Combined Notice of Filings #1, 49554-49555 [2018-21411]
Download as PDF
amozie on DSK3GDR082PROD with NOTICES1
49554
Federal Register / Vol. 83, No. 191 / Tuesday, October 2, 2018 / Notices
Comments Due: 5 p.m. ET 10/9/18.
Docket Numbers: RP18–1215–000.
Applicants: Fayetteville Express
Pipeline LLC.
Description: § 4(d) Rate Filing:
Negotiated Rate Service Agreement on
9–25–18 to be effective 9/28/2018.
Filed Date: 9/25/18.
Accession Number: 20180925–5054.
Comments Due: 5 p.m. ET 10/9/18.
Docket Numbers: RP18–1216–000.
Applicants: Texas Eastern
Transmission, LP.
Description: § 4(d) Rate Filing:
Negotiated Rate—Eco-Energy 8953069
eff 10–1–18 to be effective 10/1/2018.
Filed Date: 9/25/18.
Accession Number: 20180925–5055.
Comments Due: 5 p.m. ET 10/9/18.
Docket Numbers: RP18–1217–000.
Applicants: Columbia Gas
Transmission, LLC.
Description: § 4(d) Rate Filing: TCO
WBX NR and NC Agreements to be
effective 10/25/2018.
Filed Date: 9/25/18.
Accession Number: 20180925–5118.
Comments Due: 5 p.m. ET 10/9/18.
Docket Numbers: RP18–1218–000.
Applicants: Dominion Energy Cove
Point LNG, LP.
Description: eTariff filing per 1430:
DECP—Request for Waiver of
Requirement to File Form No. 501–G.
Filed Date: 9/25/18.
Accession Number: 20180925–5121.
Comments Due: 5 p.m. ET 10/9/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: September 26, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–21412 Filed 10–1–18; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:16 Oct 01, 2018
Jkt 247001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC18–162–000.
Applicants: Mendota Hills, LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Mendota
Hills, LLC.
Filed Date: 9/25/18.
Accession Number: 20180925–5133.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: EC18–163–000.
Applicants: San Diego Gas & Electric
Company, Citizens SycamorePenasquitos Transmission.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of San Diego Gas &
Electric Company, et. al.
Filed Date: 9/26/18.
Accession Number: 20180926–5034.
Comments Due: 5 p.m. ET 10/17/18.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER18–1883–001.
Applicants: Midcontinent
Independent System Operator, Inc.,
Michigan Electric Transmission
Company, LLC.
Description: Compliance filing: 2018–
09–26_SA 3132 Compliance Filing for
METC-Wolverine T–T to be effective
6/1/2018.
Filed Date: 9/26/18.
Accession Number: 20180926–5072.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18–1974–001.
Applicants: Otter Tail Power
Company.
Description: Compliance filing:
Compliance Notification of Effective
Date to be effective 9/17/2018.
Filed Date: 9/26/18.
Accession Number: 20180926–5086.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18–2013–000.
Applicants: Terra-Gen Dixie Valley,
LLC.
Description: Report Filing: Refund
Report to be effective N/A.
Filed Date: 9/25/18.
Accession Number: 20180925–5096.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2474–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Attachment V GIA Pro Forma Clean-Up
Filing to be effective 5/15/2018.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
Filed Date: 9/25/18.
Accession Number: 20180925–5120.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2475–000.
Applicants: Imperial Valley Solar 3,
LLC.
Description: § 205(d) Rate Filing:
Imperial Valley Solar 3, LLC CoTenancy and Shared Use Agreement to
be effective 9/26/2018.
Filed Date: 9/25/18.
Accession Number: 20180925–5122.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2476–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Historical Cleanup Filing, MISO–PJM
JOA, Section 9.4 to be effective 1/1/
2014.
Filed Date: 9/25/18.
Accession Number: 20180925–5098.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2477–000.
Applicants: DXT Commodities North
America LLC.
Description: Baseline eTariff Filing:
Application for Market Based Rate to be
effective 11/25/2018.
Filed Date: 9/25/18.
Accession Number: 20180925–5097.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2478–000.
Applicants: Southwestern Public
Service Company.
Description: Notice of cancellation of
Interconnection Agreement (No. 102–
SPS) of Southwestern Public Service
Company.
Filed Date: 9/25/18.
Accession Number: 20180925–5138.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18–2479–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Third Revised ISA, SA No. 2962; Queue
No. Z2–083 to be effective 8/28/2018.
Filed Date: 9/26/18.
Accession Number: 20180926–5039.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18–2480–000.
Applicants: Michigan Electric
Transmission Company, LLC.
