
objectively reasonable costs and are
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
non-discriminatory. In this section, the
Commission also identifies specific fee
levels for the deployment of Small
Wireless Facilities that presumptively
comply with this standard. The
Commission does so to help avoid
unnecessary litigation, while
recognizing that it is the standard itself,
not the particular, presumptive fee
levels the Commission articulates, that
ultimately will govern whether a
particular fee is allowed under Sections
253 and 332. So, fees above those levels
would be permissible under Sections
253 and 332 to the extent a locality’s
actual, reasonable costs (as measured by
the standard above) are higher.
4. Finally, the Commission focuses on
a subset of other, non-fee provisions of
state and local law that could also
operate as prohibitions on service. The
Commission does so in particular by
addressing state and local consideration
of aesthetic concerns in the deployment
of Small Wireless Facilities. The
Commission notes that the Small
Wireless Facilities that are the subject of
this Declaratory Ruling remain subject
to the Commission’s rules governing
Radio Frequency (RF) emissions
exposure.
A. Overview of the Section 253 and
Section 332(c)(7) Framework Relevant to
Small Wireless Facilities Deployment
5. As an initial matter, the
Commission notes that its Declaratory
Ruling applies with equal measure to
the effective prohibition standard that
appears in both Sections 253(a) and
332(c)(7). This ruling is consistent with
the basic canon of statutory
interpretation that identical words
appearing in neighboring provisions of
the same statute should be interpreted
to have the same meaning. Moreover,
both of these provisions apply to
wireless telecommunications services as
well as to commingled services and
facilities.
6. As explained in California
Payphone and reaffirmed here, a state or
local legal requirement will have the
effect of prohibiting wireless
telecommunications services if it
materially inhibits the provision of such
services. California Payphone Ass’n, 12
FCC Rcd 14191 (1997). The Commission
clarifies that an effective prohibition
occurs where a state or local legal
requirement materially inhibits a
provider’s ability to engage in any of a
variety of activities related to its
provision of a covered service. This test
is met not only when filling a coverage
gap but also when densifying a wireless
network, introducing new services or
otherwise improving service
capabilities. Under the California
PO 00000
Frm 00054
Fmt 4700
Sfmt 4700
Payphone standard, a state or local legal
requirement could materially inhibit
service in numerous ways—not only by
rendering a service provider unable to
provide an existing service in a new
geographic area or by restricting the
entry of a new provider in providing
service in a particular area, but also by
materially inhibiting the introduction of
new services or the improvement of
existing services. Thus, an effective
prohibition includes materially
inhibiting additional services or
improving existing services.
7. The Commission’s reading of
Section 253(a) and Section
332(c)(7)(B)(i)(II) reflects and supports a
marketplace in which services can be
offered in a multitude of ways with
varied capabilities and performance
characteristics consistent with the
policy goals in the 1996 Act and the
Communications Act. To limit Sections
253(a) and 332(c)(7)(B)(i)(II) to
protecting only against coverage gaps or
the like would be to ignore Congress’s
contemporaneously-expressed goals of
‘‘promot[ing] competition[,] . . .
secur[ing] . . . higher quality services
for American telecommunications
consumers and encourage[ing] the rapid
deployment of new telecommunications
technologies.’’ In addition, as the
Commission recently explained, the
implementation of the Act ‘‘must factor
in the fundamental objectives of the Act,
including the deployment of a ‘‘rapid,
efficient . . . wire and radio
communication service with adequate
facilities at reasonable charges’ and ‘the
development and rapid deployment of
new technologies, products and services
for the benefit of the public . . . without
administrative or judicial delays[, and]
efficient and intensive use of the
electromagnetic spectrum.’ ’’ These
provisions demonstrate that the
Commission’s interpretation of Section
253 and Section 332(c)(7)(B)(i)(II) is in
accordance with the broader goals of the
various statutes that the Commission is
entrusted to administer.
8. California Payphone further
concluded that providers must be
allowed to compete in a ‘‘fair and
balanced regulatory environment.’’ As
reflected in decisions such as the
Commission’s Texas PUC Order, a state
or local legal requirement can function
as an effective prohibition either
because of the resulting ‘‘financial
burden’’ in an absolute sense, or,
independently, because of a resulting
competitive disparity. Public Utility
Comm’n of Texas, et al., Pet. for Decl.
Ruling and/or Preemption of Certain
Provisions of the Texas Pub. Util. Reg.
Act of 1995, 13 FCC Rcd 3460 (1997).
The Commission clarifies that ‘‘[a]
E:\FR\FM\15OCR1.SGM
15OCR1
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
khammond on DSK30JT082PROD with RULES
regulatory structure that gives an
advantage to particular services or
facilities has a prohibitory effect, even if
there are no express barriers to entry in
the state or local code; the greater the
discriminatory effect, the more certain it
is that entities providing service using
the disfavored facilities will experience
prohibition.’’ This conclusion is
consistent with both Commission and
judicial precedent recognizing the
prohibitory effect that results from a
competitor being treated materially
differently than similarly-situated
providers. The Commission provides its
authoritative interpretation below of the
circumstances in which a ‘‘financial
burden,’’ as described in the Texas PUC
Order, constitutes an effective
prohibition in the context of certain
state and local fees.
B. State and Local Fees
9. Cognizant of the changing
technology and its interaction with
regulations created for a previous
generation of service, the Commission
sought comment on the scope of
Sections 253 and 332(c)(7) and on any
new or updated guidance the
Commission should provide, potentially
through a Declaratory Ruling. In
particular, the Commission sought
comment on whether it should provide
further guidance on how to interpret
and apply the phrase ‘‘prohibit or have
the effect of prohibiting.’’
10. The Commission concludes that
ROW access fees, and fees for the use of
government property in the ROW, such
as light poles, traffic lights, utility poles,
and other similar property suitable for
hosting Small Wireless Facilities, as
well as application or review fees and
similar fees imposed by a state or local
government as part of their regulation of
the deployment of Small Wireless
Facilities inside and outside the ROW,
violate Sections 253 or 332(c)(7) unless
these conditions are met: (1) The fees
are a reasonable approximation of the
state or local government’s costs, (2)
only objectively reasonable costs are
factored into those fees, and (3) the fees
are no higher than the fees charged to
similarly-situated competitors in similar
situations.
11. Capital Expenditures. Apart from
the text, structure, and legislative
history of the 1996 Act, an additional,
independent justification for the
Commission’s interpretation follows
from the simple, logical premise,
supported by the record, that state and
local fees in one place of deployment
necessarily have the effect of reducing
the amount of capital that providers can
use to deploy infrastructure elsewhere,
whether the reduction takes place on a
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
local, regional or national level. The
Commission is persuaded that providers
and infrastructure builders, like all
economic actors, have a finite (though
perhaps fluid) amount of resources to
use for the deployment of infrastructure.
This does not mean that these resources
are limitless, however. The Commission
concludes that fees imposed by
localities, above and beyond the
recovery of localities’ reasonable costs,
materially and improperly inhibit
deployment that could have occurred
elsewhere. This and regulatory
uncertainty created by such effectively
prohibitive conduct creates an
appreciable impact on resources that
materially limits plans to deploy
service. This record evidence
emphasizes the importance of
evaluating the effect of fees on Small
Wireless Facility deployment on an
aggregate basis. The record persuades
the Commission that fees associated
with Small Wireless Facility
deployment lead to ‘‘a substantial
increase in costs’’—particularly when
considered in the aggregate—thereby
‘‘plac[ing] a significant burden’’ on
carriers and materially inhibiting their
provision of service contrary to Section
253 of the Act.
12. The record reveals that fees above
a reasonable approximation of cost,
even when they may not be perceived
as excessive or likely to prohibit service
in isolation, will have the effect of
prohibiting wireless service when the
aggregate effects are considered,
particularly given the nature and
volume of anticipated Small Wireless
Facility deployment. The record reveals
that these effects can take several forms.
In some cases, the fees in a particular
jurisdiction will lead to reduced or
entirely forgone deployment of Small
Wireless Facilities in the near term for
that jurisdiction. In other cases, where
it is essential for a provider to deploy
in a given area, the fees charged in that
geographic area can deprive providers of
capital needed to deploy elsewhere, and
lead to reduced or forgone near-term
deployment of Small Wireless Facilities
in other geographic areas. In both of
those scenarios the bottom-line outcome
on the national development of 5G
networks is the same—diminished
deployment of Small Wireless Facilities
critical for wireless service and building
out 5G networks.
13. Relationship to Section 332. The
Commission clarifies that the statutory
phrase ‘‘prohibit or have the effect of
prohibiting’’ in Section 332(c)(7)(B)(i)(II)
has the same meaning as the phrase
‘‘prohibits or has the effect of
prohibiting’’ in Section 253(a). There is
no evidence to suggest that Congress
PO 00000
Frm 00055
Fmt 4700
Sfmt 4700
51869
intended for virtually identical language
to have different meanings in the two
provisions. Instead, the Commission
finds it more reasonable to conclude
that the language in both sections
should be interpreted to have the same
meaning and to reflect the same
standard, including with respect to
preemption of fees that could ‘‘prohibit’’
or have ‘‘the effect of prohibiting’’ the
provision of covered service. Both
sections were enacted to address
concerns about state and local
government practices that undermined
providers’ ability to provide covered
services, and both bar state or local
conduct that prohibits or has the effect
of prohibiting service.
14. To be sure, Sections 253 and
332(c)(7) may relate to different
categories of state and local fees.
Ultimately, the Commission needs not
resolve here the precise interplay
between Sections 253 and 332(c)(7). It is
enough for it to conclude that,
collectively, Congress intended for the
two provisions to cover the universe of
fees charged by state and local
governments in connection with the
deployment of telecommunications
infrastructure. Given the analogous
purposes of both sections and the
consistent language used by Congress,
the Commission finds the phrase
‘‘prohibit or have the effect of
prohibiting’’ in Section 332(c)(7)(B)(i)(II)
should be construed as having the same
meaning and governed by the same
preemption standard as the nearly
identical language in Section 253(a).
15. Application of the Interpretations
and Principles Established Here.
Consistent with the interpretations
above, the requirement that
compensation be limited to a reasonable
approximation of objectively reasonable
costs and be non-discriminatory applies
to all state and local government fees
paid in connection with a provider’s use
of the ROW to deploy Small Wireless
Facilities including, but not limited to,
fees for access to the ROW itself, and
fees for the attachment to or use of
property within the ROW owned or
controlled by the government (e.g.,
street lights, traffic lights, utility poles,
and other infrastructure within the
ROW suitable for the placement of
Small Wireless Facilities). This
interpretation applies with equal force
to any fees reasonably related to the
placement, construction, maintenance,
repair, movement, modification,
upgrade, replacement, or removal of
Small Wireless Facilities within the
ROW, including, but not limited to,
application or permit fees such as siting
applications, zoning variance
applications, building permits, electrical
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
51870
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
permits, parking permits, or excavation
permits.
16. Applying the principles
established in this Declaratory Ruling, a
variety of fees not reasonably tethered to
costs appear to violate Sections 253(a)
or 332(c)(7) in the context of Small
Wireless Facility deployments. For
example, the Commission agrees with
courts that have recognized that gross
revenue fees generally are not based on
the costs associated with an entity’s use
of the ROW, and where that is the case,
are preempted under Section 253(a). In
addition, although the Commission
rejects calls to preclude a state or
locality’s use of third party contractors
or consultants, or to find all associated
compensation preempted, the
Commission makes clear that the
principles discussed herein regarding
the reasonableness of cost remain
applicable. Thus, fees must not only be
limited to a reasonable approximation of
costs, but in order to be reflected in fees
the costs themselves must also be
reasonable. Accordingly, any
unreasonably high costs, such as
excessive charges by third party
contractors or consultants, may not be
passed on through fees even though
they are an actual ‘‘cost’’ to the
government. If a locality opts to incur
unreasonable costs, Sections 253 and
332(c)(7) do not permit it to pass those
costs on to providers. Fees that depart
from these principles are not saved by
Section 253(c), as the Commission
discusses below.
17. Interpretation of Section 253(c) in
the Context of Fees. In this section, the
Commission turns to the interpretation
of several provisions in Section 253(c),
which provides that state or local action
that otherwise would be subject to
preemption under Section 253(a) may
be permissible if it meets specified
criteria. Section 253(c) expressly
provides that state or local governments
may require telecommunications
providers to pay ‘‘fair and reasonable
compensation’’ for use of public ROWs
but requires that the amounts of any
such compensation be ‘‘competitively
neutral and nondiscriminatory’’ and
‘‘publicly disclosed.’’
18. The Commission interprets the
ambiguous phrase ‘‘fair and reasonable
compensation,’’ within the statutory
framework it outlined for Section 253,
to allow state or local governments to
charge fees that recover a reasonable
approximation of the state or local
governments’ actual and reasonable
costs. The Commission concludes that
an appropriate yardstick for ‘‘fair and
reasonable compensation,’’ and
therefore an indicator of whether a fee
violates Section 253(c), is whether it
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
recovers a reasonable approximation of
a state or local government’s objectively
reasonable costs of, respectively,
maintaining the ROW, maintaining a
structure within the ROW, or processing
an application or permit.
19. The existence of Section 253(c)
makes clear that Congress anticipated
that ‘‘effective prohibitions’’ could
result from state or local government
fees, and intended through that clause
to provide protections in that respect, as
discussed in greater detail herein.
Against that backdrop, the Commission
finds it unlikely that Congress would
have left providers entirely at the mercy
of effectively unconstrained
requirements of state or local
governments. The Commission’s
interpretation of Section 253(c), in fact,
is consistent with the views of many
municipal commenters, at least with
respect to one-time permit or
application fees, and the members of the
BDAC Ad Hoc Committee on Rates and
Fees who unanimously concurred that
one-time fees for municipal applications
and permits, such as an electrical
inspection or a building permit, should
be based on the cost to the government
of processing that application. The Ad
Hoc Committee noted that ‘‘[the] costbased fee structure [for one-time fees]
unanimously approved by the
committee accommodates the different
siting related costs that different
localities may incur to review, and
process permit applications, while
precluding excessive fees that impede
deployment.’’ The Commission finds
that the same reasoning should apply to
other state and local government fees
such as ROW access fees or fees for the
use of government property within the
ROW.
20. The Commission recognizes that
state and local governments incur a
variety of direct and actual costs in
connection with Small Wireless
Facilities, such as the cost for staff to
review the provider’s siting application,
costs associated with a provider’s use of
the ROW, and costs associated with
maintaining the ROW itself or structures
within the ROW to which Small
Wireless Facilities are attached. The
Commission also recognizes that direct
and actual costs may vary by location,
scope, and extent of providers’ planned
deployments, such that different
localities will have different fees under
the interpretation set forth in this
Declaratory Ruling.
21. Because the Commission
interprets fair and reasonable
compensation as a reasonable
approximation of costs, it does not
suggest that localities must use any
specific accounting method to
PO 00000
Frm 00056
Fmt 4700
Sfmt 4700
document the costs they may incur
when determining the fees they charge
for Small Wireless Facilities within the
ROW. Moreover, in order to simplify
compliance, when a locality charges
both types of recurring fees identified
above (i.e., for access to the ROW and
for use of or attachment to property in
the ROW), the Commission sees no
reason for concern with how it has
allocated costs between those two types
of fees. It is sufficient under the statute
that the total of the two recurring fees
reflects the total costs involved. Fees
that cannot ultimately be shown by a
state or locality to be a reasonable
approximation of their costs, such as
high fees designed to subsidize local
government costs in another geographic
area or accomplish some public policy
objective beyond the providers’ use of
the ROW, are not ‘‘fair and reasonable
compensation . . . for use of the public
rights-of-way’’ under Section 253(c).
Likewise, the Commission agrees with
both industry and municipal
commenters that excessive and arbitrary
consulting fees or other costs should not
be recoverable as ‘‘fair and reasonable
compensation,’’ because they are not a
function of the provider’s ‘‘use’’ of the
public ROW.
22. In addition to requiring that
compensation be ‘‘fair and reasonable,’’
Section 253(c) requires that it be
‘‘competitively neutral and
nondiscriminatory.’’ The Commission
has previously interpreted this language
to prohibit states and localities from
charging fees on new entrants and not
on incumbents. Courts have similarly
found that states and localities may not
impose a range of fees on one provider
but not on another and even some
municipal commenters acknowledge
that governments should not
discriminate on the fees charged to
different providers. The record reflects
continuing concerns from providers,
however, that they face discriminatory
charges. The Commission reiterates its
previous determination that state and
local governments may not impose fees
on some providers that they do not
impose on others. The Commission
would also be concerned about fees,
whether one-time or recurring, related
to Small Wireless Facilities, that exceed
the fees for other wireless
telecommunications infrastructure in
similar situations, and to the extent that
different fees are charged for similar use
of the public ROW.
23. Fee Levels Likely to Comply with
Section 253. The Commission’s
interpretations of Section 253(a) and
‘‘fair and reasonable compensation’’
under Section 253(c) provides guidance
for local and state fees charged with
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
respect to one-time fees generally, and
recurring fees for deployments in the
ROW. Following suggestions for the
Commission to ‘‘establish a
presumptively reasonable ‘safe harbor’
for certain ROW and use fees,’’ and to
facilitate the deployment of specific
types of infrastructure critical to the
rollout of 5G in coming years, the
Commission identifies in this section
three particular types of fee scenarios
and supply specific guidance on
amounts that are presumptively not
prohibited by Section 253. Informed by
the its review of information from a
range of sources, the Commission
concludes that fees at or below these
amounts presumptively do not
constitute an effective prohibition under
Section 253(a) or Section 332(c)(7) and
are presumed to be ‘‘fair and reasonable
compensation’’ under Section 253(c).
24. Based on its review of the
Commission’s pole attachment rate
formula, which would require fees
below the levels described in this
paragraph, as well as small cell
legislation in twenty states, local
legislation from certain municipalities
in states that have not passed small cell
legislation, and comments in the record,
the Commission presumes that the
following fees would not be prohibited
by Section 253 or Section 332(c)(7): (a)
$500 for non-recurring fees, including a
single up-front application that includes
up to five Small Wireless Facilities,
with an additional $100 for each Small
Wireless Facility beyond five, or $1,000
for non-recurring fees for a new pole
(i.e., not a collocation) intended to
support one or more Small Wireless
Facilities, and (b) $270 per Small
Wireless Facility per year for all
recurring fees, including any possible
ROW access fee or fee for attachment to
municipally-owned structures in the
ROW.
25. By presuming that fees at or below
the levels above comply with Section
253, the Commission assumes that there
would be almost no litigation by
providers over fees set at or below these
levels. Likewise, the Commission’s
review of the record, including the
many state small cell bills passed to
date, indicate that there should be only
very limited circumstances in which
localities can charge higher fees
consistent with the requirements of
Section 253. In those limited
circumstances, a locality could prevail
in charging fees that are above this level
by showing that such fees nonetheless
comply with the limits imposed by
Section 253—that is, that they are (1) a
reasonable approximation of costs, (2)
those costs themselves are reasonable,
and (3) are non-discriminatory.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
Allowing localities to charge fees above
these levels upon this showing
recognizes local variances in costs.
C. Other State and Local Requirements
That Govern Small Facilities
Deployment
26. There are also other types of state
and local land-use or zoning
requirements that may restrict Small
Wireless Facility deployments to the
degree that they have the effect of
prohibiting service in violation of
Sections 253 and 332. In this section,
the Commission discusses how those
statutory provisions apply to
requirements outside the fee context
both generally, and with particular
focus on aesthetic and undergrounding
requirements.
27. As discussed above, a state or
local legal requirement constitutes an
effective prohibition if it ‘‘materially
limits or inhibits the ability of any
competitor or potential competitor to
compete in a fair and balanced legal and
regulatory environment.’’ The
Commission’s interpretation of that
standard, as set forth above, applies
equally to fees and to non-fee legal
requirements. And as with fees, Section
253 contains certain safe harbors that
permit some legal requirements that
might otherwise be preempted by
Section 253(a). Section 253(b) saves
‘‘requirements necessary to preserve and
advance universal service, protect the
public safety and welfare, ensure the
continued quality of
telecommunications services, and
safeguard the rights of consumers. And
Section 253(c) preserves state and local
authority to manage the public rights-ofway.
28. Given the wide variety of possible
legal requirements, the Commission
does not attempt here to determine
which of every possible non-fee legal
requirements are preempted for having
the effect of prohibiting service,
although the Commission’s discussion
of fees above should prove instructive in
evaluating specific requirements.
Instead, the Commission focuses on
some specific types of requirements
raised in the record and provide
guidance on when those particular types
of requirements are preempted by the
statute.
29. Aesthetics. The Commission
sought comment on whether
deployment restrictions based on
aesthetic or similar factors are
widespread and, if so, how Sections 253
and 332(c)(7) should be applied to them.
The Commission provides guidance on
whether and in what circumstances
aesthetic requirements violate the Act.
This will help localities develop and
PO 00000
Frm 00057
Fmt 4700
Sfmt 4700
51871
implement lawful rules, enable
providers to comply with these
requirements, and facilitate the
resolution of disputes. The Commission
concludes that aesthetics requirements
are not preempted if they are (1)
reasonable, (2) no more burdensome
than those applied to other types of
infrastructure deployments, and (3)
objective and published in advance.
30. Like fees, compliance with
aesthetic requirements imposes costs on
providers, and the impact on their
ability to provide service is just the
same as the impact of fees. The
Commission therefore draws on its
analysis of fees to address aesthetic
requirements. The Commission
explained above that fees that merely
require providers to bear the direct and
reasonable costs that their deployments
impose on states and localities should
not be viewed as having the effect of
prohibiting service and are permissible.
Analogously, aesthetic requirements
that are reasonable in that they are
technically feasible and reasonably
directed to avoiding or remedying the
intangible public harm of unsightly or
out-of-character deployments are also
permissible. In assessing whether this
standard has been met, aesthetic
requirements that are more burdensome
than those the state or locality applies
to similar infrastructure deployments
are not permissible, because such
discriminatory application evidences
that the requirements are not, in fact,
reasonable and directed at remedying
the impact of the wireless infrastructure
deployment. For example, a minimum
spacing requirement that has the effect
of materially inhibiting wireless service
would be considered an effective
prohibition of service.
31. Finally, in order to establish that
they are reasonable and reasonably
directed to avoiding aesthetic harms,
aesthetic requirements must be
objective—i.e., they must incorporate
clearly-defined and ascertainable
standards, applied in a principled
manner—and must be published in
advance. ‘‘Secret’’ rules that require
applicants to guess at what types of
deployments will pass aesthetic muster
substantially increase providers’ costs
without providing any public benefit or
addressing any public harm. Providers
cannot design or implement rational
plans for deploying Small Wireless
Facilities if they cannot predict in
advance what aesthetic requirements
they will be obligated to satisfy to obtain
permission to deploy a facility at any
given site.
32. The Commission appreciates that
at least some localities will require some
time to establish and publish aesthetics
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
51872
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
standards that are consistent with this
Declaratory Ruling. Based on its review
and evaluation of commenters’
concerns, the Commission anticipates
that such publication should take no
longer than 180 days after publication of
this decision in the Federal Register.
33. Undergrounding requirements.
The Commission understands that some
local jurisdictions have adopted
undergrounding provisions that require
infrastructure to be deployed below
ground based, at least in some
circumstances, on the locality’s
aesthetic concerns. A number of
providers have complained that these
types of requirements amount to an
effective prohibition. In addressing this
issue, the Commission first reiterates
that while undergrounding
requirements may well be permissible
under state law as a general matter, any
local authority to impose
undergrounding requirements under
state law does not remove the
imposition of such undergrounding
requirements from the provisions of
Section 253. In this sense, the
Commission notes that a requirement
that all wireless facilities be deployed
underground would amount to an
effective prohibition given the
propagation characteristics of wireless
signals. Thus, undergrounding
requirements can amount to effective
prohibitions by materially inhibiting the
deployment of wireless service.
34. Minimum spacing requirements.
Some parties complain of municipal
requirements regarding the spacing of
wireless installations—i.e., mandating
that facilities be sited at least 100, 500,
or 1,000 feet, or some other minimum
distance, away from other facilities,
ostensibly to avoid excessive overhead
‘‘clutter’’ that would be visible from
public areas. The Commission
acknowledges that while some such
requirements may violate 253(a), others
may be reasonable aesthetic
requirements. For example, under the
principle that any such requirements be
reasonable and publicly available in
advance, it is difficult to envision any
circumstances in which a municipality
could reasonably promulgate a new
minimum spacing requirement that, in
effect, prevents a provider from
replacing its preexisting facilities or
collocating new equipment on a
structure already in use. Such a rule
change with retroactive effect would
almost certainly have the effect of
prohibiting service under the standards
the Commission articulate here.
Therefore, such requirements should be
evaluated under the same standards as
other aesthetic requirements.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
D. States and Localities Act in Their
Regulatory Capacities When
Authorizing and Setting Terms for
Wireless Infrastructure Deployment in
Public Rights of Way
35. The Commission confirms that it
interpretations today extend to state and
local governments’ terms for access to
public ROW that they own or control,
including areas on, below, or above
public roadways, highways, streets,
sidewalks, or similar property, as well
as their terms for use of or attachment
to government-owned property within
such ROW, such as light poles, traffic
lights, and similar property suitable for
hosting Small Wireless Facilities. As
explained below, for two alternative and
independent reasons, the Commission
disagrees with state and local
government commenters who assert
that, in providing or denying access to
government-owned structures, these
governmental entities function solely as
‘‘market participants’’ whose rights
cannot be subject to federal preemption
under Section 253(a) or Section
332(c)(7).
