Transcontinental Gas Pipe Line Company, LLC; Notice of Revised Schedule for Environmental Review of the Northeast Supply Enhancement Project, 46153 [2018-19815]

Download as PDF Federal Register / Vol. 83, No. 177 / Wednesday, September 12, 2018 / Notices daltland on DSKBBV9HB2PROD with NOTICES expected to exceed three minutes. Anyone who is not able to attend the meeting, or for whom the allotted public comments time is insufficient to address pertinent issues with the EAC, is invited to send a written statement to Mr. Lawrence Mansueti. You may submit comments, identified by: ‘‘Electricity Advisory Committee Open Meeting,’’ through any of the following methods: • Mail/Hand Delivery/Courier: Lawrence Mansueti, Office of Electricity, U.S. Department of Energy, Forrestal Building, Room 8G– 017, 1000 Independence Avenue SW, Washington, DC 20585. • Email: Lawrence.mansueti@ hq.doe.gov. Include ‘‘Electricity Advisory Committee Open Meeting’’ in the subject line of the message. • Federal eRulemaking Portal: https:// www.regulations.gov. Follow the instructions for submitting comments. Instructions: All submissions received must include the agency name and identifier. All comments received will be posted without change to https:// energy.gov/oe/services/electricityadvisory-committee-eac, including any personal information provided. • Docket: For access to the docket, to read background documents or comments received, go to https:// energy.gov/oe/services/electricityadvisory-committee-eac. The following electronic file formats are acceptable: Microsoft Word (.doc), Corel Word Perfect (.wpd), Adobe Acrobat (.pdf), Rich Text Format (.rtf), plain text (.txt), Microsoft Excel (.xls), and Microsoft PowerPoint (.ppt). If you submit information that you believe to be exempt by law from public disclosure, you must submit one complete copy, as well as one copy from which the information claimed to be exempt by law from public disclosure has been deleted. You must also explain the reasons why you believe the deleted information is exempt from disclosure. DOE is responsible for the final determination concerning disclosure or nondisclosure of the information and for treating it in accordance with the DOE’s Freedom of Information regulations (10 CFR 1004.11). Note: Delivery of the U.S. Postal Service mail to DOE may be delayed by several weeks due to security screening. DOE, therefore, encourages those wishing to comment to submit comments electronically by email. If comments are submitted by regular mail, the Department requests that they be accompanied by a CD or diskette containing electronic files of the submission. Minutes: The minutes of the EAC meeting will be posted on the EAC web page at https://energy.gov/oe/services/ VerDate Sep<11>2014 18:41 Sep 11, 2018 Jkt 244001 electricity-advisory-committee-eac. They can also be obtained by contacting Mr. Lawrence Mansueti at the address above. Signed in Washington, DC on September 6, 2018. Latanya Butler, Deputy Committee Management Officer. [FR Doc. 2018–19829 Filed 9–11–18; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–101–000] Transcontinental Gas Pipe Line Company, LLC; Notice of Revised Schedule for Environmental Review of the Northeast Supply Enhancement Project This notice identifies the Federal Energy Regulatory Commission (FERC or Commission) staff’s revised schedule for the completion of the final environmental impact statement (EIS) for Transcontinental Gas Pipe Line Company, LLC’s (Transco) Northeast Supply Enhancement Project. The first notice of schedule, issued on January 3, 2018, identified September 17, 2018 as the final EIS issuance date. Staff has revised the schedule for issuance of the final EIS based on the current status of Transco’s General Conformity review and feasible mitigation options. The forecasted schedule for the final EIS is also based upon Transco providing complete and timely responses to any future data requests. In addition, the schedule assumes that the cooperating agencies will provide input on their areas of responsibility on a timely basis. Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—January 25, 2019 90-day Federal Authorization Decision Deadline—April 25, 2019 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 46153 summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP17–101–000), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: September 6, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–19815 Filed 9–11–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13318–003] Swan Lake North Hydro LLC; Notice of Anticipated Schedule of Final Order for Swan Lake North Pumped Storage Hydroelectric Project On October 28, 2015, Swan Lake North Hydro LLC filed an application requesting authorization to construct and operate the Swan Lake North Pumped Storage Hydroelectric Project. The project would be located 11 miles northeast of Klamath Falls, in Klamath County, Oregon. In accordance with Title 41 of the Fixing America’s Surface Transportation Act, enacted on December 4, 2015, agencies are to publish completion dates for all federal environmental reviews and authorizations. This notice identifies the Commission’s anticipated schedule for issuance of the final order for the Project, which is based on the anticipated date of issuance of the final Environmental Impact Statement. Accordingly, we currently anticipate issuing a final order for the Project no later than: Issuance of Final Order—April 30, 2019 If a schedule change becomes necessary for the final order, an additional notice will be provided so that interested parties and government E:\FR\FM\12SEN1.SGM 12SEN1

Agencies

[Federal Register Volume 83, Number 177 (Wednesday, September 12, 2018)]
[Notices]
[Page 46153]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-19815]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-101-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of Revised 
Schedule for Environmental Review of the Northeast Supply Enhancement 
Project

    This notice identifies the Federal Energy Regulatory Commission 
(FERC or Commission) staff's revised schedule for the completion of the 
final environmental impact statement (EIS) for Transcontinental Gas 
Pipe Line Company, LLC's (Transco) Northeast Supply Enhancement 
Project. The first notice of schedule, issued on January 3, 2018, 
identified September 17, 2018 as the final EIS issuance date. Staff has 
revised the schedule for issuance of the final EIS based on the current 
status of Transco's General Conformity review and feasible mitigation 
options. The forecasted schedule for the final EIS is also based upon 
Transco providing complete and timely responses to any future data 
requests. In addition, the schedule assumes that the cooperating 
agencies will provide input on their areas of responsibility on a 
timely basis.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--January 25, 2019
90-day Federal Authorization Decision Deadline--April 25, 2019

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP17-101-000), and follow the instructions. For assistance with access 
to eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 
502-8659, or at [email protected]. The eLibrary link on the 
FERC website also provides access to the texts of formal documents 
issued by the Commission, such as orders, notices, and rule makings.

    Dated: September 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19815 Filed 9-11-18; 8:45 am]
 BILLING CODE 6717-01-P