Notice of Availability of Final Environmental Assessment; Great Lakes Hydro America, LLC, 49378 [2018-21277]
Download as PDF
49378
Federal Register / Vol. 83, No. 190 / Monday, October 1, 2018 / Notices
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by July 31, 2021.
o. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: September 24, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–21279 Filed 9–28–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL18–204–000]
amozie on DSK3GDR082PROD with NOTICES
Notice of Amended Complaint;
Louisiana Public Service Commission
v. System Energy Resources, Inc.;
Entergy Services, Inc.
Take notice that on September 24,
2018, pursuant to Rule 206 of the
Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR 385.206
and sections 206, 306, and 309 of the
Federal Power Act, 16 U.S.C. 824e,
825e, and 825h, the Louisiana Public
Service Commission (Complainant) filed
an amended complaint (Amended
Complaint) against System Energy
Resources, Inc. and Entergy Services,
Inc., (collectively, Respondents). The
Amended Complaint provides
additional facts alleging that System
Energy Resources, Inc. does not qualify
under the Commission’s capital
structure test for acceptance of its actual
capital structure, as more fully
explained in the Complaint.
The Complainant certifies that copies
of the Complaint were served on
contacts for the Respondents.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondents’ answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondents’ answer, motions to
VerDate Sep<11>2014
17:50 Sep 28, 2018
Jkt 247001
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on October 15, 2018.
DATED: September 25, 2018.
Kimberly D. Bose,
Secretary.
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
[Project No. 2520–076]
Notice of Availability of Final
Environmental Assessment; Great
Lakes Hydro America, LLC
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for license for the
Mattaceunk Hydroelectric Project,
located on the Penobscot River in
Aroostook and Penobscot Counties,
Maine, and has prepared a Final
Environmental Assessment (FEA) for
the project. The project does not occupy
federal land.
The FEA contains Commission staff’s
analysis of the potential environmental
effects of the project, and concludes that
licensing the project, with appropriate
environmental protective measures,
would not constitute a major federal
action that would significantly affect the
quality of the human environment.
A copy of the FEA is available for
review at the Commission in the Public
Fmt 4703
Sfmt 4703
[FR Doc. 2018–21277 Filed 9–28–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
[Docket No. EL18–205–000]
Notice of Petition for Declaratory
Order; Sunrun, Inc.
DEPARTMENT OF ENERGY
Frm 00026
Dated: September 25, 2018.
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2018–21278 Filed 9–28–18; 8:45 am]
PO 00000
Reference Room, or may be viewed on
the Commission’s website at https://
www.ferc.gov, using the ‘‘eLibrary’’ link.
Enter the docket number, excluding the
last three digits in the docket number
field, to access the document. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
For further information, contact Adam
Peer at (202) 502–8449.
Take notice that on September 24,
2018, pursuant to Rule 207(a)(2) of the
Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR
385.207(a), Sunrun, Inc. (Sunrun or
Petitioner) filed a petition for
declaratory order (petition) requesting
waiver of qualifying facility (QF)
certification filing requirements for
residential solar photovoltaic systems,
irrespective of whether such systems
aggregate to over one megawatt (1 MW)
within one mile, all as more fully
explained in the petition.
Any person desiring to intervene or to
protest in this proceeding must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
E:\FR\FM\01OCN1.SGM
01OCN1
Agencies
[Federal Register Volume 83, Number 190 (Monday, October 1, 2018)]
[Notices]
[Page 49378]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-21277]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2520-076]
Notice of Availability of Final Environmental Assessment; Great
Lakes Hydro America, LLC
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380, the Office of Energy Projects has
reviewed the application for license for the Mattaceunk Hydroelectric
Project, located on the Penobscot River in Aroostook and Penobscot
Counties, Maine, and has prepared a Final Environmental Assessment
(FEA) for the project. The project does not occupy federal land.
The FEA contains Commission staff's analysis of the potential
environmental effects of the project, and concludes that licensing the
project, with appropriate environmental protective measures, would not
constitute a major federal action that would significantly affect the
quality of the human environment.
A copy of the FEA is available for review at the Commission in the
Public Reference Room, or may be viewed on the Commission's website at
https://www.ferc.gov, using the ``eLibrary'' link. Enter the docket
number, excluding the last three digits in the docket number field, to
access the document. For assistance, contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY).
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
For further information, contact Adam Peer at (202) 502-8449.
Dated: September 25, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-21277 Filed 9-28-18; 8:45 am]