36. First, this effort to differentiate
between such governmental entities’
‘‘regulatory’’ and ‘‘proprietary’’
capacities in order to insulate the latter
from preemption ignores a fundamental
feature of the market participant
doctrine. Specifically, Section 253(a)
expressly preempts certain state and
local ‘‘legal requirements’’ and makes
no distinction between a state or
locality’s regulatory and proprietary
conduct. Indeed, as the Commission has
long recognized, Section 253(a)’s
sweeping reference to ‘‘state [and] local
statute[s] [and] regulation[s]’’ and ‘‘other
State [and] local legal requirement[s]’’
demonstrates Congress’s intent ‘‘to
capture a broad range of state and local
actions that prohibit or have the effect
of prohibiting entities from providing
telecommunications services.’’ Section
253(b) mentions ‘‘requirement[s],’’ a
phrase that is even broader than that
used in Section 253(a) but covers
‘‘universal service,’’ ‘‘public safety and
welfare,’’ ‘‘continued quality of
telecommunications,’’ and ‘‘safeguard[s
for the] rights of consumers.’’ The
subsection does not recognize a
distinction between regulatory and
proprietary. Section 253(c), which
expressly insulates from preemption
certain state and local government
activities, refers in relevant part to
‘‘manag[ing] the public rights-of-way’’
and ‘‘requir[ing] fair and reasonable
compensation,’’ while eliding any
distinction between regulatory and
proprietary action in either context. The
Commission has previously observed
PO 00000
Frm 00058
Fmt 4700
Sfmt 4700
that Section 253(c) ‘‘makes explicit a
local government’s continuing authority
to issue construction permits regulating
how and when construction is
conducted on roads and other public
rights-of-way;’’ the Commission
concludes here that, as a general matter,
‘‘manage[ment]’’ of the ROW includes
any conduct that bears on access to and
use of those ROW, notwithstanding any
attempts to characterize such conduct as
proprietary. This reading, coupled with
Section 253(c)’s narrow scope, suggests
that Congress’s omission of a blanket
proprietary exception to preemption
was intentional and thus that such
conduct can be preempted under
Section 253(a). The Commission
therefore construes Section 253(c)’s
requirements, including the requirement
that compensation be ‘‘fair and
reasonable,’’ as applying equally to
charges imposed via contracts and other
arrangements between a state or local
government and a party engaged in
wireless facility deployment. This
interpretation is consistent with Section
253(a)’s reference to ‘‘State or local legal
requirement[s],’’ which the Commission
has consistently construed to include
such agreements. In light of the
foregoing, whatever the force of the
market participant doctrine in other
contexts, the Commission believes the
language, legislative history, and
purpose of Sections 253(a) and (c) are
incompatible with the application of
this doctrine in this context. The
Commission observes once more that
‘‘[o]ur conclusion that Congress
intended this language to be interpreted
broadly is reinforced by the scope of
section 253(d),’’ which ‘‘directs the
Commission to preempt any statute,
regulation, or legal requirement
permitted or imposed by a state or local
government if it contravenes sections
253(a) or (b). A more restrictive
interpretation of the term ‘other legal
requirements’ easily could permit state
and local restrictions on competition to
escape preemption based solely on the
way in which [State] action [is]
structured. The Commission does not
believe that Congress intended this
result.’’
37. Similarly, the Commission
interprets Section 332(c)(7)(B)(ii)’s
references to ‘‘any request[s] for
authorization to place, construct, or
modify personal wireless service
facilities’’ broadly, consistent with
Congressional intent. As described
below, the Commission finds that ‘‘any’’
is unqualifiedly broad, and that
‘‘request’’ encompasses anything
required to secure all authorizations
necessary for the deployment of
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
personal wireless services
infrastructure. In particular, the
Commission finds that Section 332(c)(7)
includes authorizations relating to
access to a ROW, including but not
limited to the ‘‘place[ment],
construct[ion], or modif[ication]’’ of
facilities on government-owned
property, for the purpose of providing
‘‘personal wireless service.’’ The
Commission observes that this result,
too, is consistent with Commission
precedent, which involved a contract
that provided exclusive access to a
ROW. As but one example, to have
limited that holding to exclude
government-owned property within the
ROW even if the carrier needed access
to that property would have the effect of
diluting or completely defeating the
purpose of Section 332(c)(7).
38. Second, and in the alternative,
even if Section 253(a) and Section
332(c)(7) were to permit leeway for
states and localities acting in their
proprietary role, the examples in the
record would be excepted because they
involve states and localities fulfilling
regulatory objectives. In the proprietary
context, ‘‘a State acts as a ‘market
participant with no interest in setting
policy.’ ’’ The Commission contrasts
state and local governments’ purely
proprietary actions with states and
localities acting with respect to
managing or controlling access to
property within public ROW, or to
decisions about where facilities that will
provide personal wireless service to the
public may be sited. As several
commenters point out, courts have
recognized that states and localities
‘‘hold the public streets and sidewalks
in trust for the public’’ and ‘‘manage
public ROW in their regulatory
capacities.’’ These decisions could be
based on a number of regulatory
objectives, such as aesthetics or public
safety and welfare, some of which, as
the Commission notes elsewhere, would
fall within the preemption scheme
envisioned by Congress. In these
situations, the State or locality’s role
seems to be indistinguishable from its
function and objectives as a regulator.
To the extent that there is some
distinction, the temptation to blend the
two roles for purposes of insulating
conduct from federal preemption cannot
be underestimated in light of the
overarching statutory objective that
telecommunications service and
personal wireless services be deployed
without material impediments.
39. The Commission believes that
Section 253(c) is properly construed to
suggest that Congress did not intend to
permit states and localities to rely on
their ownership of property within a
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
ROW as a pretext to advance regulatory
objectives that prohibit or have the
effect of prohibiting the provision of
covered services, and thus that such
conduct is preempted. The
Commission’s interpretations here are
intended to facilitate the
implementation of the scheme Congress
intended and to provide greater
regulatory certainty to states,
municipalities, and regulated parties
about what conduct is preempted under
Section 253(a). Should factual questions
arise about whether a state or locality is
engaged in such behavior, Section
253(d) affords state and local
governments and private parties an
avenue for specific preemption
challenges.
E. Responses to Challenges to the
Commission’s Interpretive Authority
and Other Arguments
40. The Commission rejects claims
that it lacks authority to issue
authoritative interpretations of Sections
253 and 332(c)(7) in this Declaratory
Ruling. The Commission acts here
pursuant to its broad authority to
interpret key provisions of the
Communications Act, consistent with
the Commission’s exercise of that
interpretive authority in the past. In this
instance, the Commission finds that
issuing a Declaratory Ruling is
necessary to remove what the record
reveals is substantial uncertainty and to
reduce the number and complexity of
legal controversies regarding certain fee
and non-fee state and local legal
requirements in connection with Small
Wireless Facility infrastructure. The
Commission thus exercise its authority
in this Declaratory Ruling to interpret
Section 253 and Section 332(c)(7) and
explain how those provisions apply in
the specific scenarios at issue here.
41. Nothing in Sections 253 or
332(c)(7) purports to limit the exercise
of the Commission’s general interpretive
authority. Congress’s inclusion of
preemption provisions in Section 253(d)
and Section 332(c)(7)(B)(v) does not
limit the Commission’s ability pursuant
to other sections of the Act to construe
and provide its authoritative
interpretation as to the meaning of those
provisions. Any preemption under
Section 253 and/or Section 332(c)(7)(B)
that subsequently occurs will proceed in
accordance with the enforcement
mechanisms available in each context.
But whatever enforcement mechanisms
may be available to preempt specific
state and local requirements, nothing in
Section 253 or Section 332(c)(7)
prevents the Commission from declaring
that a category of state or local laws is
inconsistent with Section 253(a) or
PO 00000
Frm 00059
Fmt 4700
Sfmt 4700
51873
Section 332(c)(7)(B)(i)(II) because it
prohibits or has the effect of prohibiting
the relevant covered service.
42. The Commission’s interpretations
of Sections 253 and Section 332(c)(7)
are likewise not at odds with the Tenth
Amendment and constitutional
precedent, as some commenters
contend. In particular, the
Commission’s interpretations do not
directly ‘‘compel the states to
administer federal regulatory programs
or pass legislation.’’ The outcome of
violations of Section 253(a) or Section
332(c)(7)(B) of the Act are no more than
a consequence of ‘‘the limits Congress
already imposed on State and local
governments’’ through its enactment of
Section 332(c)(7).
43. The Commission also reject the
suggestion that the limits Section 253
places on state and local rights-of-way
fees and management will
unconstitutionally interfere with the
relationship between a state and its
political subdivisions. As relevant to its
interpretations here, it is not clear, at
first blush, that such concerns would be
implicated. Because state and local legal
requirements can be written and
structured in myriad ways, and
challenges to such state or local
activities could be framed in broad or
narrow terms, the Commission declines
to resolve such questions here, divorced
from any specific context.
II. Third Report and Order
44. In this Third Report and Order,
the Commission addresses the
application of shot clocks to state and
local review of wireless infrastructure
deployments. The Commission does so
by taking action in three main areas.
First, the Commission adopts a new set
of shot clocks tailored to support the
deployment Small Wireless Facilities.
Second, the Commission adopts a
specific remedy that applies to
violations of these new Small Wireless
Facility shot clocks, which the
Commission expects will operate to
significantly reduce the need for
litigation over missed shot clocks.
Third, the Commission clarifies a
number of issues that are relevant to all
of the FCC’s shot clocks, including the
types of authorizations subject to these
time periods.
A. New Shot Clocks for Small Wireless
Facility Deployments
45. In 2009, the Commission
concluded that it should use shot clocks
to define a presumptive ‘‘reasonable
period of time’’ beyond which state or
local inaction on wireless infrastructure
siting applications would constitute a
‘‘failure to act’’ within the meaning of
E:\FR\FM\15OCR1.SGM
15OCR1
51874
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
Section 332. The Commission adopted a
90-day clock for reviewing collocation
applications and a 150-day clock for
reviewing siting applications other than
collocations. The record here suggests
that the two existing Section 332 shot
clocks have increased the efficiency of
deploying wireless infrastructure. Many
localities already process wireless siting
applications in less time than required
by those shot clocks and a number of
states have enacted laws requiring that
collocation applications be processed in
60 days or less. Some siting agencies
acknowledge that they have worked to
gain efficiencies in processing siting
applications and welcome the addition
of new shot clocks tailored to the
deployment of small scale facilities.
Given siting agencies’ increased
experience with existing shot clocks, the
greater need for rapid siting of Small
Wireless Facilities nationwide, and the
lower burden siting of these facilities
places on siting agencies in many cases,
the Commission takes this opportunity
to update its approach to speed the
deployment of Small Wireless Facilities.
khammond on DSK30JT082PROD with RULES
1. Two New Section 332 Shot Clocks for
Deployment of Small Wireless Facilities
46. In this section, the Commission
adopts two new Section 332 shot clocks
for Small Wireless Facilities—60 days
for review of an application for
collocation of Small Wireless Facilities
using a preexisting structure and 90
days for review of an application for
attachment of Small Wireless Facilities
using a new structure. These new
Section 332 shot clocks carefully
balance the well-established authority
that states and local authorities have
over review of wireless siting
applications with the requirements of
Section 332(c)(7)(ii) to exercise that
authority ‘‘within a reasonable period of
time . . . taking into account the nature
and scope of the request.’’ Further, the
Commission’s decision is consistent
with the BDAC’s Model Code for
Municipalities’ recommended
timeframes, which utilize this same 60day and 90-day framework for
collocation of Small Wireless Facilities
and new structures and are similar to
shot clocks enacted in state level small
cell bills and the real world experience
of many municipalities which further
supports the reasonableness of its
approach. The Commission’s actions
will modernize the framework for
wireless facility siting by taking into
consideration that states and localities
should be able to address the siting of
Small Wireless Facilities in a more
expedited review period than needed
for larger facilities.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
47. The Commission finds compelling
reasons to establish a new
presumptively reasonable Section 332
shot clock of 60 days for collocations of
Small Wireless Facilities on existing
structures. The record demonstrates the
need for, and reasonableness of,
expediting the siting review of these
collocations. Notwithstanding the
implementation of the current shot
clocks, more streamlined procedures are
both reasonable and necessary to
provide greater predictability for siting
applications nationwide for the
deployment of Small Wireless Facilities.
The two current Section 332 shot clocks
do not reflect the evolution of the
application review process and
evidence that localities can complete
reviews more quickly than was the case
when the existing Section 332 shot
clocks were adopted nine years ago.
Since 2009, localities have gained
significant experience processing
wireless siting applications. Indeed,
many localities already process wireless
siting applications in less than the
required time and several jurisdictions
require by law that collocation
applications be processed in 60 days or
less. With the passage of time, siting
agencies have become more efficient in
processing siting applications. These
facts demonstrate that a shorter, 60-day
shot clock for processing collocation
applications for Small Wireless
Facilities is reasonable.
48. As the Commission found in 2009,
collocation applications are generally
easier to process than new construction
because the community impact is likely
to be smaller. In particular, the addition
of an antenna to an existing tower or
other structure is unlikely to have a
significant visual impact on the
community. The size of Small Wireless
Facilities poses little or no risk of
adverse effects on the environment or
historic preservation. Indeed, many
jurisdictions do not require public
hearings for approval of such
attachments, underscoring their belief
that such attachments do not implicate
complex issues requiring a more
searching review.
49. Further, the Commission finds no
reason to believe that applying a 60-day
time frame for Small Wireless Facility
collocations under Section 332 creates
confusion with collocations that fall
within the scope of ‘‘eligible facilities
requests’’ under Section 6409 of the
Spectrum Act, which are also subject to
a 60-day review. The type of facilities at
issue here are distinctly different and
the definition of a Small Wireless
Facility is clear. Further, siting
authorities are required to process
Section 6409 applications involving the
PO 00000
Frm 00060
Fmt 4700
Sfmt 4700
swap out of certain equipment in 60
days, and the Commission sees no
meaningful difference in processing
these applications than processing
Section 332 collocation applications in
60 days. There is no reason to apply
different time periods (60 vs. 90 days)
to what is essentially the same review:
Modification of an existing structure to
accommodate new equipment. Finally,
adopting a 60-day shot clock will
encourage service providers to collocate
rather than opting to build new siting
structures which has numerous
advantages.
50. For similar reasons, the
Commission also finds it reasonable to
establish a new 90-day Section 332 shot
clock for new construction of Small
Wireless Facilities. Ninety days is a
presumptively reasonable period of time
for localities to review such siting
applications. Small Wireless Facilities
have far less visual and other impact
than the facilities the Commission
considered in 2009 and should
accordingly require less time to review.
Indeed, some state and local
governments have already adopted 60day maximum reasonable periods of
time for review of all small cell siting
applications, and, even in the absence of
such maximum requirements, several
are already reviewing and approving
small-cell siting applications within 60
days or less after filing. Numerous
industry commenters advocated a 90day shot clock for all non-collocation
deployments. Based on this record, the
Commission finds review of an
application to deploy a Small Wireless
Facility using a new structure warrants
more review time than a mere
collocation, but less than the
construction of a macro tower. For the
reasons explained below, the
Commission also specifies today a
provision that will initially reset these
two new shot clocks in the event that a
locality receives a materially incomplete
application.
2. Batched Applications for Small
Wireless Facilities
51. Given the way in which Small
Wireless Facilities are likely to be
deployed, in large numbers as part of a
system meant to cover a particular area,
the Commission anticipates that some
applicants will submit ‘‘batched’’
applications: Multiple separate
applications filed at the same time, each
for one or more sites or a single
application covering multiple sites. The
Commission sought comment on
whether batched applications should be
subject to either longer or shorter shot
clocks than would apply if each
component of the batch were submitted
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
separately. The Commission sees no
reason why the shot clocks for batched
applications to deploy Small Wireless
Facilities should be longer than those
that apply to individual applications
because, in many cases, the batching of
such applications has advantages in
terms of administrative efficiency that
could actually make review easier. The
Commission’s decision flows from its
current Section 332 shot clock policy.
Under the two existing Section 332 shot
clocks, if an applicant files multiple
siting applications on the same day for
the same type of facilities, each
application is subject to the same
number of review days by the siting
agency. These multiple siting
applications are equivalent to a batched
application and therefore the shot
clocks for batching should follow the
same rules as if the applications were
filed separately. Accordingly, when
applications to deploy Small Wireless
Facilities are filed in batches, the shot
clock that applies to the batch is the
same one that would apply had the
applicant submitted individual
applications. Should an applicant file a
single application for a batch that
includes both collocated and new
construction of Small Wireless
Facilities, the longer 90-day shot clock
will apply, to ensure that the siting
authority has adequate time to review
the new construction sites.
52. The Commission recognizes the
concerns raised by parties arguing for a
longer time period for at least some
batched applications but concludes that
a separate rule is not necessary to
address these concerns. Under the
Commission’s approach, in
extraordinary cases, a siting authority,
as discussed below, can rebut the
presumption of reasonableness of the
applicable shot clock period where a
batch application causes legitimate
overload on the siting authority’s
resources. Thus, contrary to some
localities’ arguments, the Commission’s
approach provides for a certain degree
of flexibility to account for exceptional
circumstances. In addition, consistent
with, and for the same reasons as the
Commission’s conclusion below that
Section 332 does not permit states and
localities to prohibit applicants from
requesting multiple types of approvals
simultaneously, the Commission finds
that Section 332(c)(7)(B)(ii) similarly
does not allow states and localities to
refuse to accept batches of applications
to deploy Small Wireless Facilities.
B. New Remedy for Violations of the
Small Wireless Facilities Shot Clocks
53. In adopting these new shot clocks
for Small Wireless Facility applications,
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
the Commission also provides an
additional remedy that it expects will
substantially reduce the likelihood that
applicants will need to pursue
additional and costly relief in court at
the expiration of those time periods.
54. The Commission determines that
the failure of a state or local government
to issue a decision on a Small Wireless
Facility siting application within the
presumptively reasonable time periods
above will constitute a ‘‘failure to act’’
within the meaning of Section
332(c)(7)(B)(v). Therefore, a provider is,
at a minimum, entitled to the same
process and remedies available for a
failure to act within the new Small
Wireless Facility shot clocks as they
have been under the FCC’s 2009 shot
clocks. But the Commission also adds
an additional remedy for the new Small
Wireless Facility shot clocks.
55. State or local inaction by the end
of the Small Wireless Facility shot clock
will function not only as a Section
332(c)(7)(B)(v) failure to act but also
amount to a presumptive prohibition on
the provision of personal wireless
services within the meaning of Section
332(c)(7)(B)(i)(II). Accordingly, the
Commission would expect the state or
local government to issue all necessary
permits without further delay. In cases
where such action is not taken, the
Commission assumes, for the reasons
discussed below, that the applicant
would have a straightforward case for
obtaining expedited relief in court.
56. As discussed in the Declaratory
Ruling, a regulation under Section
332(c)(7)(B)(i)(II) constitutes an effective
prohibition if it materially limits or
inhibits the ability of any competitor or
potential competitor to compete in a fair
and balanced legal and regulatory
environment. Missing shot clock
deadlines would thus presumptively
have the effect of unlawfully prohibiting
service in that such failure to act can be
expected to materially limit or inhibit
the introduction of new services or the
improvement of existing services. Thus,
when a siting authority misses the
applicable shot clock deadline, the
applicant may commence suit in a court
of competent jurisdiction alleging a
violation of Section 332(c)(7)(B)(i)(II), in
addition to a violation of Section
332(c)(7)(B)(ii), as discussed above. The
siting authority then will have an
opportunity to rebut the presumption of
effective prohibition by demonstrating
that the failure to act was reasonable
under the circumstances and, therefore,
did not materially limit or inhibit the
applicant from introducing new services
or improving existing services.
57. Given the seriousness of failure to
act within a reasonable period of time,
PO 00000
Frm 00061
Fmt 4700
Sfmt 4700
51875
the Commission expects, as noted
above, siting authorities to issue without
any further delay all necessary
authorizations when notified by the
applicant that they have missed the shot
clock deadline, absent extraordinary
circumstances. Where the siting
authority nevertheless fails to issue all
necessary authorizations and litigation
is commenced based on violations of
Sections 332(c)(7)(B)(i)(II) and/or
332(c)(7)(B)(ii), the Commission expects
that applicants and other aggrieved
parties will likely pursue equitable
judicial remedies. Given the relatively
low burden on state and local
authorities of simply acting—one way or
the other—within the Small Wireless
Facility shot clocks, the Commission
thinks that applicants would have a
relatively low hurdle to clear in
establishing a right to expedited judicial
relief.
58. The Commission expects that
courts will typically find expedited and
permanent injunctive relief warranted
for violations of Sections
332(c)(7)(B)(i)(II) and 332(c)(7)(B)(ii) of
the Act when addressing the
circumstances discussed in this Order.
The Commission believes that this
approach is sensible because guarding
against barriers to the deployment of
personal wireless facilities not only
advances the goal of Section 332(c)(7)(B)
but also policies set out elsewhere in the
Communications Act and 1996 Act, as
the Commission recently has recognized
in the case of Small Wireless Facilities.
This is so whether or not these barriers
stem from bad faith. Nor does the
Commission anticipate that there would
be unresolved issues implicating the
siting authority’s expertise and therefore
requiring remand in most instances.
59. The guidance provided here
should reduce the need for, and
complexity of, case-by-case litigation
and reduce the likelihood of vastly
different timing across various
jurisdictions for the same type of
deployment. This clarification, along
with the other actions the Commission
takes in this Third Report and Order,
should streamline the courts’ decisionmaking process and reduce the
possibility of inconsistent rulings.
Consequently, the Commission believes
that its approach helps facilitate courts’
ability to ‘‘hear and decide such
[lawsuits] on an expedited basis,’’ as the
statute requires.
60. The Commission’s updated
interpretation of Section 332(c)(7) for
Small Wireless Facilities effectively
balances the interest of wireless service
providers to have siting applications
granted in a timely and streamlined
manner and the interest of localities to
E:\FR\FM\15OCR1.SGM
15OCR1
51876
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
protect public safety and welfare and
preserve their authority over the
permitting process. The Commission’s
specialized deployment categories, in
conjunction with the acknowledgement
that in rare instances, it may
legitimately take longer to act, recognize
that the siting process is complex and
handled in many different ways under
various states’ and localities’ longestablished codes. Further, the
Commission’s approach tempers
localities’ concerns about the
inflexibility of a deemed granted
proposal because the new remedy the
Commission adopts here accounts for
the breadth of potentially unforeseen
circumstances that individual localities
may face and the possibility that
additional review time may be needed
in truly exceptional circumstances. The
Commission further finds that its
interpretive framework will not be
unduly burdensome on localities
because a number of states have already
adopted even more stringent deemed
granted remedies
khammond on DSK30JT082PROD with RULES
C. Clarification of Issues Related to All
Section 332 Shot Clocks
1. Authorizations Subject to the
‘‘Reasonable Period of Time’’ Provision
of Section 332(c)(7)(B)(ii)
61. Section 332(c)(7)(B)(ii) requires
state and local governments to act
‘‘within a reasonable period of time’’ on
‘‘any request for authorization to place,
construct, or modify personal wireless
service facilities.’’ The Commission has
not addressed the specific types of
authorizations subject to this
requirement. After carefully considering
these arguments, the Commission finds
that ‘‘any request for authorization to
place, construct, or modify personal
wireless service facilities’’ under
Section 332(c)(7)(B)(ii) means all
authorizations necessary for the
deployment of personal wireless
services infrastructure. This
interpretation finds support in the
record and is consistent with the courts’
interpretation of this provision and the
text and purpose of the Act.
62. The Commission’s interpretation
remains faithful to the purpose of
Section 332(c)(7) to balance Congress’s
competing desires to preserve the
traditional role of state and local
governments in regulating land use and
zoning, while encouraging the rapid
development of new
telecommunications technologies.
Under the Commission’s interpretation,
states and localities retain their
authority over personal wireless
facilities deployment. At the same time,
deployment will be kept on track by
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
ensuring that the entire approval
process necessary for deployment is
completed within a reasonable period of
time, as defined by the shot clocks
addressed in this Third Report and
Order.
2. Codification of Section 332 Shot
Clocks
63. In addition to establishing two
new Section 332 shot clocks for Small
Wireless Facilities, the Commission
takes this opportunity to codify its two
existing Section 332 shot clocks for
siting applications that do not involve
Small Wireless Facilities. In 2009 the
Commission found that 90 days is a
reasonable time frame for processing
collocation applications and 150 days is
a reasonable time frame to process
applications other than collocations.
Since these Section 332 shot clocks
were adopted as part of a declaratory
ruling, they were not codified in the
Commission’s rules. The Commission
sought comment on whether to modify
these shot clocks. The Commission
finds no need to modify them here and
will continue to use these shot clocks
for processing Section 332 siting
applications that do not involve Small
Wireless Facilities. The Commission
does, though, codify these two existing
shot clocks in its rules alongside the two
newly-adopted shot clocks so that all
interested parties can readily find the
shot clock requirements in one place.
3. Collocations on Structures Not
Previously Zoned for Wireless Use
64. The Commission takes this
opportunity to clarify that for purposes
of the Section 332 shot clocks,
attachment of facilities to existing
structures constitutes collocation,
regardless of whether the structure or
the location has previously been zoned
for wireless facilities. As the
Commission stated in 2009, ‘‘an
application is a request for collocation
if it does not involve a ‘substantial
increase in the size of a tower’ as
defined in the Nationwide
Programmatic Agreement (NPA) for the
Collocation of Wireless Antennas.’’ The
definition of ‘‘[c]ollocation’’ in the NPA
provides for the ‘‘mounting or
installation of an antenna on an existing
tower, building or structure for the
purpose of transmitting and/or receiving
radio frequency signals for
communications purposes, whether or
not there is an existing antenna on the
structure.’’ The NPA’s definition of
collocation explicitly encompasses
collocations on structures and buildings
that have not yet been zoned for
wireless use. To interpret the NPA any
other way would be unduly narrow and
PO 00000
Frm 00062
Fmt 4700
Sfmt 4700
there is no persuasive reason to accept
a narrower interpretation. This is
particularly true given that the NPA
definition of collocation stands in direct
contrast with the definition of
collocation in the Spectrum Act,
pursuant to which facilities only fall
within the scope of an ‘‘eligible facilities
request’’ if they are attached to towers
or base stations that have already been
zoned for wireless use.
4. When Shot Clocks Start and
Incomplete Applications
65. In 2014 the Commission clarified
that a shot clock begins to run when an
application is first submitted, not when
the application is deemed complete.
The clock can be paused, however, if
the locality notifies the applicant within
30 days that the application is
incomplete. The locality may pause the
clock again if it provides written notice
within 10 days that the supplemental
submission did not provide the
information identified in the original
notice delineating missing information.
The Commission sought comment on
these determinations.
66. Based on the record, the
Commission finds no cause to alter the
Commission’s prior determinations and
now codifies them in its rules. Codified
rules, easily accessible to applicants and
localities alike, should provide helpful
clarity. The complaints by states and
localities about the sufficiency of some
of the applications they receive are
adequately addressed by the
Commission’s current policy, which
preserves the states’ and localities’
ability to pause review when they find
an application to be incomplete. The
Commission does not find it necessary
at this point to shorten the 30-day initial
review period for completeness because,
as was the case when this review period
was adopted in the 2009, it remains
consistent with review periods for
completeness under existing state
wireless infrastructure deployment
statutes and still ‘‘gives State and local
governments sufficient time for
reviewing applications for
completeness, while protecting
applicants from a last minute decision
that an application should be denied as
incomplete.’’