Description: Tariff Cancellation:
Termination of Agreements to be
effective 6/1/2018.
Filed Date: 9/26/18.
Accession Number: 20180926–5074.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18–2481–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) Rate Filing:
PSCo-WAPA-Intercon-TSA-Agrmt-376–
0.1.0 to be effective 10/1/2018.
Filed Date: 9/26/18.
E:\FR\FM\02OCN1.SGM
02OCN1
Federal Register / Vol. 83, No. 191 / Tuesday, October 2, 2018 / Notices
Accession Number: 20180926–5095.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18–2482–000.
Applicants: Wolverine Power Supply
Cooperative, Inc.
Description: Tariff Cancellation:
Notice of Cancellation of Rate Schedules
to be effective 9/27/2018.
Filed Date: 9/26/18.
Accession Number: 20180926–5113.
Comments Due: 5 p.m. ET 10/17/18.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES18–62–000.
Applicants: Oklahoma Gas and
Electric Company.
Description: Application under
Section 204 of the Federal Power Act for
Authorization to Issue Securities of
Oklahoma Gas and Electric Company.
Filed Date: 9/26/18.
Accession Number: 20180926–5088.
Comments Due: 5 p.m. ET 10/17/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: September 26, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–21411 Filed 10–1–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
amozie on DSK3GDR082PROD with NOTICES1
[Project No. 11834–068]
Notice of Application for Amendment
of License, Soliciting Comments,
Motions To Intervene, and Protests;
Brookfield White Pine Hydro, LLC
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
VerDate Sep<11>2014
17:16 Oct 01, 2018
Jkt 247001
a. Type of Proceeding: Application for
amendment of license.
b. Project No.: 11834–068.
c. Date Filed: August 28, 2018.
d. Licensee: Brookfield White Pine
Hydro, LLC.
e. Name of Project: Upper and Middle
Dams Storage Project.
f. Location: The project is located on
the Rapid River in Oxford and Franklin
counties, Maine.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a—825r.
h. Licensee Contact: Ms. Kelly
Maloney, Brookfield Renewable, 150
Main Street, Lewiston, ME, (207) 233–
1995, Kelly.maloney@
brookfieldrenewable.com.
i. FERC Contact: Ms. Rebecca Martin,
(202) 502–6012, Rebecca.martin@
ferc.gov.
j. Deadline for filing comments,
interventions, and protests is 30 days
from the issuance date of this notice by
the Commission. The Commission
strongly encourages electronic filing.
Please file motions to intervene, protests
and comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–11834–068.
k. Description of Project Facilities:
The project includes two developments:
Upper Dam, which impounds
Mooselookmeguntic Lake, and Middle
Dam, which impounds Richardson
Lake. The two dams operate as a single
water storage project to regulate flows to
the Androscoggin River for downstream
hydroelectric generation, reduction of
flood flows, and other beneficial uses.
The proposed work would only occur at
Middle Dam. Project works at the
Middle Dam Development consist of the
244-foot-long Middle Dam equipped
with a gatehouse containing: (a) Three
15-foot-wide by 12-foot-deep sluice
gates: (b) five 6-foot-wide by 14.7-footdeep gates; (c) six 7-foot-wide 14.7-footdeep shoal gates; and (d) six 9-foot-wide
by 12.3-foot deep spillway gates; a 560foot-long earthen dike extending north
of the gatehouse; a 200-foot-long earthen
dike extending south of the gatehouse;
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
49555
the 7,470 acre reservoir; the 180-footlong earthen dike (Black Cat Dike)
located 2,000 feet to the southeast of
Middle Dam; and appurtenant facilities.
l. Description of Request: The licensee
has filed a copy of its application with
the Maine Land Use Planning
Commission and the US Army Corps of
Engineers for its proposed replacement
of the spillway at the Middle Dam
Development. Replacement of the
Middle Dam Development spillway is
being required under Part 12 of the
Commission’s regulations for safety of
water power projects and project works.
The proposal involves a multi-year,
phased approach beginning with the
installation of a bypass gate to pass all
river flow during the removal of the
existing dam and installation of the new
dam. Black Cat Dike embankment
would also be modified to meet
Commission requirements. The
proposed measures would not alter the
basic footprint of the existing dam or
involve substantial modification of the
licensed operation of the project. Work
is proposed to begin in May 2019 and
be completed by December 15, 2023.
m. This filing may be viewed on the
Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction in the Commission’s
Public Reference Room located at 888
First Street NE, Room 2A, Washington,
DC 20426, or by calling (202) 502–8371.
n. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
o. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .212
and .214. In determining the appropriate
action to take, the Commission will
consider all protests or other comments
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
E:\FR\FM\02OCN1.SGM
02OCN1
Agencies
[Federal Register Volume 83, Number 191 (Tuesday, October 2, 2018)]
[Notices]
[Pages 49554-49555]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-21411]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC18-162-000.