67. However, for applications to
deploy Small Wireless Facilities, the
Commission implements a modified
tolling system designed to help ensure
that providers are submitting complete
applications on day one. This step
accounts for the fact that the shot clocks
applicable to such applications are
shorter than those established in 2009
and, because of which, there may
instances where the prevailing tolling
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
rules would further shorten the shot
clocks to such an extent that it might be
impossible for siting authorities to act
on the application. For Small Wireless
Facilities applications, the siting
authority has 10 days from the
submission of the application to
determine whether the application is
incomplete. The shot clock then resets
once the applicant submits the
supplemental information requested by
the siting authority. Thus, for example,
for an application to collocate Small
Wireless Facilities, once the applicant
submits the supplemental information
in response to a siting authority’s timely
request, the shot clock resets, effectively
giving the siting authority an additional
60 days to act on the Small Wireless
Facilities collocation application. For
subsequent determinations of
incompleteness, the tolling rules that
apply to non-Small Wireless Facilities
would apply—that is, the shot clock
would toll if the siting authority
provides written notice within 10 days
that the supplemental submission did
not provide the information identified
in the original notice delineating
missing information.
68. As noted above, multiple
authorizations may be required before a
deployment is allowed to move forward.
For instance, a locality may require a
zoning permit, a building permit, an
electrical permit, a road closure permit,
and an architectural or engineering
permit for an applicant to place,
construct, or modify its proposed
personal wireless service facilities. All
of these permits are subject to Section
332’s requirement to act within a
reasonable period of time, and thus all
are subject to the shot clocks the
Commission adopts or codifies here.
69. The Commission also finds that
mandatory pre-application procedures
and requirements do not toll the shot
clocks. The Commission concludes that
the ability to toll a shot clock when an
application is found incomplete or by
mutual agreement by the applicant and
the siting authority should be adequate
to address these concerns. Much like a
requirement to file applications one
after another, requiring pre-application
review would allow for a complete
circumvention of the shot clocks by
significantly delaying their start date.
An application is not ruled on within ‘‘a
reasonable period of time after the
request is duly filed’’ if the state or
locality takes the full ordinary review
period after having delayed the filing in
the first instance due to required preapplication review. Indeed, requiring a
pre-application review before an
application may be filed is similar to
imposing a moratorium, which the
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
Commission has made clear does not
stop the shot clocks from running.
Therefore, the Commission concludes
that if an applicant proffers an
application, but a state or locality
refuses to accept it until a preapplication review has been completed,
the shot clock begins to run when the
application is proffered.
70. That said, the Commission
encourages voluntary pre-application
discussions, which may well be useful
to both parties. The record indicates that
such meetings can clarify key aspects of
the application review process,
especially with respect to large
submissions or applicants new to a
particular locality’s processes and may
speed the pace of review. To the extent
that an applicant voluntarily engages in
a pre-application review to smooth the
way for its filing, the shot clock will
begin when an application is filed,
presumably after the pre-application
review has concluded.
71. The Commission also reiterates
that the remedies granted under Section
332(c)(7)(B)(v) are independent of, and
in addition to, any remedies that may be
available under state or local law. Thus,
where a state or locality has established
its own shot clocks, an applicant may
pursue any remedies granted under state
or local law in cases where the siting
authority fails to act within those shot
clocks. However, the applicant must
wait until the Commission shot clock
period has expired to bring suit for a
‘‘failure to act’’ under Section
332(c)(7)(B)(v).
III. Procedural Matters
A. Final Regulatory Flexibility Analysis
72. As required by the Regulatory
Flexibility Act of 1980, as amended
(RFA), an Initial Regulatory Flexibility
Analysis (IRFA) was incorporated in the
Notice of Proposed Rulemaking
(NPRM), released in April 2017 (82 FR
22453, May 16, 2017). The Commission
sought written public comment on the
proposals in the NPRM, including
comment on the IRFA. The comments
received are addressed below in Section
2. This present Final Regulatory
Flexibility Analysis (FRFA) conforms to
the RFA.
1. Need for and Objectives of the Rules
73. In the Third Report and Order, the
Commission continues its efforts to
promote the timely buildout of wireless
infrastructure across the country by
eliminating regulatory impediments that
unnecessarily delay bringing personal
wireless services to consumers. The
record shows that lengthy delays in
approving siting applications by siting
PO 00000
Frm 00063
Fmt 4700
Sfmt 4700
51877
agencies has been a persistent problem.
With this in mind, the Third Report and
Order establishes and codifies specific
rules concerning the amount of time
siting agencies may take to review and
approve certain categories of wireless
infrastructure siting applications. More
specifically, the Commission addresses
its Section 332 shot clock rules for
infrastructure applications which will
be presumed reasonable under the
Communications Act. As an initial
matter, the Commission establishes two
new shot clocks for Small Wireless
Facilities applications. For collocation
of Small Wireless Facilities on
preexisting structures, the Commission
adopts a 60-day shot clock which
applies to both individual and batched
applications. For applications
associated with Small Wireless
Facilities new construction the
Commission adopts a 90-day shot clock
for both individual and batched
applications. The Commission also
codifies two existing Section 332 shot
clocks for all other Non-Small Wireless
Facilities that were established in 2009
without codification. These existing
shot clocks require 90-days for
processing of all other Non-Small
Wireless Facilities collocation
applications, and 150-days for
processing of all other Non-Small
Wireless Facilities applications other
than collocations.
74. The Third Report and Order
addresses other issues related to both
the existing and new shot clocks. In
particular the Commission addresses the
specific types of authorizations subject
to the ‘‘Reasonable Period of Time’’
provisions of Section 332(c)(7)(B)(ii),
finding that ‘‘any request for
authorization to place, construct, or
modify personal wireless service
facilities’’ under Section 332(c)(7)(B)(ii)
means all authorizations a locality may
require, and to all aspects of and steps
in the siting process, including license
or franchise agreements to access ROW,
building permits, public notices and
meetings, lease negotiations, electric
permits, road closure permits, aesthetic
approvals, and other authorizations
needed for deployment of personal
wireless services infrastructure. The
Commission also addresses collocation
on structures not previously zoned for
wireless use, when the four Section 332
shot clocks begin to run, the impact of
incomplete applications on the
Commission’s Section 332 shot clocks,
and how state imposed shot clocks
remedies effect the Commission’s
Section 332 shot clocks remedies.
75. The Commission discusses the
appropriate judicial remedy that
applicants may pursue in cases where a
E:\FR\FM\15OCR1.SGM
15OCR1
51878
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
khammond on DSK30JT082PROD with RULES
siting authority fails to act within the
applicable shot clock period. In those
situations, applicants may commence an
action in a court of competent
jurisdiction alleging a violation of
Section 332(c)(7)(B)(i)(II) and seek
injunctive relief granting the
application. Notwithstanding the
availability of a judicial remedy if a shot
clock deadline is missed, the
Commission recognizes that the Section
332 time frames might not be met in
exceptional circumstances and has
refined its interpretation of the
circumstances when a period of time
longer than the relevant shot clock
would nonetheless be a reasonable
period of time for action by a siting
agency. In addition, a siting authority
that is subject to a court action for
missing an applicable shot clock
deadline has the opportunity to
demonstrate that the failure to act was
reasonable under the circumstances
and, therefore, did not materially limit
or inhibit the applicant from
introducing new services or improving
existing services thereby rebutting the
effective prohibition presumption.
76. The rules adopted in the Third
Report and Order will accelerate the
deployment of wireless infrastructure
needed for the mobile wireless services
of the future, while preserving the
fundamental role of localities in this
process. Under the Commission’s new
rules, localities will maintain control
over the placement, construction and
modification of personal wireless
facilities, while at the same time the
Commission’s new process will
streamline the review of wireless siting
applications.
2. Summary of Significant Issues Raised
by Public Comments in Response to the
IRFA
77. Only one party—the Smart Cities
and Special Districts Coalition—filed
comments specifically addressing the
rules and policies proposed in the IRFA.
They argue that any shortening or
alteration of the Commission’s existing
shot clocks or the adoption of a deemed
granted remedy will adversely affect
small local governments, special
districts, property owners, small
developers, and others by placing their
siting applications behind wireless
provider siting applications.
Subsequently, NATOA filed comments
concerning the draft FRFA. NATOA
argues that the new shot clocks impose
burdens on local governments and
particularly those with limited
resources. NATOA asserts that the new
shot clocks will spur more deployment
applications than localities currently
process.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
78. These arguments, however, fail to
acknowledge that Section 332 shot
clocks have been in place for years and
reflect Congressional intent as seen in
the statutory language of Section 332.
The record in this proceeding
demonstrates the need for, and
reasonableness of, expediting the siting
review of certain facility deployments.
More streamlined procedures are both
reasonable and necessary to provide
greater predictability. The current shot
clocks do not reflect the evolution of the
application review process and
evidence that localities can complete
reviews more quickly than was the case
when the original shot clocks were
adopted nine years ago. Localities have
gained significant experience processing
wireless siting applications and several
jurisdictions already have in place laws
that require applications to be processed
in less time than the Commission’s new
shot clocks. With the passage of time,
sitting agencies have become more
efficient in processing siting
applications and this, in turn, should
reduce any economic burden the
Commission’s new shot clock
provisions have on them.
79. The Commission has carefully
considered the impact of its new shot
clocks on siting authorities and has
established shot clocks that take into
consideration the nature and scope of
siting requests by establishing shot
clocks of different lengths of time that
depend on the nature of the siting
request at issue. The length of these shot
clocks is based in part on the need to
ensure that local governments have
ample time to take any steps needed to
protect public safety and welfare and to
process other pending utility
applications. Since local siting
authorities have gained experience in
processing siting requests in an
expedited fashion, they should be able
to comply with the Commission’s new
shot clocks.
80. The Commission has taken into
consideration the concerns of the Smart
Cities and Special Districts Coalition
and NATOA. It has established shot
clocks that will not favor wireless
providers over other applicants with
pending siting applications. Further,
instead of adopting a deemed granted
remedy that would grant a siting
application when a shot clock lapses
without a decision on the merits, the
Commission provides guidance as to the
appropriate judicial remedy that
applicants may pursue and examples of
exceptional circumstance where a siting
authority may be justified in needing
additional time to review a siting
application then the applicable shot
clock allows. Under this approach, the
PO 00000
Frm 00064
Fmt 4700
Sfmt 4700
applicant may seek injunctive relief as
long as several minimum requirements
are met. The siting authority, however,
can rebut the presumptive
reasonableness of the applicable shot
clock under certain circumstances. The
circumstances under which a sitting
authority might have to do this will be
rare. Under this carefully crafted
approach, the interests of siting
applicants, siting authorities, and
citizens are protected.
3. Response to Comments by the Chief
Counsel for Advocacy of the Small
Business Administration
81. Pursuant to the Small Business
Jobs Act of 2010, which amended the
RFA, the Commission is required to
respond to any comments filed by the
Chief Counsel for Advocacy of the Small
Business Administration (SBA), and to
provide a detailed statement of any
change made to the proposed rules as a
result of those comments.
82. The Chief Counsel did not file any
comments in response to the proposed
rules in this proceeding.
4. Description and Estimate of the
Number of Small Entities to Which the
Rules Will Apply
83. The RFA directs agencies to
provide a description of, and where
feasible, an estimate of the number of
small entities that may be affected by
the rules adopted herein. The RFA
generally defines the term ‘‘small
entity’’ as having the same meaning as
the terms ‘‘small business,’’ ‘‘small
organization,’’ and ‘‘small governmental
jurisdiction.’’ In addition, the term
‘‘small business’’ has the same meaning
as the term ‘‘small business concern’’
under the Small Business Act. A ‘‘small
business concern’’ is one which: (1) Is
independently owned and operated; (2)
is not dominant in its field of operation;
and (3) satisfies any additional criteria
established by the SBA.
84. Small Businesses, Small
Organizations, Small Governmental
Jurisdictions. The Commission’s actions,
over time, may affect small entities that
are not easily categorized at present.
The Commission therefore describe
here, at the outset, three broad groups of
small entities that could be directly
affected herein. First, while there are
industry specific size standards for
small businesses that are used in the
regulatory flexibility analysis, according
to data from the SBA’s Office of
Advocacy, in general a small business is
an independent business having fewer
than 500 employees. These types of
small businesses represent 99.9 percent
of all businesses in the United States
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
which translates to 28.8 million
businesses.
85. Next, the type of small entity
described as a ‘‘small organization’’ is
generally ‘‘any not-for-profit enterprise
which is independently owned and
operated and is not dominant in its
field.’’ Nationwide, as of August 2016,
there were approximately 356,494 small
organizations based on registration and
tax data filed by nonprofits with the
Internal Revenue Service (IRS).
86. Finally, the small entity described
as a ‘‘small governmental jurisdiction’’
is defined generally as ‘‘governments of
cities, counties, towns, townships,
villages, school districts, or special
districts, with a population of less than
fifty thousand.’’ U.S. Census Bureau
data from the 2012 Census of
Governments indicate that there were
90,056 local governmental jurisdictions
consisting of general purpose
governments and special purpose
governments in the United States. Of
this number there were 37,132 General
purpose governments (county,
municipal and town or township) with
populations of less than 50,000 and
12,184 Special purpose governments
(independent school districts and
special districts) with populations of
less than 50,000. The 2012 U.S. Census
Bureau data for most types of
governments in the local government
category show that the majority of these
governments have populations of less
than 50,000. Based on this data the
Commission estimates that at least
49,316 local government jurisdictions
fall in the category of ‘‘small
governmental jurisdictions.’’
87. Wireless Telecommunications
Carriers (except Satellite). This industry
comprises establishments engaged in
operating and maintaining switching
and transmission facilities to provide
communications via the airwaves.
Establishments in this industry have
spectrum licenses and provide services
using that spectrum, such as cellular
services, paging services, wireless
internet access, and wireless video
services. The appropriate size standard
under SBA rules is that such a business
is small if it has 1,500 or fewer
employees. For this industry, U.S.
Census data for 2012 show that there
were 967 firms that operated for the
entire year. Of this total, 955 firms had
employment of 999 or fewer employees
and 12 had employment of 1,000
employees or more. Thus under this
category and the associated size
standard, the Commission estimates that
the majority of wireless
telecommunications carriers (except
satellite) are small entities.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
88. The Commission’s own data—
available in its Universal Licensing
System—indicate that, as of May 17,
2018, there are 264 Cellular licensees
that will be affected by the
Commission’s actions. The Commission
does not know how many of these
licensees are small, as the Commission
does not collect that information for
these types of entities. Similarly,
according to Commission data, 413
carriers reported that they were engaged
in the provision of wireless telephony,
including cellular service, Personal
Communications Service (PCS), and
Specialized Mobile Radio (SMR)
Telephony services. Of this total, an
estimated 261 have 1,500 or fewer
employees and 152 have more than
1,500 employees. Thus, using available
data, the Commission estimates that the
majority of wireless firms can be
considered small.
89. Personal Radio Services. Personal
radio services provide short-range, lowpower radio for personal
communications, radio signaling, and
business communications not provided
for in other services. Personal radio
services include services operating in
spectrum licensed under part 95 of the
Commission’s rules. These services
include Citizen Band Radio Service,
General Mobile Radio Service, Radio
Control Radio Service, Family Radio
Service, Wireless Medical Telemetry
Service, Medical Implant
Communications Service, Low Power
Radio Service, and Multi-Use Radio
Service. There are a variety of methods
used to license the spectrum in these
rule parts, from licensing by rule, to
conditioning operation on successful
completion of a required test, to sitebased licensing, to geographic area
licensing. All such entities in this
category are wireless, therefore the
Commission applies the definition of
Wireless Telecommunications Carriers
(except Satellite), pursuant to which the
SBA’s small entity size standard is
defined as those entities employing
1,500 or fewer persons. For this
industry, U.S. Census data for 2012
show that there were 967 firms that
operated for the entire year. Of this
total, 955 firms had employment of 999
or fewer employees and 12 had
employment of 1,000 employees or
more. Thus, under this category and the
associated size standard, the
Commission estimates that the majority
of firms can be considered small. The
Commission notes however that many
of the licensees in this category are
individuals and not small entities. In
addition, due to the mostly unlicensed
and shared nature of the spectrum
PO 00000
Frm 00065
Fmt 4700
Sfmt 4700
51879
utilized in many of these services, the
Commission lacks direct information
upon which to base an estimation of the
number of small entities that may be
affected by the Commission’s actions in
this proceeding.
90. Public Safety Radio Licensees.
Public Safety Radio Pool licensees as a
general matter, include police, fire, local
government, forestry conservation,
highway maintenance, and emergency
medical services. Because of the vast
array of public safety licensees, the
Commission has not developed a small
business size standard specifically
applicable to public safety licensees.
The closest applicable SBA category is
Wireless Telecommunications Carriers
(except Satellite) which encompasses
business entities engaged in
radiotelephone communications. The
appropriate size standard for this
category under SBA rules is that such a
business is small if it has 1,500 or fewer
employees. For this industry, U.S.
Census data for 2012 show that there
were 967 firms that operated for the
entire year. Of this total, 955 firms had
employment of 999 or fewer employees
and 12 had employment of 1,000
employees or more. Thus under this
category and the associated size
standard, the Commission estimates that
the majority of firms can be considered
small. With respect to local
governments, in particular, since many
governmental entities comprise the
licensees for these services, the
Commission includes under public
safety services the number of
government entities affected. According
to Commission records, there are a total
of approximately 133,870 licenses
within these services. There are 3,121
licenses in the 4.9 GHz band, based on
an FCC Universal Licensing System
search of March 29, 2017. The
Commission estimates that fewer than
2,442 public safety radio licensees hold
these licenses because certain entities
may have multiple licenses.
91. Private Land Mobile Radio
Licensees. Private land mobile radio
(PLMR) systems serve an essential role
in a vast range of industrial, business,
land transportation, and public safety
activities. These radios are used by
companies of all sizes operating in all
U.S. business categories. Because of the
vast array of PLMR users, the
Commission has not developed a small
business size standard specifically
applicable to PLMR users. The closest
applicable SBA category is Wireless
Telecommunications Carriers (except
Satellite) which encompasses business
entities engaged in radiotelephone
communications. The appropriate size
standard for this category under SBA
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
51880
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
rules is that such a business is small if
it has 1,500 or fewer employees. For this
industry, U.S. Census data for 2012
show that there were 967 firms that
operated for the entire year. Of this
total, 955 firms had employment of 999
or fewer employees and 12 had
employment of 1,000 employees or
more. Thus, under this category and the
associated size standard, the
Commission estimates that the majority
of PLMR Licensees are small entities.
92. According to the Commission’s
records, a total of approximately
400,622 licenses comprise PLMR users.
Of this number there are a total of 3,374
licenses in the frequencies range
173.225 MHz to 173.375 MHz, which is
the range affected by the Third Report
and Order. The Commission does not
require PLMR licensees to disclose
information about number of employees
and does not have information that
could be used to determine how many
PLMR licensees constitute small entities
under this definition. The Commission
however believes that a substantial
number of PLMR licensees may be small
entities despite the lack of specific
information.
93. Multiple Address Systems. Entities
using Multiple Address Systems (MAS)
spectrum, in general, fall into two
categories: (1) Those using the spectrum
for profit-based uses, and (2) those using
the spectrum for private internal uses.
With respect to the first category, Profitbased Spectrum use, the size standards
established by the Commission define
‘‘small entity’’ for MAS licensees as an
entity that has average annual gross
revenues of less than $15 million over
the three previous calendar years. A
‘‘Very small business’’ is defined as an
entity that, together with its affiliates,
has average annual gross revenues of not
more than $3 million over the preceding
three calendar years. The SBA has
approved these definitions. The
majority of MAS operators are licensed
in bands where the Commission has
implemented a geographic area
licensing approach that requires the use
of competitive bidding procedures to
resolve mutually exclusive applications.
94. The Commission’s licensing
database indicates that, as of April 16,
2010, there were a total of 11,653 sitebased MAS station authorizations. Of
these, 58 authorizations were associated
with common carrier service. In
addition, the Commission’s licensing
database indicates that, as of April 16,
2010, there were a total of 3,330
Economic Area market area MAS
authorizations. The Commission’s
licensing database also indicates that, as
of April 16, 2010, of the 11,653 total
MAS station authorizations, 10,773
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
authorizations were for private radio
service. In 2001, an auction for 5,104
MAS licenses in 176 EAs was
conducted. Seven winning bidders
claimed status as small or very small
businesses and won 611 licenses. In
2005, the Commission completed an
auction (Auction 59) of 4,226 MAS
licenses in the Fixed Microwave
Services from the 928/959 and 932/941
MHz bands. Twenty-six winning
bidders won a total of 2,323 licenses. Of
the 26 winning bidders in this auction,
five claimed small business status and
won 1,891 licenses.
95. With respect to the second
category, Internal Private Spectrum use
consists of entities that use, or seek to
use, MAS spectrum to accommodate
their own internal communications
needs, MAS serves an essential role in
a range of industrial, safety, business,
and land transportation activities. MAS
radios are used by companies of all
sizes, operating in virtually all U.S.
business categories, and by all types of
public safety entities. For the majority of
private internal users, the definition
developed by the SBA would be more
appropriate than the Commission’s
definition. The closest applicable
definition of a small entity is the
‘‘Wireless Telecommunications Carriers
(except Satellite)’’ definition under the
SBA rules. The appropriate size
standard under SBA rules is that such
a business is small if it has 1,500 or
fewer employees. For this category, U.S.
Census data for 2012 show that there
were 967 firms that operated for the
entire year. Of this total, 955 firms had
employment of 999 or fewer employees
and 12 had employment of 1,000
employees or more. Thus, under this
category and the associated small
business size standard, the Commission
estimates that the majority of firms that
may be affected by the Commission’s
action can be considered small.
96. Broadband Radio Service and
Educational Broadband Service.
Broadband Radio Service systems,
previously referred to as Multipoint
Distribution Service (MDS) and
Multichannel Multipoint Distribution
Service (MMDS) systems, and ‘‘wireless
cable,’’ transmit video programming to
subscribers and provide two-way highspeed data operations using the
microwave frequencies of the
Broadband Radio Service (BRS) and
Educational Broadband Service (EBS)
(previously referred to as the
Instructional Television Fixed Service
(ITFS)).
97. BRS—In connection with the 1996
BRS auction, the Commission
established a small business size
standard as an entity that had annual
PO 00000
Frm 00066
Fmt 4700
Sfmt 4700
average gross revenues of no more than
$40 million in the previous three
calendar years. The BRS auctions
resulted in 67 successful bidders
obtaining licensing opportunities for
493 Basic Trading Areas (BTAs). Of the
67 auction winners, 61 met the
definition of a small business. BRS also
includes licensees of stations authorized
prior to the auction. At this time, the
Commission estimates that of the 61
small business BRS auction winners, 48
remain small business licensees. In
addition to the 48 small businesses that
hold BTA authorizations, there are
approximately there are approximately
86 incumbent BRS licensees that are
considered small entities (18 incumbent
BRS licensees do not meet the small
business size standard). After adding the
number of small business auction
licensees to the number of incumbent
licensees not already counted, the
Commission finds that there are
currently approximately 133 BRS
licensees that are defined as small
businesses under either the SBA or the
Commission’s rules.
98. In 2009, the Commission
conducted Auction 86, the sale of 78
licenses in the BRS areas. The
Commission offered three levels of
bidding credits: (i) A bidder with
attributed average annual gross revenues
that exceed $15 million and do not
exceed $40 million for the preceding
three years (small business) received a
15 percent discount on its winning bid;
(ii) a bidder with attributed average
annual gross revenues that exceed $3
million and do not exceed $15 million
for the preceding three years (very small
business) received a 25 percent discount
on its winning bid; and (iii) a bidder
with attributed average annual gross
revenues that do not exceed $3 million
for the preceding three years
(entrepreneur) received a 35 percent
discount on its winning bid. Auction 86
concluded in 2009 with the sale of 61
licenses. Of the ten winning bidders,
two bidders that claimed small business
status won 4 licenses; one bidder that
claimed very small business status won
three licenses; and two bidders that
claimed entrepreneur status won six
licenses.
99. EBS—The Educational Broadband
Service has been included within the
broad economic census category and
SBA size standard for Wired
Telecommunications Carriers since
2007. Wired Telecommunications
Carriers are comprised of establishments
primarily engaged in operating and/or
providing access to transmission
facilities and infrastructure that they
own and/or lease for the transmission of
voice, data, text, sound, and video using
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
wired telecommunications networks.
Transmission facilities may be based on
a single technology or a combination of
technologies. The SBA’s small business
size standard for this category is all such
firms having 1,500 or fewer employees.
U.S. Census Bureau data for 2012 show
that there were 3,117 firms that operated
that year. Of this total, 3,083 operated
with fewer than 1,000 employees. Thus,
under this size standard, the majority of
firms in this industry can be considered
small. In addition to Census Bureau
data, the Commission’s Universal
Licensing System indicates that as of
October 2014, there are 2,206 active EBS
licenses. The Commission estimates that
of these 2,206 licenses, the majority are
held by non-profit educational
institutions and school districts, which
are by statute defined as small
businesses.
100. Location and Monitoring Service
(LMS). LMS systems use non-voice radio
techniques to determine the location
and status of mobile radio units. For
purposes of auctioning LMS licenses,
the Commission has defined a ‘‘small
business’’ as an entity that, together
with controlling interests and affiliates,
has average annual gross revenues for
the preceding three years not to exceed
$15 million. A ‘‘very small business’’ is
defined as an entity that, together with
controlling interests and affiliates, has
average annual gross revenues for the
preceding three years not to exceed $3
million. These definitions have been
approved by the SBA. An auction for
LMS licenses commenced on February
23, 1999 and closed on March 5, 1999.
Of the 528 licenses auctioned, 289
licenses were sold to four small
businesses.
101. Television Broadcasting. This
Economic Census category ‘‘comprises
establishments primarily engaged in
broadcasting images together with
sound.’’ These establishments operate
television broadcast studios and
facilities for the programming and
transmission of programs to the public.
These establishments also produce or
transmit visual programming to
affiliated broadcast television stations,
which in turn broadcast the programs to
the public on a predetermined schedule.
Programming may originate in their own
studio, from an affiliated network, or
from external sources. The SBA has
created the following small business
size standard for such businesses: Those
having $38.5 million or less in annual
receipts. The 2012 Economic Census
reports that 751 firms in this category
operated in that year. Of that number,
656 had annual receipts of $25,000,000
or less, 25 had annual receipts between
$25,000,000 and $49,999,999 and 70
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
had annual receipts of $50,000,000 or
more. Based on this data the
Commission therefore estimates that the
majority of commercial television
broadcasters are small entities under the
applicable SBA size standard.
102. The Commission has estimated
the number of licensed commercial
television stations to be 1,377. Of this
total, 1,258 stations (or about 91
percent) had revenues of $38.5 million
or less, according to Commission staff
review of the BIA Kelsey Inc. Media
Access Pro Television Database (BIA) on
November 16, 2017, and therefore these
licensees qualify as small entities under
the SBA definition. In addition, the
Commission has estimated the number
of licensed noncommercial educational
(NCE) television stations to be 384.
Notwithstanding, the Commission does
not compile and otherwise does not
have access to information on the
revenue of NCE stations that would
permit it to determine how many such
stations would qualify as small entities.
There are also 2,300 low power
television stations, including Class A
stations (LPTV) and 3,681 TV translator
stations. Given the nature of these
services, the Commission will presume
that all of these entities qualify as small
entities under the above SBA small
business size standard.
103. The Commission notes, however,
that in assessing whether a business
concern qualifies as ‘‘small’’ under the
above definition, business (control)
affiliations must be included. The
Commission estimates, therefore likely
overstates the number of small entities
that might be affected by its action,
because the revenue figure on which it
is based does not include or aggregate
revenues from affiliated companies. In
addition, another element of the
definition of ‘‘small business’’ requires
that an entity not be dominant in its
field of operation. The Commission is
unable at this time to define or quantify
the criteria that would establish whether
a specific television broadcast station is
dominant in its field of operation.
Accordingly, the estimate of small
businesses to which rules may apply
does not exclude any television station
from the definition of a small business
on this basis and is therefore possibly
over-inclusive. Also, as noted above, an
additional element of the definition of
‘‘small business’’ is that the entity must
be independently owned and operated.
The Commission notes that it is difficult
at times to assess these criteria in the
context of media entities and its
estimates of small businesses to which
they apply may be over-inclusive to this
extent.
PO 00000
Frm 00067
Fmt 4700
Sfmt 4700
51881
104. Radio Stations. This Economic
Census category ‘‘comprises
establishments primarily engaged in
broadcasting aural programs by radio to
the public. Programming may originate
in their own studio, from an affiliated
network, or from external sources.’’ The
SBA has established a small business
size standard for this category as firms
having $38.5 million or less in annual
receipts. Economic Census data for 2012
show that 2,849 radio station firms
operated during that year. Of that
number, 2,806 operated with annual
receipts of less than $25 million per
year, 17 with annual receipts between
$25 million and $49,999,999 million
and 26 with annual receipts of $50
million or more. Therefore, based on the
SBA’s size standard the majority of such
entities are small entities.
105. According to Commission staff
review of the BIA/Kelsey, LLC’s
Publications, Inc. Media Access Pro
Radio Database (BIA) as of January 2018,
about 11,261 (or about 99.92 percent) of
11,270 commercial radio stations had
revenues of $38.5 million or less and
thus qualify as small entities under the
SBA definition. The Commission has
estimated the number of licensed
commercial AM radio stations to be
4,633 stations and the number of
commercial FM radio stations to be
6,738, for a total number of 11,371. The
Commission notes, that the Commission
has also estimated the number of
licensed NCE radio stations to be 4,128.
Nevertheless, the Commission does not
compile and otherwise does not have
access to information on the revenue of
NCE stations that would permit it to
determine how many such stations
would qualify as small entities.
106. The Commission also notes, that
in assessing whether a business entity
qualifies as small under the above
definition, business control affiliations
must be included. The Commission’s
estimate therefore likely overstates the
number of small entities that might be
affected by its action, because the
revenue figure on which it is based does
not include or aggregate revenues from
affiliated companies. In addition, to be
determined a ‘‘small business,’’ an
entity may not be dominant in its field
of operation. The Commission further
notes, that it is difficult at times to
assess these criteria in the context of
media entities, and the estimate of small
businesses to which these rules may
apply does not exclude any radio station
from the definition of a small business
on these basis, thus the Commission’s
estimate of small businesses may
therefore be over-inclusive. Also, as
noted above, an additional element of
the definition of ‘‘small business’’ is that
E:\FR\FM\15OCR1.SGM
15OCR1
khammond on DSK30JT082PROD with RULES
51882
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
the entity must be independently owned
and operated. The Commission notes
that it is difficult at times to assess these
criteria in the context of media entities
and the estimates of small businesses to
which they apply may be over-inclusive
to this extent.
107. FM Translator Stations and Low
Power FM Stations. FM translators and
Low Power FM Stations are classified in
the category of Radio Stations and are
assigned the same NAICS Code as
licensees of radio stations. This U.S.
industry, Radio Stations, comprises
establishments primarily engaged in
broadcasting aural programs by radio to
the public. Programming may originate
in their own studio, from an affiliated
network, or from external sources. The
SBA has established a small business
size standard which consists of all radio
stations whose annual receipts are $38.5
million dollars or less. U.S. Census
Bureau data for 2012 indicate that 2,849
radio station firms operated during that
year. Of that number, 2,806 operated
with annual receipts of less than $25
million per year, 17 with annual
receipts between $25 million and
$49,999,999 million and 26 with annual
receipts of $50 million or more.
Therefore, based on the SBA’s size
standard, the Commission concludes
that the majority of FM Translator
Stations and Low Power FM Stations are
small.
108. Multichannel Video Distribution
and Data Service (MVDDS). MVDDS is
a terrestrial fixed microwave service
operating in the 12.2–12.7 GHz band.
The Commission adopted criteria for
defining three groups of small
businesses for purposes of determining
their eligibility for special provisions
such as bidding credits. It defined a very
small business as an entity with average
annual gross revenues not exceeding $3
million for the preceding three years; a
small business as an entity with average
annual gross revenues not exceeding
$15 million for the preceding three
years; and an entrepreneur as an entity
with average annual gross revenues not
exceeding $40 million for the preceding
three years. These definitions were
approved by the SBA. On January 27,
2004, the Commission completed an
auction of 214 MVDDS licenses
(Auction No. 53). In this auction, ten
winning bidders won a total of 192
MVDDS licenses. Eight of the ten
winning bidders claimed small business
status and won 144 of the licenses. The
Commission also held an auction of
MVDDS licenses on December 7, 2005
(Auction 63). Of the three winning
bidders who won 22 licenses, two
winning bidders, winning 21 of the
licenses, claimed small business status.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
109. Satellite Telecommunications.
This category comprises firms
‘‘primarily engaged in providing
telecommunications services to other
establishments in the
telecommunications and broadcasting
industries by forwarding and receiving
communications signals via a system of
satellites or reselling satellite
telecommunications.’’ Satellite
telecommunications service providers
include satellite and earth station
operators. The category has a small
business size standard of $32.5 million
or less in average annual receipts, under
SBA rules. For this category, U.S.
Census Bureau data for 2012 show that
there were a total of 333 firms that
operated for the entire year. Of this
total, 299 firms had annual receipts of
less than $25 million. Consequently, the
Commission estimates that the majority
of satellite telecommunications
providers are small entities.
110. All Other Telecommunications.
The ‘‘All Other Telecommunications’’
category is comprised of establishments
that are primarily engaged in providing
specialized telecommunications
services, such as satellite tracking,
communications telemetry, and radar
station operation. This industry also
includes establishments primarily
engaged in providing satellite terminal
stations and associated facilities
connected with one or more terrestrial
systems and capable of transmitting
telecommunications to, and receiving
telecommunications from, satellite
systems. Establishments providing
internet services or voice over internet
protocol (VoIP) services via clientsupplied telecommunications
connections are also included in this
industry. The SBA has developed a
small business size standard for ‘‘All
Other Telecommunications,’’ which
consists of all such firms with gross
annual receipts of $32.5 million or less.
For this category, U.S. Census data for
2012 show that there were 1,442 firms
that operated for the entire year. Of
these firms, a total of 1,400 had gross
annual receipts of less than $25 million
and 42 firms had annual receipts of $25
million to $49,999,999. Thus, a majority
of ‘‘All Other Telecommunications’’
firms potentially affected by the
Commission’s action can be considered
small.
111. Fixed Microwave Services.
Microwave services include common
carrier, private-operational fixed, and
broadcast auxiliary radio services. They
also include the Local Multipoint
Distribution Service (LMDS), the Digital
Electronic Message Service (DEMS), the
39 GHz Service (39 GHz), the 24 GHz
Service, and the Millimeter Wave
PO 00000
Frm 00068
Fmt 4700
Sfmt 4700
Service where licensees can choose
between common carrier and noncommon carrier status. At present, there
are approximately 66,680 common
carrier fixed licensees, 69,360 private
and public safety operational-fixed
licensees, 20,150 broadcast auxiliary
radio licensees, 411 LMDS licenses, 33
24 GHz DEMS licenses, 777 39 GHz
licenses, and five 24 GHz licenses, and
467 Millimeter Wave licenses in the
microwave services. The Commission
has not yet defined a small business size
standard for microwave services. The
closest applicable SBA category is
Wireless Telecommunications Carriers
(except Satellite) and the appropriate
size standard for this category under
SBA rules is that such a business is
small if it has 1,500 or fewer employees.
U.S. Census Bureau data for 2012, show
that there were 967 firms in this
category that operated for the entire
year. Of this total, 955 had employment
of 999 or fewer, and 12 firms had
employment of 1,000 employees or
more. Thus, under this category and the
associated small business size standard,
the Commission estimates that a
majority of fixed microwave service
licensees can be considered small.
112. The Commission notes that the
number of firms does not necessarily
track the number of licensees. The
Commission also notes that it does not
have data specifying the number of
these licensees that have more than
1,500 employees, and thus is unable at
this time to estimate with greater
precision the number of fixed
microwave service licensees that would
qualify as small business concerns
under the SBA’s small business size
standard. The Commission estimates
however, that virtually all of the Fixed
Microwave licensees (excluding
broadcast auxiliary licensees) would
qualify as small entities under the SBA
definition.
113. Non-Licensee Owners of Towers
and Other Infrastructure. Although at
one time most communications towers
were owned by the licensee using the
tower to provide communications
service, many towers are now owned by
third-party businesses that do not
provide communications services
themselves but lease space on their
towers to other companies that provide
communications services. The
Commission’s rules require that any
entity, including a non-licensee,
proposing to construct a tower over 200
feet in height or within the glide slope
of an airport must register the tower
with the Commission’s Antenna
Structure Registration (‘‘ASR’’) system
and comply with applicable rules
E:\FR\FM\15OCR1.SGM
15OCR1
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
khammond on DSK30JT082PROD with RULES
regarding review for impact on the
environment and historic properties.
114. As of March 1, 2017, the ASR
database includes approximately
122,157 registration records reflecting a
‘‘Constructed’’ status and 13,987
registration records reflecting a
‘‘Granted, Not Constructed’’ status.
These figures include both towers
registered to licensees and towers
registered to non-licensee tower owners.
The Commission does not keep
information from which we can easily
determine how many of these towers are
registered to non-licensees or how many
non-licensees have registered towers.
Regarding towers that do not require
ASR registration, we do not collect
information as to the number of such
towers in use and therefore cannot
estimate the number of tower owners
that would be subject to the rules on
which the Commission seeks comment.
Moreover, the SBA has not developed a
size standard for small businesses in the
category ‘‘Tower Owners.’’ Therefore,
the Commission is unable to determine
the number of non-licensee tower
owners that are small entities. The
Commission believes, however, that
when all entities owning 10 or fewer
towers and leasing space for collocation
are included, non-licensee tower owners
number in the thousands. In addition,
there may be other non-licensee owners
of other wireless infrastructure,
including Distributed Antenna Systems
(DAS) and small cells that might be
affected by the measures on which the
Commission seeks comment. The
Commission does not have any basis for
estimating the number of such nonlicensee owners that are small entities.
115. The closest applicable SBA
category is All Other
Telecommunications, and the
appropriate size standard consists of all
such firms with gross annual receipts of
$32.5 million or less. For this category,
U.S. Census data for 2012 show that
there were 1,442 firms that operated for
the entire year. Of these firms, a total of
1,400 had gross annual receipts of less
than $25 million and 15 firms had
annual receipts of $25 million to
$49,999,999. Thus, under this SBA size
standard a majority of the firms
potentially affected by the
Commission’s action can be considered
small.
5. Description of Projected Reporting,
Recordkeeping, and Other Compliance
Requirements for Small Entities
116. The Third Report and Order does
not establish any reporting,
recordkeeping, or other compliance
requirements for companies involved in
wireless infrastructure deployment. In
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
addition to not adopting any reporting,
recordkeeping or other compliance
requirements, the Commission takes
significant steps to reduce regulatory
impediments to infrastructure
deployment and, therefore, to spur the
growth of personal wireless services.
Under the Commission’s approach,
small entities as well as large companies
will be assured that their deployment
requests will be acted upon within a
reasonable period of time and, if their
applications are not addressed within
the established time frames, applicants
may seek injunctive relief granting their
siting applications. The Commission,
therefore, has taken concrete steps to
relieve companies of all sizes of
uncertainly and has eliminated
unnecessary delays.
117. The Third Report and Order also
does not impose any reporting or
recordkeeping requirements on state
and local governments. While some
commenters argue that additional shot
clock classifications would make the
siting process needlessly complex
without any proven benefits, the
Commission concludes that any
additional administrative burden from
increasing the number of Section 332
shot clocks from two to four is
outweighed by the likely significant
benefit of regulatory certainty and the
resulting streamlined deployment
process. The Commission’s actions are
consistent with the statutory language of
Section 332 and therefore reflect
Congressional intent. Further, siting
agencies have become more efficient in
processing siting applications and will
be able to take advantage of these
efficiencies in meeting the new shot
clocks. As a result, the additional shot
clocks that the Commission adopts will
foster the deployment of the latest
wireless technology and serve consumer
interests.
6. Steps Taken To Minimize the
Significant Economic Impact on Small
Entities, and Significant Alternatives
Considered
118. The RFA requires an agency to
describe any significant alternatives that
it has considered in reaching its
approach, which may include the
following four alternatives (among
others): ‘‘(1) The establishment of
differing compliance or reporting
requirements or timetables that take into
account the resources available to small
entities; (2) the clarification,
consolidation, or simplification of
compliance and reporting requirements
under the rule for such small entities;
(3) the use of performance rather than
design standards; and (4) an exemption
PO 00000
Frm 00069
Fmt 4700
Sfmt 4700
51883
from coverage of the rule, or any part
thereof, for such small entities.’’
119. The steps taken by the
Commission in the Third Report and
Order eliminate regulatory burdens for
small entities as well as large companies
that are involved with the deployment
of person wireless services
infrastructure. By establishing shot
clocks and guidance on injunctive relief
for personal wireless services
infrastructure deployments, the
Commission has standardized and
streamlined the permitting process.
These changes will significantly
minimize the economic burden of the
siting process on all entities, including
small entities, involved in deploying
personal wireless services
infrastructure. The record shows that
permitting delays imposes significant
economic and financial burdens on
companies with pending wireless
infrastructure permits. Eliminating
permitting delays will remove the
associated cost burdens and enabling
significant public interest benefits by
speeding up the deployment of personal
wireless services and infrastructure. In
addition, siting agencies will be able to
utilize the efficiencies that they have
gained over the years processing siting
applications to minimize financial
impacts.
120. The Commission considered but
did not adopt proposals by commenters
to issue ‘‘Best Practices’’ or
‘‘Recommended Practices,’’ and to
develop an informal dispute resolution
process and mediation program, noting
that the steps taken in the Third Report
and Order address the concerns
underlying these proposals to facilitate
cooperation between parties to reach
mutually agreed upon solutions. The
Commission anticipates that the
changes it has made to the permitting
process will provide significant
efficiencies in the deployment of
personal wireless services facilities and
this in turn will benefit all companies,
but particularly small entities, that may
not have the resources and economies of
scale of larger entities to navigate the
permitting process. By adopting these
changes, the Commission will continue
to fulfill its statutory responsibilities,
while reducing the burden on small
entities by removing unnecessary
impediments to the rapid deployment of
personal wireless services facilities and
infrastructure across the country.
7. Report to Congress
121. The Commission will send a
copy of the Third Report and Order,
including this FRFA, in a report to
Congress pursuant to the Congressional
Review Act. In addition, the
E:\FR\FM\15OCR1.SGM
15OCR1
51884
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
Commission will send a copy of the
Third Report and Order, including this
FRFA, to the Chief Counsel for
Advocacy of the SBA. A copy of the
Third Report and Order and FRFA (or
summaries thereof) also will be
published in the Federal Register.
B. Paperwork Reduction Act
122. This Third Report and Order
does not contain new or revised
information collection requirements
subject to the Paperwork Reduction Act
of 1995 (PRA), Public Law 104–13.
khammond on DSK30JT082PROD with RULES
C. Congressional Review Act
123. The Commission will send a
copy of this Declaratory Ruling and
Third Report and Order in a report to be
sent to Congress and the Government
Accountability Office pursuant to the
Congressional Review Act (CRA), see 5
U.S.C. 801(a)(1)(A).
IV. Ordering Clauses
124. Accordingly, it is ordered,
pursuant to sections 1, 4(i)–(j), 7, 201,
253, 301, 303, 309, 319, and 332 of the
Communications Act of 1934, as
amended, 47 U.S.C. 151, 154(i)–(j), 157,
201, 253, 301, 303, 309, 319, 332, that
this Declaratory Ruling and Third
Report and Order in WT Docket No. 17–
79 is hereby adopted.
125. It is further ordered that part 1
of the Commission’s rules is amended
as set forth in the final rules of this
Declaratory Ruling and Third Report
and Order, and that these changes shall
be effective January 14, 2019.
126. It is further ordered that this
Third Report and Order shall be
effective January 14, 2019. The
Declaratory Ruling and the obligations
set forth therein are effective on the
same day that this Third Report and
Order becomes effective. It is our
intention in adopting the foregoing
Declaratory Ruling and these rule
changes that, if any provision of the
Declaratory Ruling or the rules, or the
application thereof to any person or
circumstance, is held to be unlawful,
the remaining portions of such
Declaratory Ruling and the rules not
deemed unlawful, and the application
of such Declaratory Ruling and the rules
to other person or circumstances, shall
remain in effect to the fullest extent
permitted by law.
127. It is further ordered that,
pursuant to 47 CFR 1.4(b)(1), the period
for filing petitions for reconsideration or
petitions for judicial review of this
Declaratory Ruling and Third Report
and Order will commence on the date
that a summary of this Declaratory
Ruling and Third Report and Order is
published in the Federal Register.
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
128. It is further ordered that the
Commission’s Consumer &
Governmental Affairs Bureau, Reference
Information Center, shall send a copy of
this Declaratory Ruling and Third
Report and Order, including the Final
Regulatory Flexibility Analysis, to the
Chief Counsel for Advocacy of the Small
Business Administration.
129. It is further ordered that this
Declaratory Ruling and Third Report
and Order shall be sent to Congress and
the Government Accountability Office
pursuant to the Congressional Review
Act, see 5 U.S.C. 801(a)(1)(A).
List of Subjects in 47 CFR Part 1
Communications common carriers,
Communications equipment,
Environmental protection, Historic
preservation, Radio,
Telecommunications.
Federal Communications Commission.
Cecilia Sigmund,
Federal Register Liaison Officer, Office of the
Secretary.
Final Rules
For the reasons discussed in the
preamble, the Federal Communications
Commission amends 47 CFR part 1 as
follows:
PART 1—PRACTICE AND
PROCEDURE
1. The authority citation for part 1
continues to read as follows:
■
Authority: 47 U.S.C. chs. 2, 5, 9, 13; Sec.
102(c), Div. P, Public Law 115–141, 132 Stat.
1084; 28 U.S.C. 2461, unless otherwise noted.
2. Add subpart U, consisting of
§§ 1.6001 through 1.6003, to read as
follows:
■
Subpart U—State and Local
Government Regulation of the
Placement, Construction, and
Modification of Personal Wireless
Service Facilities
Sec.
1.6001 Purpose.
1.6002 Definitions.
1.6003 Reasonable periods of time to act on
siting applications.
§ 1.6001
Purpose.
This subpart implements 47 U.S.C.
332(c)(7) and 1455.
§ 1.6002
Definitions.
Terms not specifically defined in this
section or elsewhere in this subpart
have the meanings defined in this part
and the Communications Act of 1934,
47 U.S.C. 151 et seq. Terms used in this
subpart have the following meanings:
(a) Action or to act on a siting
application means a siting authority’s
PO 00000
Frm 00070
Fmt 4700
Sfmt 4700
grant of a siting application or issuance
of a written decision denying a siting
application.
(b) Antenna, consistent with
§ 1.1320(d), means an apparatus
designed for the purpose of emitting
radiofrequency (RF) radiation, to be
operated or operating from a fixed
location pursuant to Commission
authorization, for the provision of
personal wireless service and any
commingled information services. For
purposes of this definition, the term
antenna does not include an
unintentional radiator, mobile station,
or device authorized under part 15 of
this chapter.
(c) Antenna equipment, consistent
with § 1.1320(d), means equipment,
switches, wiring, cabling, power
sources, shelters or cabinets associated
with an antenna, located at the same
fixed location as the antenna, and, when
collocated on a structure, is mounted or
installed at the same time as such
antenna.
(d) Antenna facility means an antenna
and associated antenna equipment.
(e) Applicant means a person or entity
that submits a siting application and the
agents, employees, and contractors of
such person or entity.
(f) Authorization means any approval
that a siting authority must issue under
applicable law prior to the deployment
of personal wireless service facilities,
including, but not limited to, zoning
approval and building permit.
(g) Collocation, consistent with
§ 1.1320(d) and the Nationwide
Programmatic Agreement (NPA) for the
Collocation of Wireless Antennas,
appendix B of this part, section I.B,
means—
(1) Mounting or installing an antenna
facility on a pre-existing structure; and/
or
(2) Modifying a structure for the
purpose of mounting or installing an
antenna facility on that structure.
(3) The definition of ‘‘collocation’’ in
§ 1.6100(b)(2) applies to the term as
used in that section.
(h) Deployment means placement,
construction, or modification of a
personal wireless service facility.
(i) Facility or personal wireless service
facility means an antenna facility or a
structure that is used for the provision
of personal wireless service, whether
such service is provided on a standalone basis or commingled with other
wireless communications services.
(j) Siting application or application
means a written submission to a siting
authority requesting authorization for
the deployment of a personal wireless
service facility at a specified location.
E:\FR\FM\15OCR1.SGM
15OCR1
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
(k) Siting authority means a State
government, local government, or
instrumentality of a State government or
local government, including any official
or organizational unit thereof, whose
authorization is necessary prior to the
deployment of personal wireless service
facilities.
(l) Small wireless facilities, consistent
with § 1.1312(e)(2), are facilities that
meet each of the following conditions:
(1) The facilities—
(i) Are mounted on structures 50 feet
or less in height including their
antennas as defined in § 1.1320(d); or
(ii) Are mounted on structures no
more than 10 percent taller than other
adjacent structures; or
(iii) Do not extend existing structures
on which they are located to a height of
more than 50 feet or by more than 10
percent, whichever is greater;
(2) Each antenna associated with the
deployment, excluding associated
antenna equipment (as defined in the
definition of ‘‘antenna’’ in § 1.1320(d)),
is no more than three cubic feet in
volume;
(3) All other wireless equipment
associated with the structure, including
the wireless equipment associated with
the antenna and any pre-existing
associated equipment on the structure,
is no more than 28 cubic feet in volume;
(4) The facilities do not require
antenna structure registration under part
17 of this chapter;
(5) The facilities are not located on
Tribal lands, as defined under 36 CFR
800.16(x); and
(6) The facilities do not result in
human exposure to radiofrequency
radiation in excess of the applicable
safety standards specified in § 1.1307(b).
(m) Structure means a pole, tower,
base station, or other building, whether
or not it has an existing antenna facility,
that is used or to be used for the
provision of personal wireless service
(whether on its own or comingled with
other types of services).
khammond on DSK30JT082PROD with RULES
§ 1.6003 Reasonable periods of time to act
on siting applications.
(a) Timely action required. A siting
authority that fails to act on a siting
application on or before the shot clock
date for the application, as defined in
paragraph (e) of this section, is
presumed not to have acted within a
reasonable period of time.
(b) Shot clock period. The shot clock
period for a siting application is the sum
of—
(1) The number of days of the
presumptively reasonable period of time
for the pertinent type of application,
pursuant to paragraph (c) of this section;
plus
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
(2) The number of days of the tolling
period, if any, pursuant to paragraph (d)
of this section.
(c) Presumptively reasonable periods
of time—(1) Review periods for
individual applications. The following
are the presumptively reasonable
periods of time for action on
applications seeking authorization for
deployments in the categories set forth
in paragraphs (c)(1)(i) through (iv) of
this section:
(i) Review of an application to
collocate a Small Wireless Facility using
an existing structure: 60 days.
(ii) Review of an application to
collocate a facility other than a Small
Wireless Facility using an existing
structure: 90 days.
(iii) Review of an application to
deploy a Small Wireless Facility using
a new structure: 90 days.
(iv) Review of an application to
deploy a facility other than a Small
Wireless Facility using a new structure:
150 days.
(2) Batching. (i) If a single application
seeks authorization for multiple
deployments, all of which fall within a
category set forth in either paragraph
(c)(1)(i) or (iii) of this section, then the
presumptively reasonable period of time
for the application as a whole is equal
to that for a single deployment within
that category.
(ii) If a single application seeks
authorization for multiple deployments,
the components of which are a mix of
deployments that fall within paragraph
(c)(1)(i) of this section and deployments
that fall within paragraph (c)(1)(iii) of
this section, then the presumptively
reasonable period of time for the
application as a whole is 90 days.
(iii) Siting authorities may not refuse
to accept applications under paragraphs
(c)(2)(i) and (ii) of this section.
(d) Tolling period. Unless a written
agreement between the applicant and
the siting authority provides otherwise,
the tolling period for an application (if
any) is as set forth in paragraphs (d)(1)
through (3) of this section.
(1) For an initial application to deploy
Small Wireless Facilities, if the siting
authority notifies the applicant on or
before the 10th day after submission
that the application is materially
incomplete, and clearly and specifically
identifies the missing documents or
information and the specific rule or
regulation creating the obligation to
submit such documents or information,
the shot clock date calculation shall
restart at zero on the date on which the
applicant submits all the documents
and information identified by the siting
authority to render the application
complete.
PO 00000
Frm 00071
Fmt 4700
Sfmt 4700
51885
(2) For all other initial applications,
the tolling period shall be the number
of days from—
(i) The day after the date when the
siting authority notifies the applicant in
writing that the application is materially
incomplete and clearly and specifically
identifies the missing documents or
information that the applicant must
submit to render the application
complete and the specific rule or
regulation creating this obligation; until
(ii) The date when the applicant
submits all the documents and
information identified by the siting
authority to render the application
complete;
(iii) But only if the notice pursuant to
paragraph (d)(2)(i) of this section is
effectuated on or before the 30th day
after the date when the application was
submitted; or
(3) For resubmitted applications
following a notice of deficiency, the
tolling period shall be the number of
days from—
(i) The day after the date when the
siting authority notifies the applicant in
writing that the applicant’s
supplemental submission was not
sufficient to render the application
complete and clearly and specifically
identifies the missing documents or
information that need to be submitted
based on the siting authority’s original
request under paragraph (d)(1) or (2) of
this section; until
(ii) The date when the applicant
submits all the documents and
information identified by the siting
authority to render the application
complete;
(iii) But only if the notice pursuant to
paragraph (d)(3)(i) of this section is
effectuated on or before the 10th day
after the date when the applicant makes
a supplemental submission in response
to the siting authority’s request under
paragraph (d)(1) or (2) of this section.