Applicants: Mendota Hills, LLC.
Description: Application for Authorization Under Section 203 of the
Federal Power Act, et al. of Mendota Hills, LLC.
Filed Date: 9/25/18.
Accession Number: 20180925-5133.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: EC18-163-000.
Applicants: San Diego Gas & Electric Company, Citizens Sycamore-
Penasquitos Transmission.
Description: Joint Application for Authorization Under Section 203
of the Federal Power Act of San Diego Gas & Electric Company, et. al.
Filed Date: 9/26/18.
Accession Number: 20180926-5034.
Comments Due: 5 p.m. ET 10/17/18.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER18-1883-001.
Applicants: Midcontinent Independent System Operator, Inc.,
Michigan Electric Transmission Company, LLC.
Description: Compliance filing: 2018-09-26_SA 3132 Compliance
Filing for METC-Wolverine T-T to be effective 6/1/2018.
Filed Date: 9/26/18.
Accession Number: 20180926-5072.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18-1974-001.
Applicants: Otter Tail Power Company.
Description: Compliance filing: Compliance Notification of
Effective Date to be effective 9/17/2018.
Filed Date: 9/26/18.
Accession Number: 20180926-5086.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18-2013-000.
Applicants: Terra-Gen Dixie Valley, LLC.
Description: Report Filing: Refund Report to be effective N/A.
Filed Date: 9/25/18.
Accession Number: 20180925-5096.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2474-000.
Applicants: Southwest Power Pool, Inc.
Description: Sec. 205(d) Rate Filing: Attachment V GIA Pro Forma
Clean-Up Filing to be effective 5/15/2018.
Filed Date: 9/25/18.
Accession Number: 20180925-5120.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2475-000.
Applicants: Imperial Valley Solar 3, LLC.
Description: Sec. 205(d) Rate Filing: Imperial Valley Solar 3, LLC
Co-Tenancy and Shared Use Agreement to be effective 9/26/2018.
Filed Date: 9/25/18.
Accession Number: 20180925-5122.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2476-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Historical Cleanup Filing,
MISO-PJM JOA, Section 9.4 to be effective 1/1/2014.
Filed Date: 9/25/18.
Accession Number: 20180925-5098.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2477-000.
Applicants: DXT Commodities North America LLC.
Description: Baseline eTariff Filing: Application for Market Based
Rate to be effective 11/25/2018.
Filed Date: 9/25/18.
Accession Number: 20180925-5097.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2478-000.
Applicants: Southwestern Public Service Company.
Description: Notice of cancellation of Interconnection Agreement
(No. 102-SPS) of Southwestern Public Service Company.
Filed Date: 9/25/18.
Accession Number: 20180925-5138.
Comments Due: 5 p.m. ET 10/16/18.
Docket Numbers: ER18-2479-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Third Revised ISA, SA No.
2962; Queue No. Z2-083 to be effective 8/28/2018.
Filed Date: 9/26/18.
Accession Number: 20180926-5039.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18-2480-000.
Applicants: Michigan Electric Transmission Company, LLC.
Description: Tariff Cancellation: Termination of Agreements to be
effective 6/1/2018.
Filed Date: 9/26/18.
Accession Number: 20180926-5074.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18-2481-000.
Applicants: Public Service Company of Colorado.
Description: Sec. 205(d) Rate Filing: PSCo-WAPA-Intercon-TSA-
Agrmt-376-0.1.0 to be effective 10/1/2018.
Filed Date: 9/26/18.
[[Page 49555]]
Accession Number: 20180926-5095.
Comments Due: 5 p.m. ET 10/17/18.
Docket Numbers: ER18-2482-000.
Applicants: Wolverine Power Supply Cooperative, Inc.
Description: Tariff Cancellation: Notice of Cancellation of Rate
Schedules to be effective 9/27/2018.
Filed Date: 9/26/18.
Accession Number: 20180926-5113.
Comments Due: 5 p.m. ET 10/17/18.
Take notice that the Commission received the following electric
securities filings:
Docket Numbers: ES18-62-000.
Applicants: Oklahoma Gas and Electric Company.
Description: Application under Section 204 of the Federal Power Act
for Authorization to Issue Securities of Oklahoma Gas and Electric
Company.
Filed Date: 9/26/18.
Accession Number: 20180926-5088.
Comments Due: 5 p.m. ET 10/17/18.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: September 26, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-21411 Filed 10-1-18; 8:45 am]