(e) Shot clock date. The shot clock
date for a siting application is
determined by counting forward,
beginning on the day after the date
when the application was submitted, by
the number of calendar days of the shot
clock period identified pursuant to
paragraph (b) of this section and
including any pre-application period
asserted by the siting authority;
provided, that if the date calculated in
this manner is a ‘‘holiday’’ as defined in
§ 1.4(e)(1) or a legal holiday within the
relevant State or local jurisdiction, the
shot clock date is the next business day
after such date. The term ‘‘business
day’’ means any day as defined in
§ 1.4(e)(2) and any day that is not a legal
holiday as defined by the State or local
jurisdiction.
E:\FR\FM\15OCR1.SGM
15OCR1
51886
Federal Register / Vol. 83, No. 199 / Monday, October 15, 2018 / Rules and Regulations
§ 1.40001 [Redesignated as § 1.6100 and
Amended]
Subpart CC—[Removed]
3. Redesignate § 1.40001 as § 1.6100
and, in newly redesignated § 1.6100,
remove and reserve paragraph (a).
■
khammond on DSK30JT082PROD with RULES
■
VerDate Sep<11>2014
16:29 Oct 12, 2018
Jkt 247001
4. Remove subpart CC.
[FR Doc. 2018–22234 Filed 10–12–18; 8:45 am]
BILLING CODE 6712–01–P
PO 00000
Frm 00072
Fmt 4700
Sfmt 9990
E:\FR\FM\15OCR1.SGM
15OCR1
Agencies
[Federal Register Volume 83, Number 199 (Monday, October 15, 2018)]
[Rules and Regulations]
[Pages 51867-51886]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-22234]
=======================================================================
-----------------------------------------------------------------------
FEDERAL COMMUNICATIONS COMMISSION
47 CFR Part 1
[WT Docket No. 17-79, WC Docket No. 17-84; FCC 18-133]
Accelerating Wireless and Wireline Broadband Deployment by
Removing Barriers to Infrastructure Investment
AGENCY: Federal Communications Commission.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: In this document, the Federal Communications Commission
(``Commission'' or ``FCC'') issues guidance and adopts rules to
streamline the wireless infrastructure siting review process to
facilitate the deployment of next-generation wireless facilities.
Specifically, in the Declaratory Ruling, the Commission identifies
specific fee levels for the deployment of Small Wireless Facilities,
and it addresses state and local consideration of aesthetic concerns
that effect the deployment of Small Wireless Facilities. In the Order,
the Commission addresses the ``shot clocks'' governing the review of
wireless infrastructure deployments and establishes two new shot clocks
for Small Wireless Facilities.
DATES: Effective January 14, 2019.
FOR FURTHER INFORMATION CONTACT: Jiaming Shang, Deputy Chief (Acting)
Competition and Infrastructure Policy Division, Wireless
Telecommunications Bureau, (202) 418-1303, email [email protected].
SUPPLEMENTARY INFORMATION: This is a summary of the Commission's
Declaratory Ruling and Third Report and Order (Declaratory Ruling and
Order), WT Docket No. 17-79 and WC Docket No. 17-84; FCC 18-133,
adopted September 26, 2018 and released September 27, 2018. The full
text of this document is available for inspection and copying during
business hours in the FCC Reference Information Center, Portals II, 445
12th Street SW, Room CY-A257, Washington, DC 20554. Also, it may be
purchased from the Commission's duplicating contractor at
[[Page 51868]]
Portals II, 445 12th Street SW, Room CY-B402, Washington, DC 20554; the
contractor's website, https://www.bcpiweb.com; or by calling (800) 378-
3160, facsimile (202) 488-5563, or email [email protected]. Copies of the
Declaratory Ruling and Order also may be obtained via the Commission's
Electronic Comment Filing System (ECFS) by entering the docket number
WT Docket 17-79 and WC Docket No. 17-84. Additionally, the complete
item is available on the Federal Communications Commission's website at
https://www.fcc.gov.
Synopsis
I. Declaratory Ruling
1. In the Declaratory Ruling, the Commission notes that a number of
appellate courts have articulated different and often conflicting views
regarding the scope and nature of the limits Congress imposed on state
and local governments through Sections 253 and 332. In light of these
diverging views, Congress's vision for a consistent, national policy
framework, and the need to ensure that the Commission's approach
continues to make sense in light of the relatively new trend towards
the large-scale deployment of Small Wireless Facilities, the Commission
takes the opportunity to clarify and update the FCC's reading of the
limits Congress imposed. The Commission does so in three main respects.
2. First, the Commission expresses its agreement with the views
already stated by the First, Second, and Tenth Circuits that the
``materially inhibit'' standard articulated in 1997 by the Clinton-era
FCC's California Payphone decision is the appropriate standard for
determining whether a state or local law operates as a prohibition or
effective prohibition within the meaning of Sections 253 and 332.
3. Second, the Commission notes, as numerous courts have
recognized, that state and local fees and other charges associated with
the deployment of wireless infrastructure can effectively prohibit the
provision of service. At the same time, courts have articulated various
approaches to determining the types of fees that run afoul of
Congress's limits in Sections 253 and 332. The Commission thus
clarifies the particular standard that governs the fees and charges
that violate Sections 253 and 332 when it comes to the Small Wireless
Facilities at issue in this decision. Namely, fees are only permitted
to the extent that they represent a reasonable approximation of the
local government's objectively reasonable costs and are non-
discriminatory. In this section, the Commission also identifies
specific fee levels for the deployment of Small Wireless Facilities
that presumptively comply with this standard. The Commission does so to
help avoid unnecessary litigation, while recognizing that it is the
standard itself, not the particular, presumptive fee levels the
Commission articulates, that ultimately will govern whether a
particular fee is allowed under Sections 253 and 332. So, fees above
those levels would be permissible under Sections 253 and 332 to the
extent a locality's actual, reasonable costs (as measured by the
standard above) are higher.
4. Finally, the Commission focuses on a subset of other, non-fee
provisions of state and local law that could also operate as
prohibitions on service. The Commission does so in particular by
addressing state and local consideration of aesthetic concerns in the
deployment of Small Wireless Facilities. The Commission notes that the
Small Wireless Facilities that are the subject of this Declaratory
Ruling remain subject to the Commission's rules governing Radio
Frequency (RF) emissions exposure.
A. Overview of the Section 253 and Section 332(c)(7) Framework Relevant
to Small Wireless Facilities Deployment
5. As an initial matter, the Commission notes that its Declaratory
Ruling applies with equal measure to the effective prohibition standard
that appears in both Sections 253(a) and 332(c)(7). This ruling is
consistent with the basic canon of statutory interpretation that
identical words appearing in neighboring provisions of the same statute
should be interpreted to have the same meaning. Moreover, both of these
provisions apply to wireless telecommunications services as well as to
commingled services and facilities.
6. As explained in California Payphone and reaffirmed here, a state
or local legal requirement will have the effect of prohibiting wireless
telecommunications services if it materially inhibits the provision of
such services. California Payphone Ass'n, 12 FCC Rcd 14191 (1997). The
Commission clarifies that an effective prohibition occurs where a state
or local legal requirement materially inhibits a provider's ability to
engage in any of a variety of activities related to its provision of a
covered service. This test is met not only when filling a coverage gap
but also when densifying a wireless network, introducing new services
or otherwise improving service capabilities. Under the California
Payphone standard, a state or local legal requirement could materially
inhibit service in numerous ways--not only by rendering a service
provider unable to provide an existing service in a new geographic area
or by restricting the entry of a new provider in providing service in a
particular area, but also by materially inhibiting the introduction of
new services or the improvement of existing services. Thus, an
effective prohibition includes materially inhibiting additional
services or improving existing services.
7. The Commission's reading of Section 253(a) and Section
332(c)(7)(B)(i)(II) reflects and supports a marketplace in which
services can be offered in a multitude of ways with varied capabilities
and performance characteristics consistent with the policy goals in the
1996 Act and the Communications Act. To limit Sections 253(a) and
332(c)(7)(B)(i)(II) to protecting only against coverage gaps or the
like would be to ignore Congress's contemporaneously-expressed goals of
``promot[ing] competition[,] . . . secur[ing] . . . higher quality
services for American telecommunications consumers and encourage[ing]
the rapid deployment of new telecommunications technologies.'' In
addition, as the Commission recently explained, the implementation of
the Act ``must factor in the fundamental objectives of the Act,
including the deployment of a ``rapid, efficient . . . wire and radio
communication service with adequate facilities at reasonable charges'
and `the development and rapid deployment of new technologies, products
and services for the benefit of the public . . . without administrative
or judicial delays[, and] efficient and intensive use of the
electromagnetic spectrum.' '' These provisions demonstrate that the
Commission's interpretation of Section 253 and Section
332(c)(7)(B)(i)(II) is in accordance with the broader goals of the
various statutes that the Commission is entrusted to administer.
8. California Payphone further concluded that providers must be
allowed to compete in a ``fair and balanced regulatory environment.''
As reflected in decisions such as the Commission's Texas PUC Order, a
state or local legal requirement can function as an effective
prohibition either because of the resulting ``financial burden'' in an
absolute sense, or, independently, because of a resulting competitive
disparity. Public Utility Comm'n of Texas, et al., Pet. for Decl.
Ruling and/or Preemption of Certain Provisions of the Texas Pub. Util.
Reg. Act of 1995, 13 FCC Rcd 3460 (1997). The Commission clarifies that
``[a]
[[Page 51869]]
regulatory structure that gives an advantage to particular services or
facilities has a prohibitory effect, even if there are no express
barriers to entry in the state or local code; the greater the
discriminatory effect, the more certain it is that entities providing
service using the disfavored facilities will experience prohibition.''
This conclusion is consistent with both Commission and judicial
precedent recognizing the prohibitory effect that results from a
competitor being treated materially differently than similarly-situated
providers. The Commission provides its authoritative interpretation
below of the circumstances in which a ``financial burden,'' as
described in the Texas PUC Order, constitutes an effective prohibition
in the context of certain state and local fees.
B. State and Local Fees
9. Cognizant of the changing technology and its interaction with
regulations created for a previous generation of service, the
Commission sought comment on the scope of Sections 253 and 332(c)(7)
and on any new or updated guidance the Commission should provide,
potentially through a Declaratory Ruling. In particular, the Commission
sought comment on whether it should provide further guidance on how to
interpret and apply the phrase ``prohibit or have the effect of
prohibiting.''
10. The Commission concludes that ROW access fees, and fees for the
use of government property in the ROW, such as light poles, traffic
lights, utility poles, and other similar property suitable for hosting
Small Wireless Facilities, as well as application or review fees and
similar fees imposed by a state or local government as part of their
regulation of the deployment of Small Wireless Facilities inside and
outside the ROW, violate Sections 253 or 332(c)(7) unless these
conditions are met: (1) The fees are a reasonable approximation of the
state or local government's costs, (2) only objectively reasonable
costs are factored into those fees, and (3) the fees are no higher than
the fees charged to similarly-situated competitors in similar
situations.
11. Capital Expenditures. Apart from the text, structure, and
legislative history of the 1996 Act, an additional, independent
justification for the Commission's interpretation follows from the
simple, logical premise, supported by the record, that state and local
fees in one place of deployment necessarily have the effect of reducing
the amount of capital that providers can use to deploy infrastructure
elsewhere, whether the reduction takes place on a local, regional or
national level. The Commission is persuaded that providers and
infrastructure builders, like all economic actors, have a finite
(though perhaps fluid) amount of resources to use for the deployment of
infrastructure. This does not mean that these resources are limitless,
however. The Commission concludes that fees imposed by localities,
above and beyond the recovery of localities' reasonable costs,
materially and improperly inhibit deployment that could have occurred
elsewhere. This and regulatory uncertainty created by such effectively
prohibitive conduct creates an appreciable impact on resources that
materially limits plans to deploy service. This record evidence
emphasizes the importance of evaluating the effect of fees on Small
Wireless Facility deployment on an aggregate basis. The record
persuades the Commission that fees associated with Small Wireless
Facility deployment lead to ``a substantial increase in costs''--
particularly when considered in the aggregate--thereby ``plac[ing] a
significant burden'' on carriers and materially inhibiting their
provision of service contrary to Section 253 of the Act.
12. The record reveals that fees above a reasonable approximation
of cost, even when they may not be perceived as excessive or likely to
prohibit service in isolation, will have the effect of prohibiting
wireless service when the aggregate effects are considered,
particularly given the nature and volume of anticipated Small Wireless
Facility deployment. The record reveals that these effects can take
several forms. In some cases, the fees in a particular jurisdiction
will lead to reduced or entirely forgone deployment of Small Wireless
Facilities in the near term for that jurisdiction. In other cases,
where it is essential for a provider to deploy in a given area, the
fees charged in that geographic area can deprive providers of capital
needed to deploy elsewhere, and lead to reduced or forgone near-term
deployment of Small Wireless Facilities in other geographic areas. In
both of those scenarios the bottom-line outcome on the national
development of 5G networks is the same--diminished deployment of Small
Wireless Facilities critical for wireless service and building out 5G
networks.
13. Relationship to Section 332. The Commission clarifies that the
statutory phrase ``prohibit or have the effect of prohibiting'' in
Section 332(c)(7)(B)(i)(II) has the same meaning as the phrase
``prohibits or has the effect of prohibiting'' in Section 253(a). There
is no evidence to suggest that Congress intended for virtually
identical language to have different meanings in the two provisions.
Instead, the Commission finds it more reasonable to conclude that the
language in both sections should be interpreted to have the same
meaning and to reflect the same standard, including with respect to
preemption of fees that could ``prohibit'' or have ``the effect of
prohibiting'' the provision of covered service. Both sections were
enacted to address concerns about state and local government practices
that undermined providers' ability to provide covered services, and
both bar state or local conduct that prohibits or has the effect of
prohibiting service.
14. To be sure, Sections 253 and 332(c)(7) may relate to different
categories of state and local fees. Ultimately, the Commission needs
not resolve here the precise interplay between Sections 253 and
332(c)(7). It is enough for it to conclude that, collectively, Congress
intended for the two provisions to cover the universe of fees charged
by state and local governments in connection with the deployment of
telecommunications infrastructure. Given the analogous purposes of both
sections and the consistent language used by Congress, the Commission
finds the phrase ``prohibit or have the effect of prohibiting'' in
Section 332(c)(7)(B)(i)(II) should be construed as having the same
meaning and governed by the same preemption standard as the nearly
identical language in Section 253(a).
15. Application of the Interpretations and Principles Established
Here. Consistent with the interpretations above, the requirement that
compensation be limited to a reasonable approximation of objectively
reasonable costs and be non-discriminatory applies to all state and
local government fees paid in connection with a provider's use of the
ROW to deploy Small Wireless Facilities including, but not limited to,
fees for access to the ROW itself, and fees for the attachment to or
use of property within the ROW owned or controlled by the government
(e.g., street lights, traffic lights, utility poles, and other
infrastructure within the ROW suitable for the placement of Small
Wireless Facilities). This interpretation applies with equal force to
any fees reasonably related to the placement, construction,
maintenance, repair, movement, modification, upgrade, replacement, or
removal of Small Wireless Facilities within the ROW, including, but not
limited to, application or permit fees such as siting applications,
zoning variance applications, building permits, electrical
[[Page 51870]]
permits, parking permits, or excavation permits.
16. Applying the principles established in this Declaratory Ruling,
a variety of fees not reasonably tethered to costs appear to violate
Sections 253(a) or 332(c)(7) in the context of Small Wireless Facility
deployments. For example, the Commission agrees with courts that have
recognized that gross revenue fees generally are not based on the costs
associated with an entity's use of the ROW, and where that is the case,
are preempted under Section 253(a). In addition, although the
Commission rejects calls to preclude a state or locality's use of third
party contractors or consultants, or to find all associated
compensation preempted, the Commission makes clear that the principles
discussed herein regarding the reasonableness of cost remain
applicable. Thus, fees must not only be limited to a reasonable
approximation of costs, but in order to be reflected in fees the costs
themselves must also be reasonable. Accordingly, any unreasonably high
costs, such as excessive charges by third party contractors or
consultants, may not be passed on through fees even though they are an
actual ``cost'' to the government. If a locality opts to incur
unreasonable costs, Sections 253 and 332(c)(7) do not permit it to pass
those costs on to providers. Fees that depart from these principles are
not saved by Section 253(c), as the Commission discusses below.
17. Interpretation of Section 253(c) in the Context of Fees. In
this section, the Commission turns to the interpretation of several
provisions in Section 253(c), which provides that state or local action
that otherwise would be subject to preemption under Section 253(a) may
be permissible if it meets specified criteria. Section 253(c) expressly
provides that state or local governments may require telecommunications
providers to pay ``fair and reasonable compensation'' for use of public
ROWs but requires that the amounts of any such compensation be
``competitively neutral and nondiscriminatory'' and ``publicly
disclosed.''
18. The Commission interprets the ambiguous phrase ``fair and
reasonable compensation,'' within the statutory framework it outlined
for Section 253, to allow state or local governments to charge fees
that recover a reasonable approximation of the state or local
governments' actual and reasonable costs. The Commission concludes that
an appropriate yardstick for ``fair and reasonable compensation,'' and
therefore an indicator of whether a fee violates Section 253(c), is
whether it recovers a reasonable approximation of a state or local
government's objectively reasonable costs of, respectively, maintaining
the ROW, maintaining a structure within the ROW, or processing an
application or permit.
19. The existence of Section 253(c) makes clear that Congress
anticipated that ``effective prohibitions'' could result from state or
local government fees, and intended through that clause to provide
protections in that respect, as discussed in greater detail herein.
Against that backdrop, the Commission finds it unlikely that Congress
would have left providers entirely at the mercy of effectively
unconstrained requirements of state or local governments. The
Commission's interpretation of Section 253(c), in fact, is consistent
with the views of many municipal commenters, at least with respect to
one-time permit or application fees, and the members of the BDAC Ad Hoc
Committee on Rates and Fees who unanimously concurred that one-time
fees for municipal applications and permits, such as an electrical
inspection or a building permit, should be based on the cost to the
government of processing that application. The Ad Hoc Committee noted
that ``[the] cost-based fee structure [for one-time fees] unanimously
approved by the committee accommodates the different siting related
costs that different localities may incur to review, and process permit
applications, while precluding excessive fees that impede deployment.''
The Commission finds that the same reasoning should apply to other
state and local government fees such as ROW access fees or fees for the
use of government property within the ROW.
20. The Commission recognizes that state and local governments
incur a variety of direct and actual costs in connection with Small
Wireless Facilities, such as the cost for staff to review the
provider's siting application, costs associated with a provider's use
of the ROW, and costs associated with maintaining the ROW itself or
structures within the ROW to which Small Wireless Facilities are
attached. The Commission also recognizes that direct and actual costs
may vary by location, scope, and extent of providers' planned
deployments, such that different localities will have different fees
under the interpretation set forth in this Declaratory Ruling.
21. Because the Commission interprets fair and reasonable
compensation as a reasonable approximation of costs, it does not
suggest that localities must use any specific accounting method to
document the costs they may incur when determining the fees they charge
for Small Wireless Facilities within the ROW. Moreover, in order to
simplify compliance, when a locality charges both types of recurring
fees identified above (i.e., for access to the ROW and for use of or
attachment to property in the ROW), the Commission sees no reason for
concern with how it has allocated costs between those two types of
fees. It is sufficient under the statute that the total of the two
recurring fees reflects the total costs involved. Fees that cannot
ultimately be shown by a state or locality to be a reasonable
approximation of their costs, such as high fees designed to subsidize
local government costs in another geographic area or accomplish some
public policy objective beyond the providers' use of the ROW, are not
``fair and reasonable compensation . . . for use of the public rights-
of-way'' under Section 253(c). Likewise, the Commission agrees with
both industry and municipal commenters that excessive and arbitrary
consulting fees or other costs should not be recoverable as ``fair and
reasonable compensation,'' because they are not a function of the
provider's ``use'' of the public ROW.
22. In addition to requiring that compensation be ``fair and
reasonable,'' Section 253(c) requires that it be ``competitively
neutral and nondiscriminatory.'' The Commission has previously
interpreted this language to prohibit states and localities from
charging fees on new entrants and not on incumbents. Courts have
similarly found that states and localities may not impose a range of
fees on one provider but not on another and even some municipal
commenters acknowledge that governments should not discriminate on the
fees charged to different providers. The record reflects continuing
concerns from providers, however, that they face discriminatory
charges. The Commission reiterates its previous determination that
state and local governments may not impose fees on some providers that
they do not impose on others. The Commission would also be concerned
about fees, whether one-time or recurring, related to Small Wireless
Facilities, that exceed the fees for other wireless telecommunications
infrastructure in similar situations, and to the extent that different
fees are charged for similar use of the public ROW.
23. Fee Levels Likely to Comply with Section 253. The Commission's
interpretations of Section 253(a) and ``fair and reasonable
compensation'' under Section 253(c) provides guidance for local and
state fees charged with
[[Page 51871]]
respect to one-time fees generally, and recurring fees for deployments
in the ROW. Following suggestions for the Commission to ``establish a
presumptively reasonable `safe harbor' for certain ROW and use fees,''
and to facilitate the deployment of specific types of infrastructure
critical to the rollout of 5G in coming years, the Commission
identifies in this section three particular types of fee scenarios and
supply specific guidance on amounts that are presumptively not
prohibited by Section 253. Informed by the its review of information
from a range of sources, the Commission concludes that fees at or below
these amounts presumptively do not constitute an effective prohibition
under Section 253(a) or Section 332(c)(7) and are presumed to be ``fair
and reasonable compensation'' under Section 253(c).
24. Based on its review of the Commission's pole attachment rate
formula, which would require fees below the levels described in this
paragraph, as well as small cell legislation in twenty states, local
legislation from certain municipalities in states that have not passed
small cell legislation, and comments in the record, the Commission
presumes that the following fees would not be prohibited by Section 253
or Section 332(c)(7): (a) $500 for non-recurring fees, including a
single up-front application that includes up to five Small Wireless
Facilities, with an additional $100 for each Small Wireless Facility
beyond five, or $1,000 for non-recurring fees for a new pole (i.e., not
a collocation) intended to support one or more Small Wireless
Facilities, and (b) $270 per Small Wireless Facility per year for all
recurring fees, including any possible ROW access fee or fee for
attachment to municipally-owned structures in the ROW.
25. By presuming that fees at or below the levels above comply with
Section 253, the Commission assumes that there would be almost no
litigation by providers over fees set at or below these levels.
Likewise, the Commission's review of the record, including the many
state small cell bills passed to date, indicate that there should be
only very limited circumstances in which localities can charge higher
fees consistent with the requirements of Section 253. In those limited
circumstances, a locality could prevail in charging fees that are above
this level by showing that such fees nonetheless comply with the limits
imposed by Section 253--that is, that they are (1) a reasonable
approximation of costs, (2) those costs themselves are reasonable, and
(3) are non-discriminatory. Allowing localities to charge fees above
these levels upon this showing recognizes local variances in costs.
C. Other State and Local Requirements That Govern Small Facilities
Deployment
26. There are also other types of state and local land-use or
zoning requirements that may restrict Small Wireless Facility
deployments to the degree that they have the effect of prohibiting
service in violation of Sections 253 and 332. In this section, the
Commission discusses how those statutory provisions apply to
requirements outside the fee context both generally, and with
particular focus on aesthetic and undergrounding requirements.
27. As discussed above, a state or local legal requirement
constitutes an effective prohibition if it ``materially limits or
inhibits the ability of any competitor or potential competitor to
compete in a fair and balanced legal and regulatory environment.'' The
Commission's interpretation of that standard, as set forth above,
applies equally to fees and to non-fee legal requirements. And as with
fees, Section 253 contains certain safe harbors that permit some legal
requirements that might otherwise be preempted by Section 253(a).
Section 253(b) saves ``requirements necessary to preserve and advance
universal service, protect the public safety and welfare, ensure the
continued quality of telecommunications services, and safeguard the
rights of consumers. And Section 253(c) preserves state and local
authority to manage the public rights-of-way.
28. Given the wide variety of possible legal requirements, the
Commission does not attempt here to determine which of every possible
non-fee legal requirements are preempted for having the effect of
prohibiting service, although the Commission's discussion of fees above
should prove instructive in evaluating specific requirements. Instead,
the Commission focuses on some specific types of requirements raised in
the record and provide guidance on when those particular types of
requirements are preempted by the statute.
29. Aesthetics. The Commission sought comment on whether deployment
restrictions based on aesthetic or similar factors are widespread and,
if so, how Sections 253 and 332(c)(7) should be applied to them. The
Commission provides guidance on whether and in what circumstances
aesthetic requirements violate the Act. This will help localities
develop and implement lawful rules, enable providers to comply with
these requirements, and facilitate the resolution of disputes. The
Commission concludes that aesthetics requirements are not preempted if
they are (1) reasonable, (2) no more burdensome than those applied to
other types of infrastructure deployments, and (3) objective and
published in advance.
30. Like fees, compliance with aesthetic requirements imposes costs
on providers, and the impact on their ability to provide service is
just the same as the impact of fees. The Commission therefore draws on
its analysis of fees to address aesthetic requirements. The Commission
explained above that fees that merely require providers to bear the
direct and reasonable costs that their deployments impose on states and
localities should not be viewed as having the effect of prohibiting
service and are permissible. Analogously, aesthetic requirements that
are reasonable in that they are technically feasible and reasonably
directed to avoiding or remedying the intangible public harm of
unsightly or out-of-character deployments are also permissible. In
assessing whether this standard has been met, aesthetic requirements
that are more burdensome than those the state or locality applies to
similar infrastructure deployments are not permissible, because such
discriminatory application evidences that the requirements are not, in
fact, reasonable and directed at remedying the impact of the wireless
infrastructure deployment. For example, a minimum spacing requirement
that has the effect of materially inhibiting wireless service would be
considered an effective prohibition of service.
31. Finally, in order to establish that they are reasonable and
reasonably directed to avoiding aesthetic harms, aesthetic requirements
must be objective--i.e., they must incorporate clearly-defined and
ascertainable standards, applied in a principled manner--and must be
published in advance. ``Secret'' rules that require applicants to guess
at what types of deployments will pass aesthetic muster substantially
increase providers' costs without providing any public benefit or
addressing any public harm. Providers cannot design or implement
rational plans for deploying Small Wireless Facilities if they cannot
predict in advance what aesthetic requirements they will be obligated
to satisfy to obtain permission to deploy a facility at any given site.
32. The Commission appreciates that at least some localities will
require some time to establish and publish aesthetics
[[Page 51872]]
standards that are consistent with this Declaratory Ruling. Based on
its review and evaluation of commenters' concerns, the Commission
anticipates that such publication should take no longer than 180 days
after publication of this decision in the Federal Register.
33. Undergrounding requirements. The Commission understands that
some local jurisdictions have adopted undergrounding provisions that
require infrastructure to be deployed below ground based, at least in
some circumstances, on the locality's aesthetic concerns. A number of
providers have complained that these types of requirements amount to an
effective prohibition. In addressing this issue, the Commission first
reiterates that while undergrounding requirements may well be
permissible under state law as a general matter, any local authority to
impose undergrounding requirements under state law does not remove the
imposition of such undergrounding requirements from the provisions of
Section 253. In this sense, the Commission notes that a requirement
that all wireless facilities be deployed underground would amount to an
effective prohibition given the propagation characteristics of wireless
signals. Thus, undergrounding requirements can amount to effective
prohibitions by materially inhibiting the deployment of wireless
service.
34. Minimum spacing requirements. Some parties complain of
municipal requirements regarding the spacing of wireless
installations--i.e., mandating that facilities be sited at least 100,
500, or 1,000 feet, or some other minimum distance, away from other
facilities, ostensibly to avoid excessive overhead ``clutter'' that
would be visible from public areas. The Commission acknowledges that
while some such requirements may violate 253(a), others may be
reasonable aesthetic requirements. For example, under the principle
that any such requirements be reasonable and publicly available in
advance, it is difficult to envision any circumstances in which a
municipality could reasonably promulgate a new minimum spacing
requirement that, in effect, prevents a provider from replacing its
preexisting facilities or collocating new equipment on a structure
already in use. Such a rule change with retroactive effect would almost
certainly have the effect of prohibiting service under the standards
the Commission articulate here. Therefore, such requirements should be
evaluated under the same standards as other aesthetic requirements.
D. States and Localities Act in Their Regulatory Capacities When
Authorizing and Setting Terms for Wireless Infrastructure Deployment in
Public Rights of Way
35. The Commission confirms that it interpretations today extend to
state and local governments' terms for access to public ROW that they
own or control, including areas on, below, or above public roadways,
highways, streets, sidewalks, or similar property, as well as their
terms for use of or attachment to government-owned property within such
ROW, such as light poles, traffic lights, and similar property suitable
for hosting Small Wireless Facilities. As explained below, for two
alternative and independent reasons, the Commission disagrees with
state and local government commenters who assert that, in providing or
denying access to government-owned structures, these governmental
entities function solely as ``market participants'' whose rights cannot
be subject to federal preemption under Section 253(a) or Section
332(c)(7).
36. First, this effort to differentiate between such governmental
entities' ``regulatory'' and ``proprietary'' capacities in order to
insulate the latter from preemption ignores a fundamental feature of
the market participant doctrine. Specifically, Section 253(a) expressly
preempts certain state and local ``legal requirements'' and makes no
distinction between a state or locality's regulatory and proprietary
conduct. Indeed, as the Commission has long recognized, Section
253(a)'s sweeping reference to ``state [and] local statute[s] [and]
regulation[s]'' and ``other State [and] local legal requirement[s]''
demonstrates Congress's intent ``to capture a broad range of state and
local actions that prohibit or have the effect of prohibiting entities
from providing telecommunications services.'' Section 253(b) mentions
``requirement[s],'' a phrase that is even broader than that used in
Section 253(a) but covers ``universal service,'' ``public safety and
welfare,'' ``continued quality of telecommunications,'' and
``safeguard[s for the] rights of consumers.'' The subsection does not
recognize a distinction between regulatory and proprietary. Section
253(c), which expressly insulates from preemption certain state and
local government activities, refers in relevant part to ``manag[ing]
the public rights-of-way'' and ``requir[ing] fair and reasonable
compensation,'' while eliding any distinction between regulatory and
proprietary action in either context. The Commission has previously
observed that Section 253(c) ``makes explicit a local government's
continuing authority to issue construction permits regulating how and
when construction is conducted on roads and other public rights-of-
way;'' the Commission concludes here that, as a general matter,
``manage[ment]'' of the ROW includes any conduct that bears on access
to and use of those ROW, notwithstanding any attempts to characterize
such conduct as proprietary. This reading, coupled with Section
253(c)'s narrow scope, suggests that Congress's omission of a blanket
proprietary exception to preemption was intentional and thus that such
conduct can be preempted under Section 253(a). The Commission therefore
construes Section 253(c)'s requirements, including the requirement that
compensation be ``fair and reasonable,'' as applying equally to charges
imposed via contracts and other arrangements between a state or local
government and a party engaged in wireless facility deployment. This
interpretation is consistent with Section 253(a)'s reference to ``State
or local legal requirement[s],'' which the Commission has consistently
construed to include such agreements. In light of the foregoing,
whatever the force of the market participant doctrine in other
contexts, the Commission believes the language, legislative history,
and purpose of Sections 253(a) and (c) are incompatible with the
application of this doctrine in this context. The Commission observes
once more that ``[o]ur conclusion that Congress intended this language
to be interpreted broadly is reinforced by the scope of section
253(d),'' which ``directs the Commission to preempt any statute,
regulation, or legal requirement permitted or imposed by a state or
local government if it contravenes sections 253(a) or (b). A more
restrictive interpretation of the term `other legal requirements'
easily could permit state and local restrictions on competition to
escape preemption based solely on the way in which [State] action [is]
structured. The Commission does not believe that Congress intended this
result.''
37. Similarly, the Commission interprets Section 332(c)(7)(B)(ii)'s
references to ``any request[s] for authorization to place, construct,
or modify personal wireless service facilities'' broadly, consistent
with Congressional intent. As described below, the Commission finds
that ``any'' is unqualifiedly broad, and that ``request'' encompasses
anything required to secure all authorizations necessary for the
deployment of
[[Page 51873]]
personal wireless services infrastructure. In particular, the
Commission finds that Section 332(c)(7) includes authorizations
relating to access to a ROW, including but not limited to the
``place[ment], construct[ion], or modif[ication]'' of facilities on
government-owned property, for the purpose of providing ``personal
wireless service.'' The Commission observes that this result, too, is
consistent with Commission precedent, which involved a contract that
provided exclusive access to a ROW. As but one example, to have limited
that holding to exclude government-owned property within the ROW even
if the carrier needed access to that property would have the effect of
diluting or completely defeating the purpose of Section 332(c)(7).
38. Second, and in the alternative, even if Section 253(a) and
Section 332(c)(7) were to permit leeway for states and localities
acting in their proprietary role, the examples in the record would be
excepted because they involve states and localities fulfilling
regulatory objectives. In the proprietary context, ``a State acts as a
`market participant with no interest in setting policy.' '' The
Commission contrasts state and local governments' purely proprietary
actions with states and localities acting with respect to managing or
controlling access to property within public ROW, or to decisions about
where facilities that will provide personal wireless service to the
public may be sited. As several commenters point out, courts have
recognized that states and localities ``hold the public streets and
sidewalks in trust for the public'' and ``manage public ROW in their
regulatory capacities.'' These decisions could be based on a number of
regulatory objectives, such as aesthetics or public safety and welfare,
some of which, as the Commission notes elsewhere, would fall within the
preemption scheme envisioned by Congress. In these situations, the
State or locality's role seems to be indistinguishable from its
function and objectives as a regulator. To the extent that there is
some distinction, the temptation to blend the two roles for purposes of
insulating conduct from federal preemption cannot be underestimated in
light of the overarching statutory objective that telecommunications
service and personal wireless services be deployed without material
impediments.
39. The Commission believes that Section 253(c) is properly
construed to suggest that Congress did not intend to permit states and
localities to rely on their ownership of property within a ROW as a
pretext to advance regulatory objectives that prohibit or have the
effect of prohibiting the provision of covered services, and thus that
such conduct is preempted. The Commission's interpretations here are
intended to facilitate the implementation of the scheme Congress
intended and to provide greater regulatory certainty to states,
municipalities, and regulated parties about what conduct is preempted
under Section 253(a). Should factual questions arise about whether a
state or locality is engaged in such behavior, Section 253(d) affords
state and local governments and private parties an avenue for specific
preemption challenges.
E. Responses to Challenges to the Commission's Interpretive Authority
and Other Arguments
40. The Commission rejects claims that it lacks authority to issue
authoritative interpretations of Sections 253 and 332(c)(7) in this
Declaratory Ruling. The Commission acts here pursuant to its broad
authority to interpret key provisions of the Communications Act,
consistent with the Commission's exercise of that interpretive
authority in the past. In this instance, the Commission finds that
issuing a Declaratory Ruling is necessary to remove what the record
reveals is substantial uncertainty and to reduce the number and
complexity of legal controversies regarding certain fee and non-fee
state and local legal requirements in connection with Small Wireless
Facility infrastructure. The Commission thus exercise its authority in
this Declaratory Ruling to interpret Section 253 and Section 332(c)(7)
and explain how those provisions apply in the specific scenarios at
issue here.
41. Nothing in Sections 253 or 332(c)(7) purports to limit the
exercise of the Commission's general interpretive authority. Congress's
inclusion of preemption provisions in Section 253(d) and Section
332(c)(7)(B)(v) does not limit the Commission's ability pursuant to
other sections of the Act to construe and provide its authoritative
interpretation as to the meaning of those provisions. Any preemption
under Section 253 and/or Section 332(c)(7)(B) that subsequently occurs
will proceed in accordance with the enforcement mechanisms available in
each context. But whatever enforcement mechanisms may be available to
preempt specific state and local requirements, nothing in Section 253
or Section 332(c)(7) prevents the Commission from declaring that a
category of state or local laws is inconsistent with Section 253(a) or
Section 332(c)(7)(B)(i)(II) because it prohibits or has the effect of
prohibiting the relevant covered service.
42. The Commission's interpretations of Sections 253 and Section
332(c)(7) are likewise not at odds with the Tenth Amendment and
constitutional precedent, as some commenters contend. In particular,
the Commission's interpretations do not directly ``compel the states to
administer federal regulatory programs or pass legislation.'' The
outcome of violations of Section 253(a) or Section 332(c)(7)(B) of the
Act are no more than a consequence of ``the limits Congress already
imposed on State and local governments'' through its enactment of
Section 332(c)(7).
43. The Commission also reject the suggestion that the limits
Section 253 places on state and local rights-of-way fees and management
will unconstitutionally interfere with the relationship between a state
and its political subdivisions. As relevant to its interpretations
here, it is not clear, at first blush, that such concerns would be
implicated. Because state and local legal requirements can be written
and structured in myriad ways, and challenges to such state or local
activities could be framed in broad or narrow terms, the Commission
declines to resolve such questions here, divorced from any specific
context.
II. Third Report and Order
44. In this Third Report and Order, the Commission addresses the
application of shot clocks to state and local review of wireless
infrastructure deployments. The Commission does so by taking action in
three main areas. First, the Commission adopts a new set of shot clocks
tailored to support the deployment Small Wireless Facilities. Second,
the Commission adopts a specific remedy that applies to violations of
these new Small Wireless Facility shot clocks, which the Commission
expects will operate to significantly reduce the need for litigation
over missed shot clocks. Third, the Commission clarifies a number of
issues that are relevant to all of the FCC's shot clocks, including the
types of authorizations subject to these time periods.
A. New Shot Clocks for Small Wireless Facility Deployments
45. In 2009, the Commission concluded that it should use shot
clocks to define a presumptive ``reasonable period of time'' beyond
which state or local inaction on wireless infrastructure siting
applications would constitute a ``failure to act'' within the meaning
of
[[Page 51874]]
Section 332. The Commission adopted a 90-day clock for reviewing
collocation applications and a 150-day clock for reviewing siting
applications other than collocations. The record here suggests that the
two existing Section 332 shot clocks have increased the efficiency of
deploying wireless infrastructure. Many localities already process
wireless siting applications in less time than required by those shot
clocks and a number of states have enacted laws requiring that
collocation applications be processed in 60 days or less. Some siting
agencies acknowledge that they have worked to gain efficiencies in
processing siting applications and welcome the addition of new shot
clocks tailored to the deployment of small scale facilities. Given
siting agencies' increased experience with existing shot clocks, the
greater need for rapid siting of Small Wireless Facilities nationwide,
and the lower burden siting of these facilities places on siting
agencies in many cases, the Commission takes this opportunity to update
its approach to speed the deployment of Small Wireless Facilities.
1. Two New Section 332 Shot Clocks for Deployment of Small Wireless
Facilities
46. In this section, the Commission adopts two new Section 332 shot
clocks for Small Wireless Facilities--60 days for review of an
application for collocation of Small Wireless Facilities using a
preexisting structure and 90 days for review of an application for
attachment of Small Wireless Facilities using a new structure. These
new Section 332 shot clocks carefully balance the well-established
authority that states and local authorities have over review of
wireless siting applications with the requirements of Section
332(c)(7)(ii) to exercise that authority ``within a reasonable period
of time . . . taking into account the nature and scope of the
request.'' Further, the Commission's decision is consistent with the
BDAC's Model Code for Municipalities' recommended timeframes, which
utilize this same 60-day and 90-day framework for collocation of Small
Wireless Facilities and new structures and are similar to shot clocks
enacted in state level small cell bills and the real world experience
of many municipalities which further supports the reasonableness of its
approach. The Commission's actions will modernize the framework for
wireless facility siting by taking into consideration that states and
localities should be able to address the siting of Small Wireless
Facilities in a more expedited review period than needed for larger
facilities.
47. The Commission finds compelling reasons to establish a new
presumptively reasonable Section 332 shot clock of 60 days for
collocations of Small Wireless Facilities on existing structures. The
record demonstrates the need for, and reasonableness of, expediting the
siting review of these collocations. Notwithstanding the implementation
of the current shot clocks, more streamlined procedures are both
reasonable and necessary to provide greater predictability for siting
applications nationwide for the deployment of Small Wireless
Facilities. The two current Section 332 shot clocks do not reflect the
evolution of the application review process and evidence that
localities can complete reviews more quickly than was the case when the
existing Section 332 shot clocks were adopted nine years ago. Since
2009, localities have gained significant experience processing wireless
siting applications. Indeed, many localities already process wireless
siting applications in less than the required time and several
jurisdictions require by law that collocation applications be processed
in 60 days or less. With the passage of time, siting agencies have
become more efficient in processing siting applications. These facts
demonstrate that a shorter, 60-day shot clock for processing
collocation applications for Small Wireless Facilities is reasonable.
48. As the Commission found in 2009, collocation applications are
generally easier to process than new construction because the community
impact is likely to be smaller. In particular, the addition of an
antenna to an existing tower or other structure is unlikely to have a
significant visual impact on the community. The size of Small Wireless
Facilities poses little or no risk of adverse effects on the
environment or historic preservation. Indeed, many jurisdictions do not
require public hearings for approval of such attachments, underscoring
their belief that such attachments do not implicate complex issues
requiring a more searching review.
49. Further, the Commission finds no reason to believe that
applying a 60-day time frame for Small Wireless Facility collocations
under Section 332 creates confusion with collocations that fall within
the scope of ``eligible facilities requests'' under Section 6409 of the
Spectrum Act, which are also subject to a 60-day review. The type of
facilities at issue here are distinctly different and the definition of
a Small Wireless Facility is clear. Further, siting authorities are
required to process Section 6409 applications involving the swap out of
certain equipment in 60 days, and the Commission sees no meaningful
difference in processing these applications than processing Section 332
collocation applications in 60 days. There is no reason to apply
different time periods (60 vs. 90 days) to what is essentially the same
review: Modification of an existing structure to accommodate new
equipment. Finally, adopting a 60-day shot clock will encourage service
providers to collocate rather than opting to build new siting
structures which has numerous advantages.
50. For similar reasons, the Commission also finds it reasonable to
establish a new 90-day Section 332 shot clock for new construction of
Small Wireless Facilities. Ninety days is a presumptively reasonable
period of time for localities to review such siting applications. Small
Wireless Facilities have far less visual and other impact than the
facilities the Commission considered in 2009 and should accordingly
require less time to review. Indeed, some state and local governments
have already adopted 60-day maximum reasonable periods of time for
review of all small cell siting applications, and, even in the absence
of such maximum requirements, several are already reviewing and
approving small-cell siting applications within 60 days or less after
filing. Numerous industry commenters advocated a 90-day shot clock for
all non-collocation deployments. Based on this record, the Commission
finds review of an application to deploy a Small Wireless Facility
using a new structure warrants more review time than a mere
collocation, but less than the construction of a macro tower. For the
reasons explained below, the Commission also specifies today a
provision that will initially reset these two new shot clocks in the
event that a locality receives a materially incomplete application.
2. Batched Applications for Small Wireless Facilities
51. Given the way in which Small Wireless Facilities are likely to
be deployed, in large numbers as part of a system meant to cover a
particular area, the Commission anticipates that some applicants will
submit ``batched'' applications: Multiple separate applications filed
at the same time, each for one or more sites or a single application
covering multiple sites. The Commission sought comment on whether
batched applications should be subject to either longer or shorter shot
clocks than would apply if each component of the batch were submitted
[[Page 51875]]
separately. The Commission sees no reason why the shot clocks for
batched applications to deploy Small Wireless Facilities should be
longer than those that apply to individual applications because, in
many cases, the batching of such applications has advantages in terms
of administrative efficiency that could actually make review easier.
The Commission's decision flows from its current Section 332 shot clock
policy. Under the two existing Section 332 shot clocks, if an applicant
files multiple siting applications on the same day for the same type of
facilities, each application is subject to the same number of review
days by the siting agency. These multiple siting applications are
equivalent to a batched application and therefore the shot clocks for
batching should follow the same rules as if the applications were filed
separately. Accordingly, when applications to deploy Small Wireless
Facilities are filed in batches, the shot clock that applies to the
batch is the same one that would apply had the applicant submitted
individual applications. Should an applicant file a single application
for a batch that includes both collocated and new construction of Small
Wireless Facilities, the longer 90-day shot clock will apply, to ensure
that the siting authority has adequate time to review the new
construction sites.
52. The Commission recognizes the concerns raised by parties
arguing for a longer time period for at least some batched applications
but concludes that a separate rule is not necessary to address these
concerns. Under the Commission's approach, in extraordinary cases, a
siting authority, as discussed below, can rebut the presumption of
reasonableness of the applicable shot clock period where a batch
application causes legitimate overload on the siting authority's
resources. Thus, contrary to some localities' arguments, the
Commission's approach provides for a certain degree of flexibility to
account for exceptional circumstances. In addition, consistent with,
and for the same reasons as the Commission's conclusion below that
Section 332 does not permit states and localities to prohibit
applicants from requesting multiple types of approvals simultaneously,
the Commission finds that Section 332(c)(7)(B)(ii) similarly does not
allow states and localities to refuse to accept batches of applications
to deploy Small Wireless Facilities.
B. New Remedy for Violations of the Small Wireless Facilities Shot
Clocks
53. In adopting these new shot clocks for Small Wireless Facility
applications, the Commission also provides an additional remedy that it
expects will substantially reduce the likelihood that applicants will
need to pursue additional and costly relief in court at the expiration
of those time periods.
54. The Commission determines that the failure of a state or local
government to issue a decision on a Small Wireless Facility siting
application within the presumptively reasonable time periods above will
constitute a ``failure to act'' within the meaning of Section
332(c)(7)(B)(v). Therefore, a provider is, at a minimum, entitled to
the same process and remedies available for a failure to act within the
new Small Wireless Facility shot clocks as they have been under the
FCC's 2009 shot clocks. But the Commission also adds an additional
remedy for the new Small Wireless Facility shot clocks.
55. State or local inaction by the end of the Small Wireless
Facility shot clock will function not only as a Section 332(c)(7)(B)(v)
failure to act but also amount to a presumptive prohibition on the
provision of personal wireless services within the meaning of Section
332(c)(7)(B)(i)(II). Accordingly, the Commission would expect the state
or local government to issue all necessary permits without further
delay. In cases where such action is not taken, the Commission assumes,
for the reasons discussed below, that the applicant would have a
straightforward case for obtaining expedited relief in court.
56. As discussed in the Declaratory Ruling, a regulation under
Section 332(c)(7)(B)(i)(II) constitutes an effective prohibition if it
materially limits or inhibits the ability of any competitor or
potential competitor to compete in a fair and balanced legal and
regulatory environment. Missing shot clock deadlines would thus
presumptively have the effect of unlawfully prohibiting service in that
such failure to act can be expected to materially limit or inhibit the
introduction of new services or the improvement of existing services.
Thus, when a siting authority misses the applicable shot clock
deadline, the applicant may commence suit in a court of competent
jurisdiction alleging a violation of Section 332(c)(7)(B)(i)(II), in
addition to a violation of Section 332(c)(7)(B)(ii), as discussed
above. The siting authority then will have an opportunity to rebut the
presumption of effective prohibition by demonstrating that the failure
to act was reasonable under the circumstances and, therefore, did not
materially limit or inhibit the applicant from introducing new services
or improving existing services.
57. Given the seriousness of failure to act within a reasonable
period of time, the Commission expects, as noted above, siting
authorities to issue without any further delay all necessary
authorizations when notified by the applicant that they have missed the
shot clock deadline, absent extraordinary circumstances. Where the
siting authority nevertheless fails to issue all necessary
authorizations and litigation is commenced based on violations of
Sections 332(c)(7)(B)(i)(II) and/or 332(c)(7)(B)(ii), the Commission
expects that applicants and other aggrieved parties will likely pursue
equitable judicial remedies. Given the relatively low burden on state
and local authorities of simply acting--one way or the other--within
the Small Wireless Facility shot clocks, the Commission thinks that
applicants would have a relatively low hurdle to clear in establishing
a right to expedited judicial relief.
58. The Commission expects that courts will typically find
expedited and permanent injunctive relief warranted for violations of
Sections 332(c)(7)(B)(i)(II) and 332(c)(7)(B)(ii) of the Act when
addressing the circumstances discussed in this Order. The Commission
believes that this approach is sensible because guarding against
barriers to the deployment of personal wireless facilities not only
advances the goal of Section 332(c)(7)(B) but also policies set out
elsewhere in the Communications Act and 1996 Act, as the Commission
recently has recognized in the case of Small Wireless Facilities. This
is so whether or not these barriers stem from bad faith. Nor does the
Commission anticipate that there would be unresolved issues implicating
the siting authority's expertise and therefore requiring remand in most
instances.
59. The guidance provided here should reduce the need for, and
complexity of, case-by-case litigation and reduce the likelihood of
vastly different timing across various jurisdictions for the same type
of deployment. This clarification, along with the other actions the
Commission takes in this Third Report and Order, should streamline the
courts' decision-making process and reduce the possibility of
inconsistent rulings. Consequently, the Commission believes that its
approach helps facilitate courts' ability to ``hear and decide such
[lawsuits] on an expedited basis,'' as the statute requires.
60. The Commission's updated interpretation of Section 332(c)(7)
for Small Wireless Facilities effectively balances the interest of
wireless service providers to have siting applications granted in a
timely and streamlined manner and the interest of localities to
[[Page 51876]]
protect public safety and welfare and preserve their authority over the
permitting process. The Commission's specialized deployment categories,
in conjunction with the acknowledgement that in rare instances, it may
legitimately take longer to act, recognize that the siting process is
complex and handled in many different ways under various states' and
localities' long-established codes. Further, the Commission's approach
tempers localities' concerns about the inflexibility of a deemed
granted proposal because the new remedy the Commission adopts here
accounts for the breadth of potentially unforeseen circumstances that
individual localities may face and the possibility that additional
review time may be needed in truly exceptional circumstances. The
Commission further finds that its interpretive framework will not be
unduly burdensome on localities because a number of states have already
adopted even more stringent deemed granted remedies
C. Clarification of Issues Related to All Section 332 Shot Clocks
1. Authorizations Subject to the ``Reasonable Period of Time''
Provision of Section 332(c)(7)(B)(ii)
61. Section 332(c)(7)(B)(ii) requires state and local governments
to act ``within a reasonable period of time'' on ``any request for
authorization to place, construct, or modify personal wireless service
facilities.'' The Commission has not addressed the specific types of
authorizations subject to this requirement. After carefully considering
these arguments, the Commission finds that ``any request for
authorization to place, construct, or modify personal wireless service
facilities'' under Section 332(c)(7)(B)(ii) means all authorizations
necessary for the deployment of personal wireless services
infrastructure. This interpretation finds support in the record and is
consistent with the courts' interpretation of this provision and the
text and purpose of the Act.
62. The Commission's interpretation remains faithful to the purpose
of Section 332(c)(7) to balance Congress's competing desires to
preserve the traditional role of state and local governments in
regulating land use and zoning, while encouraging the rapid development
of new telecommunications technologies. Under the Commission's
interpretation, states and localities retain their authority over
personal wireless facilities deployment. At the same time, deployment
will be kept on track by ensuring that the entire approval process
necessary for deployment is completed within a reasonable period of
time, as defined by the shot clocks addressed in this Third Report and
Order.
2. Codification of Section 332 Shot Clocks
63. In addition to establishing two new Section 332 shot clocks for
Small Wireless Facilities, the Commission takes this opportunity to
codify its two existing Section 332 shot clocks for siting applications
that do not involve Small Wireless Facilities. In 2009 the Commission
found that 90 days is a reasonable time frame for processing
collocation applications and 150 days is a reasonable time frame to
process applications other than collocations. Since these Section 332
shot clocks were adopted as part of a declaratory ruling, they were not
codified in the Commission's rules. The Commission sought comment on
whether to modify these shot clocks. The Commission finds no need to
modify them here and will continue to use these shot clocks for
processing Section 332 siting applications that do not involve Small
Wireless Facilities. The Commission does, though, codify these two
existing shot clocks in its rules alongside the two newly-adopted shot
clocks so that all interested parties can readily find the shot clock
requirements in one place.
3. Collocations on Structures Not Previously Zoned for Wireless Use
64. The Commission takes this opportunity to clarify that for
purposes of the Section 332 shot clocks, attachment of facilities to
existing structures constitutes collocation, regardless of whether the
structure or the location has previously been zoned for wireless
facilities. As the Commission stated in 2009, ``an application is a
request for collocation if it does not involve a `substantial increase
in the size of a tower' as defined in the Nationwide Programmatic
Agreement (NPA) for the Collocation of Wireless Antennas.'' The
definition of ``[c]ollocation'' in the NPA provides for the ``mounting
or installation of an antenna on an existing tower, building or
structure for the purpose of transmitting and/or receiving radio
frequency signals for communications purposes, whether or not there is
an existing antenna on the structure.'' The NPA's definition of
collocation explicitly encompasses collocations on structures and
buildings that have not yet been zoned for wireless use. To interpret
the NPA any other way would be unduly narrow and there is no persuasive
reason to accept a narrower interpretation. This is particularly true
given that the NPA definition of collocation stands in direct contrast
with the definition of collocation in the Spectrum Act, pursuant to
which facilities only fall within the scope of an ``eligible facilities
request'' if they are attached to towers or base stations that have
already been zoned for wireless use.
4. When Shot Clocks Start and Incomplete Applications
65. In 2014 the Commission clarified that a shot clock begins to
run when an application is first submitted, not when the application is
deemed complete. The clock can be paused, however, if the locality
notifies the applicant within 30 days that the application is
incomplete. The locality may pause the clock again if it provides
written notice within 10 days that the supplemental submission did not
provide the information identified in the original notice delineating
missing information. The Commission sought comment on these
determinations.
66. Based on the record, the Commission finds no cause to alter the
Commission's prior determinations and now codifies them in its rules.
Codified rules, easily accessible to applicants and localities alike,
should provide helpful clarity. The complaints by states and localities
about the sufficiency of some of the applications they receive are
adequately addressed by the Commission's current policy, which
preserves the states' and localities' ability to pause review when they
find an application to be incomplete. The Commission does not find it
necessary at this point to shorten the 30-day initial review period for
completeness because, as was the case when this review period was
adopted in the 2009, it remains consistent with review periods for
completeness under existing state wireless infrastructure deployment
statutes and still ``gives State and local governments sufficient time
for reviewing applications for completeness, while protecting
applicants from a last minute decision that an application should be
denied as incomplete.''
67. However, for applications to deploy Small Wireless Facilities,
the Commission implements a modified tolling system designed to help
ensure that providers are submitting complete applications on day one.
This step accounts for the fact that the shot clocks applicable to such
applications are shorter than those established in 2009 and, because of
which, there may instances where the prevailing tolling
[[Page 51877]]
rules would further shorten the shot clocks to such an extent that it
might be impossible for siting authorities to act on the application.
For Small Wireless Facilities applications, the siting authority has 10
days from the submission of the application to determine whether the
application is incomplete. The shot clock then resets once the
applicant submits the supplemental information requested by the siting
authority. Thus, for example, for an application to collocate Small
Wireless Facilities, once the applicant submits the supplemental
information in response to a siting authority's timely request, the
shot clock resets, effectively giving the siting authority an
additional 60 days to act on the Small Wireless Facilities collocation
application. For subsequent determinations of incompleteness, the
tolling rules that apply to non-Small Wireless Facilities would apply--
that is, the shot clock would toll if the siting authority provides
written notice within 10 days that the supplemental submission did not
provide the information identified in the original notice delineating
missing information.
68. As noted above, multiple authorizations may be required before
a deployment is allowed to move forward. For instance, a locality may
require a zoning permit, a building permit, an electrical permit, a
road closure permit, and an architectural or engineering permit for an
applicant to place, construct, or modify its proposed personal wireless
service facilities. All of these permits are subject to Section 332's
requirement to act within a reasonable period of time, and thus all are
subject to the shot clocks the Commission adopts or codifies here.
69. The Commission also finds that mandatory pre-application
procedures and requirements do not toll the shot clocks. The Commission
concludes that the ability to toll a shot clock when an application is
found incomplete or by mutual agreement by the applicant and the siting
authority should be adequate to address these concerns. Much like a
requirement to file applications one after another, requiring pre-
application review would allow for a complete circumvention of the shot
clocks by significantly delaying their start date. An application is
not ruled on within ``a reasonable period of time after the request is
duly filed'' if the state or locality takes the full ordinary review
period after having delayed the filing in the first instance due to
required pre-application review. Indeed, requiring a pre-application
review before an application may be filed is similar to imposing a
moratorium, which the Commission has made clear does not stop the shot
clocks from running. Therefore, the Commission concludes that if an
applicant proffers an application, but a state or locality refuses to
accept it until a pre-application review has been completed, the shot
clock begins to run when the application is proffered.
70. That said, the Commission encourages voluntary pre-application
discussions, which may well be useful to both parties. The record
indicates that such meetings can clarify key aspects of the application
review process, especially with respect to large submissions or
applicants new to a particular locality's processes and may speed the
pace of review. To the extent that an applicant voluntarily engages in
a pre-application review to smooth the way for its filing, the shot
clock will begin when an application is filed, presumably after the
pre-application review has concluded.
71. The Commission also reiterates that the remedies granted under
Section 332(c)(7)(B)(v) are independent of, and in addition to, any
remedies that may be available under state or local law. Thus, where a
state or locality has established its own shot clocks, an applicant may
pursue any remedies granted under state or local law in cases where the
siting authority fails to act within those shot clocks. However, the
applicant must wait until the Commission shot clock period has expired
to bring suit for a ``failure to act'' under Section 332(c)(7)(B)(v).
III. Procedural Matters
A. Final Regulatory Flexibility Analysis
72. As required by the Regulatory Flexibility Act of 1980, as
amended (RFA), an Initial Regulatory Flexibility Analysis (IRFA) was
incorporated in the Notice of Proposed Rulemaking (NPRM), released in
April 2017 (82 FR 22453, May 16, 2017). The Commission sought written
public comment on the proposals in the NPRM, including comment on the
IRFA. The comments received are addressed below in Section 2. This
present Final Regulatory Flexibility Analysis (FRFA) conforms to the
RFA.
1. Need for and Objectives of the Rules
73. In the Third Report and Order, the Commission continues its
efforts to promote the timely buildout of wireless infrastructure
across the country by eliminating regulatory impediments that
unnecessarily delay bringing personal wireless services to consumers.
The record shows that lengthy delays in approving siting applications
by siting agencies has been a persistent problem. With this in mind,
the Third Report and Order establishes and codifies specific rules
concerning the amount of time siting agencies may take to review and
approve certain categories of wireless infrastructure siting
applications. More specifically, the Commission addresses its Section
332 shot clock rules for infrastructure applications which will be
presumed reasonable under the Communications Act. As an initial matter,
the Commission establishes two new shot clocks for Small Wireless
Facilities applications. For collocation of Small Wireless Facilities
on preexisting structures, the Commission adopts a 60-day shot clock
which applies to both individual and batched applications. For
applications associated with Small Wireless Facilities new construction
the Commission adopts a 90-day shot clock for both individual and
batched applications. The Commission also codifies two existing Section
332 shot clocks for all other Non-Small Wireless Facilities that were
established in 2009 without codification. These existing shot clocks
require 90-days for processing of all other Non-Small Wireless
Facilities collocation applications, and 150-days for processing of all
other Non-Small Wireless Facilities applications other than
collocations.
74. The Third Report and Order addresses other issues related to
both the existing and new shot clocks. In particular the Commission
addresses the specific types of authorizations subject to the
``Reasonable Period of Time'' provisions of Section 332(c)(7)(B)(ii),
finding that ``any request for authorization to place, construct, or
modify personal wireless service facilities'' under Section
332(c)(7)(B)(ii) means all authorizations a locality may require, and
to all aspects of and steps in the siting process, including license or
franchise agreements to access ROW, building permits, public notices
and meetings, lease negotiations, electric permits, road closure
permits, aesthetic approvals, and other authorizations needed for
deployment of personal wireless services infrastructure. The Commission
also addresses collocation on structures not previously zoned for
wireless use, when the four Section 332 shot clocks begin to run, the
impact of incomplete applications on the Commission's Section 332 shot
clocks, and how state imposed shot clocks remedies effect the
Commission's Section 332 shot clocks remedies.
75. The Commission discusses the appropriate judicial remedy that
applicants may pursue in cases where a
[[Page 51878]]
siting authority fails to act within the applicable shot clock period.
In those situations, applicants may commence an action in a court of
competent jurisdiction alleging a violation of Section
332(c)(7)(B)(i)(II) and seek injunctive relief granting the
application. Notwithstanding the availability of a judicial remedy if a
shot clock deadline is missed, the Commission recognizes that the
Section 332 time frames might not be met in exceptional circumstances
and has refined its interpretation of the circumstances when a period
of time longer than the relevant shot clock would nonetheless be a
reasonable period of time for action by a siting agency. In addition, a
siting authority that is subject to a court action for missing an
applicable shot clock deadline has the opportunity to demonstrate that
the failure to act was reasonable under the circumstances and,
therefore, did not materially limit or inhibit the applicant from
introducing new services or improving existing services thereby
rebutting the effective prohibition presumption.
76. The rules adopted in the Third Report and Order will accelerate
the deployment of wireless infrastructure needed for the mobile
wireless services of the future, while preserving the fundamental role
of localities in this process. Under the Commission's new rules,
localities will maintain control over the placement, construction and
modification of personal wireless facilities, while at the same time
the Commission's new process will streamline the review of wireless
siting applications.
2. Summary of Significant Issues Raised by Public Comments in Response
to the IRFA
77. Only one party--the Smart Cities and Special Districts
Coalition--filed comments specifically addressing the rules and
policies proposed in the IRFA. They argue that any shortening or
alteration of the Commission's existing shot clocks or the adoption of
a deemed granted remedy will adversely affect small local governments,
special districts, property owners, small developers, and others by
placing their siting applications behind wireless provider siting
applications. Subsequently, NATOA filed comments concerning the draft
FRFA. NATOA argues that the new shot clocks impose burdens on local
governments and particularly those with limited resources. NATOA
asserts that the new shot clocks will spur more deployment applications
than localities currently process.
78. These arguments, however, fail to acknowledge that Section 332
shot clocks have been in place for years and reflect Congressional
intent as seen in the statutory language of Section 332. The record in
this proceeding demonstrates the need for, and reasonableness of,
expediting the siting review of certain facility deployments. More
streamlined procedures are both reasonable and necessary to provide
greater predictability. The current shot clocks do not reflect the
evolution of the application review process and evidence that
localities can complete reviews more quickly than was the case when the
original shot clocks were adopted nine years ago. Localities have
gained significant experience processing wireless siting applications
and several jurisdictions already have in place laws that require
applications to be processed in less time than the Commission's new
shot clocks. With the passage of time, sitting agencies have become
more efficient in processing siting applications and this, in turn,
should reduce any economic burden the Commission's new shot clock
provisions have on them.
79. The Commission has carefully considered the impact of its new
shot clocks on siting authorities and has established shot clocks that
take into consideration the nature and scope of siting requests by
establishing shot clocks of different lengths of time that depend on
the nature of the siting request at issue. The length of these shot
clocks is based in part on the need to ensure that local governments
have ample time to take any steps needed to protect public safety and
welfare and to process other pending utility applications. Since local
siting authorities have gained experience in processing siting requests
in an expedited fashion, they should be able to comply with the
Commission's new shot clocks.
80. The Commission has taken into consideration the concerns of the
Smart Cities and Special Districts Coalition and NATOA. It has
established shot clocks that will not favor wireless providers over
other applicants with pending siting applications. Further, instead of
adopting a deemed granted remedy that would grant a siting application
when a shot clock lapses without a decision on the merits, the
Commission provides guidance as to the appropriate judicial remedy that
applicants may pursue and examples of exceptional circumstance where a
siting authority may be justified in needing additional time to review
a siting application then the applicable shot clock allows. Under this
approach, the applicant may seek injunctive relief as long as several
minimum requirements are met. The siting authority, however, can rebut
the presumptive reasonableness of the applicable shot clock under
certain circumstances. The circumstances under which a sitting
authority might have to do this will be rare. Under this carefully
crafted approach, the interests of siting applicants, siting
authorities, and citizens are protected.
3. Response to Comments by the Chief Counsel for Advocacy of the Small
Business Administration
81. Pursuant to the Small Business Jobs Act of 2010, which amended
the RFA, the Commission is required to respond to any comments filed by
the Chief Counsel for Advocacy of the Small Business Administration
(SBA), and to provide a detailed statement of any change made to the
proposed rules as a result of those comments.
82. The Chief Counsel did not file any comments in response to the
proposed rules in this proceeding.
4. Description and Estimate of the Number of Small Entities to Which
the Rules Will Apply
83. The RFA directs agencies to provide a description of, and where
feasible, an estimate of the number of small entities that may be
affected by the rules adopted herein. The RFA generally defines the
term ``small entity'' as having the same meaning as the terms ``small
business,'' ``small organization,'' and ``small governmental
jurisdiction.'' In addition, the term ``small business'' has the same
meaning as the term ``small business concern'' under the Small Business
Act. A ``small business concern'' is one which: (1) Is independently
owned and operated; (2) is not dominant in its field of operation; and
(3) satisfies any additional criteria established by the SBA.
84. Small Businesses, Small Organizations, Small Governmental
Jurisdictions. The Commission's actions, over time, may affect small
entities that are not easily categorized at present. The Commission
therefore describe here, at the outset, three broad groups of small
entities that could be directly affected herein. First, while there are
industry specific size standards for small businesses that are used in
the regulatory flexibility analysis, according to data from the SBA's
Office of Advocacy, in general a small business is an independent
business having fewer than 500 employees. These types of small
businesses represent 99.9 percent of all businesses in the United
States
[[Page 51879]]
which translates to 28.8 million businesses.
85. Next, the type of small entity described as a ``small
organization'' is generally ``any not-for-profit enterprise which is
independently owned and operated and is not dominant in its field.''
Nationwide, as of August 2016, there were approximately 356,494 small
organizations based on registration and tax data filed by nonprofits
with the Internal Revenue Service (IRS).
86. Finally, the small entity described as a ``small governmental
jurisdiction'' is defined generally as ``governments of cities,
counties, towns, townships, villages, school districts, or special
districts, with a population of less than fifty thousand.'' U.S. Census
Bureau data from the 2012 Census of Governments indicate that there
were 90,056 local governmental jurisdictions consisting of general
purpose governments and special purpose governments in the United
States. Of this number there were 37,132 General purpose governments
(county, municipal and town or township) with populations of less than
50,000 and 12,184 Special purpose governments (independent school
districts and special districts) with populations of less than 50,000.
The 2012 U.S. Census Bureau data for most types of governments in the
local government category show that the majority of these governments
have populations of less than 50,000. Based on this data the Commission
estimates that at least 49,316 local government jurisdictions fall in
the category of ``small governmental jurisdictions.''
87. Wireless Telecommunications Carriers (except Satellite). This
industry comprises establishments engaged in operating and maintaining
switching and transmission facilities to provide communications via the
airwaves. Establishments in this industry have spectrum licenses and
provide services using that spectrum, such as cellular services, paging
services, wireless internet access, and wireless video services. The
appropriate size standard under SBA rules is that such a business is
small if it has 1,500 or fewer employees. For this industry, U.S.
Census data for 2012 show that there were 967 firms that operated for
the entire year. Of this total, 955 firms had employment of 999 or
fewer employees and 12 had employment of 1,000 employees or more. Thus
under this category and the associated size standard, the Commission
estimates that the majority of wireless telecommunications carriers
(except satellite) are small entities.
88. The Commission's own data--available in its Universal Licensing
System--indicate that, as of May 17, 2018, there are 264 Cellular
licensees that will be affected by the Commission's actions. The
Commission does not know how many of these licensees are small, as the
Commission does not collect that information for these types of
entities. Similarly, according to Commission data, 413 carriers
reported that they were engaged in the provision of wireless telephony,
including cellular service, Personal Communications Service (PCS), and
Specialized Mobile Radio (SMR) Telephony services. Of this total, an
estimated 261 have 1,500 or fewer employees and 152 have more than
1,500 employees. Thus, using available data, the Commission estimates
that the majority of wireless firms can be considered small.
89. Personal Radio Services. Personal radio services provide short-
range, low-power radio for personal communications, radio signaling,
and business communications not provided for in other services.
Personal radio services include services operating in spectrum licensed
under part 95 of the Commission's rules. These services include Citizen
Band Radio Service, General Mobile Radio Service, Radio Control Radio
Service, Family Radio Service, Wireless Medical Telemetry Service,
Medical Implant Communications Service, Low Power Radio Service, and
Multi-Use Radio Service. There are a variety of methods used to license
the spectrum in these rule parts, from licensing by rule, to
conditioning operation on successful completion of a required test, to
site-based licensing, to geographic area licensing. All such entities
in this category are wireless, therefore the Commission applies the
definition of Wireless Telecommunications Carriers (except Satellite),
pursuant to which the SBA's small entity size standard is defined as
those entities employing 1,500 or fewer persons. For this industry,
U.S. Census data for 2012 show that there were 967 firms that operated
for the entire year. Of this total, 955 firms had employment of 999 or
fewer employees and 12 had employment of 1,000 employees or more. Thus,
under this category and the associated size standard, the Commission
estimates that the majority of firms can be considered small. The
Commission notes however that many of the licensees in this category
are individuals and not small entities. In addition, due to the mostly
unlicensed and shared nature of the spectrum utilized in many of these
services, the Commission lacks direct information upon which to base an
estimation of the number of small entities that may be affected by the
Commission's actions in this proceeding.
90. Public Safety Radio Licensees. Public Safety Radio Pool
licensees as a general matter, include police, fire, local government,
forestry conservation, highway maintenance, and emergency medical
services. Because of the vast array of public safety licensees, the
Commission has not developed a small business size standard
specifically applicable to public safety licensees. The closest
applicable SBA category is Wireless Telecommunications Carriers (except
Satellite) which encompasses business entities engaged in
radiotelephone communications. The appropriate size standard for this
category under SBA rules is that such a business is small if it has
1,500 or fewer employees. For this industry, U.S. Census data for 2012
show that there were 967 firms that operated for the entire year. Of
this total, 955 firms had employment of 999 or fewer employees and 12
had employment of 1,000 employees or more. Thus under this category and
the associated size standard, the Commission estimates that the
majority of firms can be considered small. With respect to local
governments, in particular, since many governmental entities comprise
the licensees for these services, the Commission includes under public
safety services the number of government entities affected. According
to Commission records, there are a total of approximately 133,870
licenses within these services. There are 3,121 licenses in the 4.9 GHz
band, based on an FCC Universal Licensing System search of March 29,
2017. The Commission estimates that fewer than 2,442 public safety
radio licensees hold these licenses because certain entities may have
multiple licenses.
91. Private Land Mobile Radio Licensees. Private land mobile radio
(PLMR) systems serve an essential role in a vast range of industrial,
business, land transportation, and public safety activities. These
radios are used by companies of all sizes operating in all U.S.
business categories. Because of the vast array of PLMR users, the
Commission has not developed a small business size standard
specifically applicable to PLMR users. The closest applicable SBA
category is Wireless Telecommunications Carriers (except Satellite)
which encompasses business entities engaged in radiotelephone
communications. The appropriate size standard for this category under
SBA
[[Page 51880]]
rules is that such a business is small if it has 1,500 or fewer
employees. For this industry, U.S. Census data for 2012 show that there
were 967 firms that operated for the entire year. Of this total, 955
firms had employment of 999 or fewer employees and 12 had employment of
1,000 employees or more. Thus, under this category and the associated
size standard, the Commission estimates that the majority of PLMR
Licensees are small entities.
92. According to the Commission's records, a total of approximately
400,622 licenses comprise PLMR users. Of this number there are a total
of 3,374 licenses in the frequencies range 173.225 MHz to 173.375 MHz,
which is the range affected by the Third Report and Order. The
Commission does not require PLMR licensees to disclose information
about number of employees and does not have information that could be
used to determine how many PLMR licensees constitute small entities
under this definition. The Commission however believes that a
substantial number of PLMR licensees may be small entities despite the
lack of specific information.
93. Multiple Address Systems. Entities using Multiple Address
Systems (MAS) spectrum, in general, fall into two categories: (1) Those
using the spectrum for profit-based uses, and (2) those using the
spectrum for private internal uses. With respect to the first category,
Profit-based Spectrum use, the size standards established by the
Commission define ``small entity'' for MAS licensees as an entity that
has average annual gross revenues of less than $15 million over the
three previous calendar years. A ``Very small business'' is defined as
an entity that, together with its affiliates, has average annual gross
revenues of not more than $3 million over the preceding three calendar
years. The SBA has approved these definitions. The majority of MAS
operators are licensed in bands where the Commission has implemented a
geographic area licensing approach that requires the use of competitive
bidding procedures to resolve mutually exclusive applications.
94. The Commission's licensing database indicates that, as of April
16, 2010, there were a total of 11,653 site-based MAS station
authorizations. Of these, 58 authorizations were associated with common
carrier service. In addition, the Commission's licensing database
indicates that, as of April 16, 2010, there were a total of 3,330
Economic Area market area MAS authorizations. The Commission's
licensing database also indicates that, as of April 16, 2010, of the
11,653 total MAS station authorizations, 10,773 authorizations were for
private radio service. In 2001, an auction for 5,104 MAS licenses in
176 EAs was conducted. Seven winning bidders claimed status as small or
very small businesses and won 611 licenses. In 2005, the Commission
completed an auction (Auction 59) of 4,226 MAS licenses in the Fixed
Microwave Services from the 928/959 and 932/941 MHz bands. Twenty-six
winning bidders won a total of 2,323 licenses. Of the 26 winning
bidders in this auction, five claimed small business status and won
1,891 licenses.
95. With respect to the second category, Internal Private Spectrum
use consists of entities that use, or seek to use, MAS spectrum to
accommodate their own internal communications needs, MAS serves an
essential role in a range of industrial, safety, business, and land
transportation activities. MAS radios are used by companies of all
sizes, operating in virtually all U.S. business categories, and by all
types of public safety entities. For the majority of private internal
users, the definition developed by the SBA would be more appropriate
than the Commission's definition. The closest applicable definition of
a small entity is the ``Wireless Telecommunications Carriers (except
Satellite)'' definition under the SBA rules. The appropriate size
standard under SBA rules is that such a business is small if it has
1,500 or fewer employees. For this category, U.S. Census data for 2012
show that there were 967 firms that operated for the entire year. Of
this total, 955 firms had employment of 999 or fewer employees and 12
had employment of 1,000 employees or more. Thus, under this category
and the associated small business size standard, the Commission
estimates that the majority of firms that may be affected by the
Commission's action can be considered small.
96. Broadband Radio Service and Educational Broadband Service.
Broadband Radio Service systems, previously referred to as Multipoint
Distribution Service (MDS) and Multichannel Multipoint Distribution
Service (MMDS) systems, and ``wireless cable,'' transmit video
programming to subscribers and provide two-way high-speed data
operations using the microwave frequencies of the Broadband Radio
Service (BRS) and Educational Broadband Service (EBS) (previously
referred to as the Instructional Television Fixed Service (ITFS)).
97. BRS--In connection with the 1996 BRS auction, the Commission
established a small business size standard as an entity that had annual
average gross revenues of no more than $40 million in the previous
three calendar years. The BRS auctions resulted in 67 successful
bidders obtaining licensing opportunities for 493 Basic Trading Areas
(BTAs). Of the 67 auction winners, 61 met the definition of a small
business. BRS also includes licensees of stations authorized prior to
the auction. At this time, the Commission estimates that of the 61
small business BRS auction winners, 48 remain small business licensees.
In addition to the 48 small businesses that hold BTA authorizations,
there are approximately there are approximately 86 incumbent BRS
licensees that are considered small entities (18 incumbent BRS
licensees do not meet the small business size standard). After adding
the number of small business auction licensees to the number of
incumbent licensees not already counted, the Commission finds that
there are currently approximately 133 BRS licensees that are defined as
small businesses under either the SBA or the Commission's rules.
98. In 2009, the Commission conducted Auction 86, the sale of 78
licenses in the BRS areas. The Commission offered three levels of
bidding credits: (i) A bidder with attributed average annual gross
revenues that exceed $15 million and do not exceed $40 million for the
preceding three years (small business) received a 15 percent discount
on its winning bid; (ii) a bidder with attributed average annual gross
revenues that exceed $3 million and do not exceed $15 million for the
preceding three years (very small business) received a 25 percent
discount on its winning bid; and (iii) a bidder with attributed average
annual gross revenues that do not exceed $3 million for the preceding
three years (entrepreneur) received a 35 percent discount on its
winning bid. Auction 86 concluded in 2009 with the sale of 61 licenses.
Of the ten winning bidders, two bidders that claimed small business
status won 4 licenses; one bidder that claimed very small business
status won three licenses; and two bidders that claimed entrepreneur
status won six licenses.
99. EBS--The Educational Broadband Service has been included within
the broad economic census category and SBA size standard for Wired
Telecommunications Carriers since 2007. Wired Telecommunications
Carriers are comprised of establishments primarily engaged in operating
and/or providing access to transmission facilities and infrastructure
that they own and/or lease for the transmission of voice, data, text,
sound, and video using
[[Page 51881]]
wired telecommunications networks. Transmission facilities may be based
on a single technology or a combination of technologies. The SBA's
small business size standard for this category is all such firms having
1,500 or fewer employees. U.S. Census Bureau data for 2012 show that
there were 3,117 firms that operated that year. Of this total, 3,083
operated with fewer than 1,000 employees. Thus, under this size
standard, the majority of firms in this industry can be considered
small. In addition to Census Bureau data, the Commission's Universal
Licensing System indicates that as of October 2014, there are 2,206
active EBS licenses. The Commission estimates that of these 2,206
licenses, the majority are held by non-profit educational institutions
and school districts, which are by statute defined as small businesses.
100. Location and Monitoring Service (LMS). LMS systems use non-
voice radio techniques to determine the location and status of mobile
radio units. For purposes of auctioning LMS licenses, the Commission
has defined a ``small business'' as an entity that, together with
controlling interests and affiliates, has average annual gross revenues
for the preceding three years not to exceed $15 million. A ``very small
business'' is defined as an entity that, together with controlling
interests and affiliates, has average annual gross revenues for the
preceding three years not to exceed $3 million. These definitions have
been approved by the SBA. An auction for LMS licenses commenced on
February 23, 1999 and closed on March 5, 1999. Of the 528 licenses
auctioned, 289 licenses were sold to four small businesses.
101. Television Broadcasting. This Economic Census category
``comprises establishments primarily engaged in broadcasting images
together with sound.'' These establishments operate television
broadcast studios and facilities for the programming and transmission
of programs to the public. These establishments also produce or
transmit visual programming to affiliated broadcast television
stations, which in turn broadcast the programs to the public on a
predetermined schedule. Programming may originate in their own studio,
from an affiliated network, or from external sources. The SBA has
created the following small business size standard for such businesses:
Those having $38.5 million or less in annual receipts. The 2012
Economic Census reports that 751 firms in this category operated in
that year. Of that number, 656 had annual receipts of $25,000,000 or
less, 25 had annual receipts between $25,000,000 and $49,999,999 and 70
had annual receipts of $50,000,000 or more. Based on this data the
Commission therefore estimates that the majority of commercial
television broadcasters are small entities under the applicable SBA
size standard.
102. The Commission has estimated the number of licensed commercial
television stations to be 1,377. Of this total, 1,258 stations (or
about 91 percent) had revenues of $38.5 million or less, according to
Commission staff review of the BIA Kelsey Inc. Media Access Pro
Television Database (BIA) on November 16, 2017, and therefore these
licensees qualify as small entities under the SBA definition. In
addition, the Commission has estimated the number of licensed
noncommercial educational (NCE) television stations to be 384.
Notwithstanding, the Commission does not compile and otherwise does not
have access to information on the revenue of NCE stations that would
permit it to determine how many such stations would qualify as small
entities. There are also 2,300 low power television stations, including
Class A stations (LPTV) and 3,681 TV translator stations. Given the
nature of these services, the Commission will presume that all of these
entities qualify as small entities under the above SBA small business
size standard.
103. The Commission notes, however, that in assessing whether a
business concern qualifies as ``small'' under the above definition,
business (control) affiliations must be included. The Commission
estimates, therefore likely overstates the number of small entities
that might be affected by its action, because the revenue figure on
which it is based does not include or aggregate revenues from
affiliated companies. In addition, another element of the definition of
``small business'' requires that an entity not be dominant in its field
of operation. The Commission is unable at this time to define or
quantify the criteria that would establish whether a specific
television broadcast station is dominant in its field of operation.
Accordingly, the estimate of small businesses to which rules may apply
does not exclude any television station from the definition of a small
business on this basis and is therefore possibly over-inclusive. Also,
as noted above, an additional element of the definition of ``small
business'' is that the entity must be independently owned and operated.
The Commission notes that it is difficult at times to assess these
criteria in the context of media entities and its estimates of small
businesses to which they apply may be over-inclusive to this extent.
104. Radio Stations. This Economic Census category ``comprises
establishments primarily engaged in broadcasting aural programs by
radio to the public. Programming may originate in their own studio,
from an affiliated network, or from external sources.'' The SBA has
established a small business size standard for this category as firms
having $38.5 million or less in annual receipts. Economic Census data
for 2012 show that 2,849 radio station firms operated during that year.
Of that number, 2,806 operated with annual receipts of less than $25
million per year, 17 with annual receipts between $25 million and
$49,999,999 million and 26 with annual receipts of $50 million or more.
Therefore, based on the SBA's size standard the majority of such
entities are small entities.
105. According to Commission staff review of the BIA/Kelsey, LLC's
Publications, Inc. Media Access Pro Radio Database (BIA) as of January
2018, about 11,261 (or about 99.92 percent) of 11,270 commercial radio
stations had revenues of $38.5 million or less and thus qualify as
small entities under the SBA definition. The Commission has estimated
the number of licensed commercial AM radio stations to be 4,633
stations and the number of commercial FM radio stations to be 6,738,
for a total number of 11,371. The Commission notes, that the Commission
has also estimated the number of licensed NCE radio stations to be
4,128. Nevertheless, the Commission does not compile and otherwise does
not have access to information on the revenue of NCE stations that
would permit it to determine how many such stations would qualify as
small entities.
106. The Commission also notes, that in assessing whether a
business entity qualifies as small under the above definition, business
control affiliations must be included. The Commission's estimate
therefore likely overstates the number of small entities that might be
affected by its action, because the revenue figure on which it is based
does not include or aggregate revenues from affiliated companies. In
addition, to be determined a ``small business,'' an entity may not be
dominant in its field of operation. The Commission further notes, that
it is difficult at times to assess these criteria in the context of
media entities, and the estimate of small businesses to which these
rules may apply does not exclude any radio station from the definition
of a small business on these basis, thus the Commission's estimate of
small businesses may therefore be over-inclusive. Also, as noted above,
an additional element of the definition of ``small business'' is that
[[Page 51882]]
the entity must be independently owned and operated. The Commission
notes that it is difficult at times to assess these criteria in the
context of media entities and the estimates of small businesses to
which they apply may be over-inclusive to this extent.
107. FM Translator Stations and Low Power FM Stations. FM
translators and Low Power FM Stations are classified in the category of
Radio Stations and are assigned the same NAICS Code as licensees of
radio stations. This U.S. industry, Radio Stations, comprises
establishments primarily engaged in broadcasting aural programs by
radio to the public. Programming may originate in their own studio,
from an affiliated network, or from external sources. The SBA has
established a small business size standard which consists of all radio
stations whose annual receipts are $38.5 million dollars or less. U.S.
Census Bureau data for 2012 indicate that 2,849 radio station firms
operated during that year. Of that number, 2,806 operated with annual
receipts of less than $25 million per year, 17 with annual receipts
between $25 million and $49,999,999 million and 26 with annual receipts
of $50 million or more. Therefore, based on the SBA's size standard,
the Commission concludes that the majority of FM Translator Stations
and Low Power FM Stations are small.
108. Multichannel Video Distribution and Data Service (MVDDS).
MVDDS is a terrestrial fixed microwave service operating in the 12.2-
12.7 GHz band. The Commission adopted criteria for defining three
groups of small businesses for purposes of determining their
eligibility for special provisions such as bidding credits. It defined
a very small business as an entity with average annual gross revenues
not exceeding $3 million for the preceding three years; a small
business as an entity with average annual gross revenues not exceeding
$15 million for the preceding three years; and an entrepreneur as an
entity with average annual gross revenues not exceeding $40 million for
the preceding three years. These definitions were approved by the SBA.
On January 27, 2004, the Commission completed an auction of 214 MVDDS
licenses (Auction No. 53). In this auction, ten winning bidders won a
total of 192 MVDDS licenses. Eight of the ten winning bidders claimed
small business status and won 144 of the licenses. The Commission also
held an auction of MVDDS licenses on December 7, 2005 (Auction 63). Of
the three winning bidders who won 22 licenses, two winning bidders,
winning 21 of the licenses, claimed small business status.
109. Satellite Telecommunications. This category comprises firms
``primarily engaged in providing telecommunications services to other
establishments in the telecommunications and broadcasting industries by
forwarding and receiving communications signals via a system of
satellites or reselling satellite telecommunications.'' Satellite
telecommunications service providers include satellite and earth
station operators. The category has a small business size standard of
$32.5 million or less in average annual receipts, under SBA rules. For
this category, U.S. Census Bureau data for 2012 show that there were a
total of 333 firms that operated for the entire year. Of this total,
299 firms had annual receipts of less than $25 million. Consequently,
the Commission estimates that the majority of satellite
telecommunications providers are small entities.
110. All Other Telecommunications. The ``All Other
Telecommunications'' category is comprised of establishments that are
primarily engaged in providing specialized telecommunications services,
such as satellite tracking, communications telemetry, and radar station
operation. This industry also includes establishments primarily engaged
in providing satellite terminal stations and associated facilities
connected with one or more terrestrial systems and capable of
transmitting telecommunications to, and receiving telecommunications
from, satellite systems. Establishments providing internet services or
voice over internet protocol (VoIP) services via client-supplied
telecommunications connections are also included in this industry. The
SBA has developed a small business size standard for ``All Other
Telecommunications,'' which consists of all such firms with gross
annual receipts of $32.5 million or less. For this category, U.S.
Census data for 2012 show that there were 1,442 firms that operated for
the entire year. Of these firms, a total of 1,400 had gross annual
receipts of less than $25 million and 42 firms had annual receipts of
$25 million to $49,999,999. Thus, a majority of ``All Other
Telecommunications'' firms potentially affected by the Commission's
action can be considered small.
111. Fixed Microwave Services. Microwave services include common
carrier, private-operational fixed, and broadcast auxiliary radio
services. They also include the Local Multipoint Distribution Service
(LMDS), the Digital Electronic Message Service (DEMS), the 39 GHz
Service (39 GHz), the 24 GHz Service, and the Millimeter Wave Service
where licensees can choose between common carrier and non-common
carrier status. At present, there are approximately 66,680 common
carrier fixed licensees, 69,360 private and public safety operational-
fixed licensees, 20,150 broadcast auxiliary radio licensees, 411 LMDS
licenses, 33 24 GHz DEMS licenses, 777 39 GHz licenses, and five 24 GHz
licenses, and 467 Millimeter Wave licenses in the microwave services.
The Commission has not yet defined a small business size standard for
microwave services. The closest applicable SBA category is Wireless
Telecommunications Carriers (except Satellite) and the appropriate size
standard for this category under SBA rules is that such a business is
small if it has 1,500 or fewer employees. U.S. Census Bureau data for
2012, show that there were 967 firms in this category that operated for
the entire year. Of this total, 955 had employment of 999 or fewer, and
12 firms had employment of 1,000 employees or more. Thus, under this
category and the associated small business size standard, the
Commission estimates that a majority of fixed microwave service
licensees can be considered small.
112. The Commission notes that the number of firms does not
necessarily track the number of licensees. The Commission also notes
that it does not have data specifying the number of these licensees
that have more than 1,500 employees, and thus is unable at this time to
estimate with greater precision the number of fixed microwave service
licensees that would qualify as small business concerns under the SBA's
small business size standard. The Commission estimates however, that
virtually all of the Fixed Microwave licensees (excluding broadcast
auxiliary licensees) would qualify as small entities under the SBA
definition.
113. Non-Licensee Owners of Towers and Other Infrastructure.
Although at one time most communications towers were owned by the
licensee using the tower to provide communications service, many towers
are now owned by third-party businesses that do not provide
communications services themselves but lease space on their towers to
other companies that provide communications services. The Commission's
rules require that any entity, including a non-licensee, proposing to
construct a tower over 200 feet in height or within the glide slope of
an airport must register the tower with the Commission's Antenna
Structure Registration (``ASR'') system and comply with applicable
rules
[[Page 51883]]
regarding review for impact on the environment and historic properties.
114. As of March 1, 2017, the ASR database includes approximately
122,157 registration records reflecting a ``Constructed'' status and
13,987 registration records reflecting a ``Granted, Not Constructed''
status. These figures include both towers registered to licensees and
towers registered to non-licensee tower owners. The Commission does not
keep information from which we can easily determine how many of these
towers are registered to non-licensees or how many non-licensees have
registered towers. Regarding towers that do not require ASR
registration, we do not collect information as to the number of such
towers in use and therefore cannot estimate the number of tower owners
that would be subject to the rules on which the Commission seeks
comment. Moreover, the SBA has not developed a size standard for small
businesses in the category ``Tower Owners.'' Therefore, the Commission
is unable to determine the number of non-licensee tower owners that are
small entities. The Commission believes, however, that when all
entities owning 10 or fewer towers and leasing space for collocation
are included, non-licensee tower owners number in the thousands. In
addition, there may be other non-licensee owners of other wireless
infrastructure, including Distributed Antenna Systems (DAS) and small
cells that might be affected by the measures on which the Commission
seeks comment. The Commission does not have any basis for estimating
the number of such non-licensee owners that are small entities.
115. The closest applicable SBA category is All Other
Telecommunications, and the appropriate size standard consists of all
such firms with gross annual receipts of $32.5 million or less. For
this category, U.S. Census data for 2012 show that there were 1,442
firms that operated for the entire year. Of these firms, a total of
1,400 had gross annual receipts of less than $25 million and 15 firms
had annual receipts of $25 million to $49,999,999. Thus, under this SBA
size standard a majority of the firms potentially affected by the
Commission's action can be considered small.
5. Description of Projected Reporting, Recordkeeping, and Other
Compliance Requirements for Small Entities
116. The Third Report and Order does not establish any reporting,
recordkeeping, or other compliance requirements for companies involved
in wireless infrastructure deployment. In addition to not adopting any
reporting, recordkeeping or other compliance requirements, the
Commission takes significant steps to reduce regulatory impediments to
infrastructure deployment and, therefore, to spur the growth of
personal wireless services. Under the Commission's approach, small
entities as well as large companies will be assured that their
deployment requests will be acted upon within a reasonable period of
time and, if their applications are not addressed within the
established time frames, applicants may seek injunctive relief granting
their siting applications. The Commission, therefore, has taken
concrete steps to relieve companies of all sizes of uncertainly and has
eliminated unnecessary delays.
117. The Third Report and Order also does not impose any reporting
or recordkeeping requirements on state and local governments. While
some commenters argue that additional shot clock classifications would
make the siting process needlessly complex without any proven benefits,
the Commission concludes that any additional administrative burden from
increasing the number of Section 332 shot clocks from two to four is
outweighed by the likely significant benefit of regulatory certainty
and the resulting streamlined deployment process. The Commission's
actions are consistent with the statutory language of Section 332 and
therefore reflect Congressional intent. Further, siting agencies have
become more efficient in processing siting applications and will be
able to take advantage of these efficiencies in meeting the new shot
clocks. As a result, the additional shot clocks that the Commission
adopts will foster the deployment of the latest wireless technology and
serve consumer interests.
6. Steps Taken To Minimize the Significant Economic Impact on Small
Entities, and Significant Alternatives Considered
118. The RFA requires an agency to describe any significant
alternatives that it has considered in reaching its approach, which may
include the following four alternatives (among others): ``(1) The
establishment of differing compliance or reporting requirements or
timetables that take into account the resources available to small
entities; (2) the clarification, consolidation, or simplification of
compliance and reporting requirements under the rule for such small
entities; (3) the use of performance rather than design standards; and
(4) an exemption from coverage of the rule, or any part thereof, for
such small entities.''
119. The steps taken by the Commission in the Third Report and
Order eliminate regulatory burdens for small entities as well as large
companies that are involved with the deployment of person wireless
services infrastructure. By establishing shot clocks and guidance on
injunctive relief for personal wireless services infrastructure
deployments, the Commission has standardized and streamlined the
permitting process. These changes will significantly minimize the
economic burden of the siting process on all entities, including small
entities, involved in deploying personal wireless services
infrastructure. The record shows that permitting delays imposes
significant economic and financial burdens on companies with pending
wireless infrastructure permits. Eliminating permitting delays will
remove the associated cost burdens and enabling significant public
interest benefits by speeding up the deployment of personal wireless
services and infrastructure. In addition, siting agencies will be able
to utilize the efficiencies that they have gained over the years
processing siting applications to minimize financial impacts.
120. The Commission considered but did not adopt proposals by
commenters to issue ``Best Practices'' or ``Recommended Practices,''
and to develop an informal dispute resolution process and mediation
program, noting that the steps taken in the Third Report and Order
address the concerns underlying these proposals to facilitate
cooperation between parties to reach mutually agreed upon solutions.
The Commission anticipates that the changes it has made to the
permitting process will provide significant efficiencies in the
deployment of personal wireless services facilities and this in turn
will benefit all companies, but particularly small entities, that may
not have the resources and economies of scale of larger entities to
navigate the permitting process. By adopting these changes, the
Commission will continue to fulfill its statutory responsibilities,
while reducing the burden on small entities by removing unnecessary
impediments to the rapid deployment of personal wireless services
facilities and infrastructure across the country.
7. Report to Congress
121. The Commission will send a copy of the Third Report and Order,
including this FRFA, in a report to Congress pursuant to the
Congressional Review Act. In addition, the
[[Page 51884]]
Commission will send a copy of the Third Report and Order, including
this FRFA, to the Chief Counsel for Advocacy of the SBA. A copy of the
Third Report and Order and FRFA (or summaries thereof) also will be
published in the Federal Register.
B. Paperwork Reduction Act
122. This Third Report and Order does not contain new or revised
information collection requirements subject to the Paperwork Reduction
Act of 1995 (PRA), Public Law 104-13.
C. Congressional Review Act
123. The Commission will send a copy of this Declaratory Ruling and
Third Report and Order in a report to be sent to Congress and the
Government Accountability Office pursuant to the Congressional Review
Act (CRA), see 5 U.S.C. 801(a)(1)(A).
IV. Ordering Clauses
124. Accordingly, it is ordered, pursuant to sections 1, 4(i)-(j),
7, 201, 253, 301, 303, 309, 319, and 332 of the Communications Act of
1934, as amended, 47 U.S.C. 151, 154(i)-(j), 157, 201, 253, 301, 303,
309, 319, 332, that this Declaratory Ruling and Third Report and Order
in WT Docket No. 17-79 is hereby adopted.
125. It is further ordered that part 1 of the Commission's rules is
amended as set forth in the final rules of this Declaratory Ruling and
Third Report and Order, and that these changes shall be effective
January 14, 2019.
126. It is further ordered that this Third Report and Order shall
be effective January 14, 2019. The Declaratory Ruling and the
obligations set forth therein are effective on the same day that this
Third Report and Order becomes effective. It is our intention in
adopting the foregoing Declaratory Ruling and these rule changes that,
if any provision of the Declaratory Ruling or the rules, or the
application thereof to any person or circumstance, is held to be
unlawful, the remaining portions of such Declaratory Ruling and the
rules not deemed unlawful, and the application of such Declaratory
Ruling and the rules to other person or circumstances, shall remain in
effect to the fullest extent permitted by law.
127. It is further ordered that, pursuant to 47 CFR 1.4(b)(1), the
period for filing petitions for reconsideration or petitions for
judicial review of this Declaratory Ruling and Third Report and Order
will commence on the date that a summary of this Declaratory Ruling and
Third Report and Order is published in the Federal Register.
128. It is further ordered that the Commission's Consumer &
Governmental Affairs Bureau, Reference Information Center, shall send a
copy of this Declaratory Ruling and Third Report and Order, including
the Final Regulatory Flexibility Analysis, to the Chief Counsel for
Advocacy of the Small Business Administration.
129. It is further ordered that this Declaratory Ruling and Third
Report and Order shall be sent to Congress and the Government
Accountability Office pursuant to the Congressional Review Act, see 5
U.S.C. 801(a)(1)(A).
List of Subjects in 47 CFR Part 1
Communications common carriers, Communications equipment,
Environmental protection, Historic preservation, Radio,
Telecommunications.
Federal Communications Commission.
Cecilia Sigmund,
Federal Register Liaison Officer, Office of the Secretary.
Final Rules
For the reasons discussed in the preamble, the Federal
Communications Commission amends 47 CFR part 1 as follows:
PART 1--PRACTICE AND PROCEDURE
0
1. The authority citation for part 1 continues to read as follows:
Authority: 47 U.S.C. chs. 2, 5, 9, 13; Sec. 102(c), Div. P,
Public Law 115-141, 132 Stat. 1084; 28 U.S.C. 2461, unless otherwise
noted.
0
2. Add subpart U, consisting of Sec. Sec. 1.6001 through 1.6003, to
read as follows:
Subpart U--State and Local Government Regulation of the Placement,
Construction, and Modification of Personal Wireless Service
Facilities
Sec.
1.6001 Purpose.
1.6002 Definitions.
1.6003 Reasonable periods of time to act on siting applications.
Sec. 1.6001 Purpose.
This subpart implements 47 U.S.C. 332(c)(7) and 1455.
Sec. 1.6002 Definitions.
Terms not specifically defined in this section or elsewhere in this
subpart have the meanings defined in this part and the Communications
Act of 1934, 47 U.S.C. 151 et seq. Terms used in this subpart have the
following meanings:
(a) Action or to act on a siting application means a siting
authority's grant of a siting application or issuance of a written
decision denying a siting application.
(b) Antenna, consistent with Sec. 1.1320(d), means an apparatus
designed for the purpose of emitting radiofrequency (RF) radiation, to
be operated or operating from a fixed location pursuant to Commission
authorization, for the provision of personal wireless service and any
commingled information services. For purposes of this definition, the
term antenna does not include an unintentional radiator, mobile
station, or device authorized under part 15 of this chapter.
(c) Antenna equipment, consistent with Sec. 1.1320(d), means
equipment, switches, wiring, cabling, power sources, shelters or
cabinets associated with an antenna, located at the same fixed location
as the antenna, and, when collocated on a structure, is mounted or
installed at the same time as such antenna.
(d) Antenna facility means an antenna and associated antenna
equipment.
(e) Applicant means a person or entity that submits a siting
application and the agents, employees, and contractors of such person
or entity.
(f) Authorization means any approval that a siting authority must
issue under applicable law prior to the deployment of personal wireless
service facilities, including, but not limited to, zoning approval and
building permit.
(g) Collocation, consistent with Sec. 1.1320(d) and the Nationwide
Programmatic Agreement (NPA) for the Collocation of Wireless Antennas,
appendix B of this part, section I.B, means--
(1) Mounting or installing an antenna facility on a pre-existing
structure; and/or
(2) Modifying a structure for the purpose of mounting or installing
an antenna facility on that structure.
(3) The definition of ``collocation'' in Sec. 1.6100(b)(2) applies
to the term as used in that section.
(h) Deployment means placement, construction, or modification of a
personal wireless service facility.
(i) Facility or personal wireless service facility means an antenna
facility or a structure that is used for the provision of personal
wireless service, whether such service is provided on a stand-alone
basis or commingled with other wireless communications services.
(j) Siting application or application means a written submission to
a siting authority requesting authorization for the deployment of a
personal wireless service facility at a specified location.
[[Page 51885]]
(k) Siting authority means a State government, local government, or
instrumentality of a State government or local government, including
any official or organizational unit thereof, whose authorization is
necessary prior to the deployment of personal wireless service
facilities.
(l) Small wireless facilities, consistent with Sec. 1.1312(e)(2),
are facilities that meet each of the following conditions:
(1) The facilities--
(i) Are mounted on structures 50 feet or less in height including
their antennas as defined in Sec. 1.1320(d); or
(ii) Are mounted on structures no more than 10 percent taller than
other adjacent structures; or
(iii) Do not extend existing structures on which they are located
to a height of more than 50 feet or by more than 10 percent, whichever
is greater;
(2) Each antenna associated with the deployment, excluding
associated antenna equipment (as defined in the definition of
``antenna'' in Sec. 1.1320(d)), is no more than three cubic feet in
volume;
(3) All other wireless equipment associated with the structure,
including the wireless equipment associated with the antenna and any
pre-existing associated equipment on the structure, is no more than 28
cubic feet in volume;
(4) The facilities do not require antenna structure registration
under part 17 of this chapter;
(5) The facilities are not located on Tribal lands, as defined
under 36 CFR 800.16(x); and
(6) The facilities do not result in human exposure to
radiofrequency radiation in excess of the applicable safety standards
specified in Sec. 1.1307(b).
(m) Structure means a pole, tower, base station, or other building,
whether or not it has an existing antenna facility, that is used or to
be used for the provision of personal wireless service (whether on its
own or comingled with other types of services).
Sec. 1.6003 Reasonable periods of time to act on siting
applications.
(a) Timely action required. A siting authority that fails to act on
a siting application on or before the shot clock date for the
application, as defined in paragraph (e) of this section, is presumed
not to have acted within a reasonable period of time.
(b) Shot clock period. The shot clock period for a siting
application is the sum of--
(1) The number of days of the presumptively reasonable period of
time for the pertinent type of application, pursuant to paragraph (c)
of this section; plus
(2) The number of days of the tolling period, if any, pursuant to
paragraph (d) of this section.
(c) Presumptively reasonable periods of time--(1) Review periods
for individual applications. The following are the presumptively
reasonable periods of time for action on applications seeking
authorization for deployments in the categories set forth in paragraphs
(c)(1)(i) through (iv) of this section:
(i) Review of an application to collocate a Small Wireless Facility
using an existing structure: 60 days.
(ii) Review of an application to collocate a facility other than a
Small Wireless Facility using an existing structure: 90 days.
(iii) Review of an application to deploy a Small Wireless Facility
using a new structure: 90 days.
(iv) Review of an application to deploy a facility other than a
Small Wireless Facility using a new structure: 150 days.
(2) Batching. (i) If a single application seeks authorization for
multiple deployments, all of which fall within a category set forth in
either paragraph (c)(1)(i) or (iii) of this section, then the
presumptively reasonable period of time for the application as a whole
is equal to that for a single deployment within that category.
(ii) If a single application seeks authorization for multiple
deployments, the components of which are a mix of deployments that fall
within paragraph (c)(1)(i) of this section and deployments that fall
within paragraph (c)(1)(iii) of this section, then the presumptively
reasonable period of time for the application as a whole is 90 days.
(iii) Siting authorities may not refuse to accept applications
under paragraphs (c)(2)(i) and (ii) of this section.
(d) Tolling period. Unless a written agreement between the
applicant and the siting authority provides otherwise, the tolling
period for an application (if any) is as set forth in paragraphs (d)(1)
through (3) of this section.
(1) For an initial application to deploy Small Wireless Facilities,
if the siting authority notifies the applicant on or before the 10th
day after submission that the application is materially incomplete, and
clearly and specifically identifies the missing documents or
information and the specific rule or regulation creating the obligation
to submit such documents or information, the shot clock date
calculation shall restart at zero on the date on which the applicant
submits all the documents and information identified by the siting
authority to render the application complete.
(2) For all other initial applications, the tolling period shall be
the number of days from--
(i) The day after the date when the siting authority notifies the
applicant in writing that the application is materially incomplete and
clearly and specifically identifies the missing documents or
information that the applicant must submit to render the application
complete and the specific rule or regulation creating this obligation;
until
(ii) The date when the applicant submits all the documents and
information identified by the siting authority to render the
application complete;
(iii) But only if the notice pursuant to paragraph (d)(2)(i) of
this section is effectuated on or before the 30th day after the date
when the application was submitted; or
(3) For resubmitted applications following a notice of deficiency,
the tolling period shall be the number of days from--
(i) The day after the date when the siting authority notifies the
applicant in writing that the applicant's supplemental submission was
not sufficient to render the application complete and clearly and
specifically identifies the missing documents or information that need
to be submitted based on the siting authority's original request under
paragraph (d)(1) or (2) of this section; until
(ii) The date when the applicant submits all the documents and
information identified by the siting authority to render the
application complete;
(iii) But only if the notice pursuant to paragraph (d)(3)(i) of
this section is effectuated on or before the 10th day after the date
when the applicant makes a supplemental submission in response to the
siting authority's request under paragraph (d)(1) or (2) of this
section.
(e) Shot clock date. The shot clock date for a siting application
is determined by counting forward, beginning on the day after the date
when the application was submitted, by the number of calendar days of
the shot clock period identified pursuant to paragraph (b) of this
section and including any pre-application period asserted by the siting
authority; provided, that if the date calculated in this manner is a
``holiday'' as defined in Sec. 1.4(e)(1) or a legal holiday within the
relevant State or local jurisdiction, the shot clock date is the next
business day after such date. The term ``business day'' means any day
as defined in Sec. 1.4(e)(2) and any day that is not a legal holiday
as defined by the State or local jurisdiction.
[[Page 51886]]
Sec. 1.40001 [Redesignated as Sec. 1.6100 and Amended]
0
3. Redesignate Sec. 1.40001 as Sec. 1.6100 and, in newly redesignated
Sec. 1.6100, remove and reserve paragraph (a).
Subpart CC--[Removed]
0
4. Remove subpart CC.
[FR Doc. 2018-22234 Filed 10-12-18; 8:45 am]
BILLING CODE 6712-01-P