Corpus Christi Liquefaction Stage III, LLC; Corpus Christi Liquefaction, LLC; and Cheniere Corpus Christi Pipeline, L.P.; Notice of Schedule for Environmental Review of the Stage 3 Project, 45433 [2018-19406]
Download as PDF
Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices
Project Description
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP18–512–000, CP18–513–
000]
Corpus Christi Liquefaction Stage III,
LLC; Corpus Christi Liquefaction, LLC;
and Cheniere Corpus Christi Pipeline,
L.P.; Notice of Schedule for
Environmental Review of the Stage 3
Project
daltland on DSKBBV9HB2PROD with NOTICES
On June 28, 2018, Corpus Christi
Liquefaction Stage III, LLC and Corpus
Christi Liquefaction, LLC (collectively
with Cheniere Corpus Christi Pipeline,
L.P. referred to as Cheniere) filed an
application in Docket No. CP18–512–
000 requesting an authorization for
siting, construction, and operation of a
liquefied natural gas (LNG) export
facility pursuant to Section 3(a) of the
Natural Gas Act (NGA). On the same
day, Cheniere Corpus Christi Pipeline,
L.P. filed an application in Docket No.
CP18–513–000 requesting a Certificate
of Public Convenience and Necessity
pursuant to Section 7(c) of the NGA to
construct, operate, and maintain certain
natural gas pipeline facilities.
Combined, the proposed project is
known as the Stage 3 Project (Project)
and would provide gas and processing
to produce up to 11.45 million tonnes
per annum of LNG for export.
On July 12, 2018, the Federal Energy
Regulatory Commission (FERC or
Commission) issued its Notice of
Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
the request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for completion of the
EA for the Project. The forecasted
schedule for the EA is based upon
Cheniere providing complete and timely
responses to any data requests. In
addition, the schedule assumes that the
cooperating agencies will provide input
on their areas of responsibility on a
timely basis.
Schedule for Environmental Review
Issuance of EA: February 8, 2019
90-Day Federal Authorization Decision
Deadline: May 9, 2019
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
VerDate Sep<11>2014
17:55 Sep 06, 2018
Jkt 244001
Cheniere proposes to install seven
mid-scale liquefaction trains and one
new LNG storage tank expanding the
previously authorized and currently
under construction Corpus Christi
Liquefaction Project in Nueces County,
Texas. The proposed LNG facilities
would be located primarily within areas
previously disturbed for construction
and/or operation of the Corpus Christi
Liquefaction Project. Cheniere would
also construct a new 21-mile-long, 42inch-diameter natural gas pipeline from
the recently completed Sinton
Compressor Station (FERC Docket No.
CP12–508–000) to the proposed Stage 3
liquefaction facilities, all of which
would be located within Nueces
County, Texas. The Project would also
include the addition of two compressor
units totaling approximately 44,000
horsepower at the Sinton Compressor
Station. No new marine facilities would
be installed as part of the Project;
however, Cheniere anticipates that an
annual increase of 100 LNG carriers
would utilize the LNG terminal during
operation of the Project.
Background
On June 9, 2015, the Commission staff
granted Cheniere’s request to use the
FERC’s pre-filing environmental review
process and assigned the Stage 3 Project
Docket No. PF15–26–000. On August
17, 2015, the Commission issued a
Notice of Intent to Prepare an
Environmental Assessment for the
Planned Stage 3 Project, and Request for
Comments on Environmental Issues
(NOI). The NOI was issued during the
pre-filing review of the Project in Docket
No. PF15–26–000 and was sent to
federal, state, and local government
agencies; elected officials; affected
landowners; environmental and public
interest groups; Native American tribes
and regional organizations; commenters
and other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission received
comments from the U.S. Fish and
Wildlife Service, U.S. Environmental
Protection Agency, Tonkawa Tribe of
Oklahoma, Federal Emergency
Management Agency, and Texas Parks
and Wildlife Department. The primary
issues raised by the commenters include
effects on threatened and endangered
species and vegetation, water quality
impacts, greenhouse gas emissions, and
cumulative impacts.
The U.S. Department of
Transportation Pipeline and Hazardous
Materials Administration, U.S. Coast
Guard, U.S. Department of Energy, U.S.
Army Corps of Engineers, U.S. Fish and
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
45433
Wildlife Service, and U.S.
Environmental Protection Agency are
cooperating agencies in the preparation
of the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP18–512 and CP18–513), and follow
the instructions. For assistance with
access to eLibrary, the helpline can be
reached at (866) 208–3676, TTY (202)
502–8659, or at FERCOnlineSupport@
ferc.gov. The eLibrary link on the FERC
website also provides access to the texts
of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–19406 Filed 9–6–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–45–000]
Notice of Availability of the
Environmental Assessment for the
Proposed Dominion Energy
Transmission, Inc. Sweden Valley
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared an
environmental assessment (EA) for the
Sweden Valley Project (Project),
proposed by Dominion Energy
Transmission, Inc. (Dominion) in the
above-referenced docket. The Project is
designed to provide 120 million cubic
feet per day of firm transportation
service from an existing point of
interconnection located on Dominion’s
E:\FR\FM\07SEN1.SGM
07SEN1
Agencies
[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Page 45433]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-19406]
[[Page 45433]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP18-512-000, CP18-513-000]
Corpus Christi Liquefaction Stage III, LLC; Corpus Christi
Liquefaction, LLC; and Cheniere Corpus Christi Pipeline, L.P.; Notice
of Schedule for Environmental Review of the Stage 3 Project
On June 28, 2018, Corpus Christi Liquefaction Stage III, LLC and
Corpus Christi Liquefaction, LLC (collectively with Cheniere Corpus
Christi Pipeline, L.P. referred to as Cheniere) filed an application in
Docket No. CP18-512-000 requesting an authorization for siting,
construction, and operation of a liquefied natural gas (LNG) export
facility pursuant to Section 3(a) of the Natural Gas Act (NGA). On the
same day, Cheniere Corpus Christi Pipeline, L.P. filed an application
in Docket No. CP18-513-000 requesting a Certificate of Public
Convenience and Necessity pursuant to Section 7(c) of the NGA to
construct, operate, and maintain certain natural gas pipeline
facilities. Combined, the proposed project is known as the Stage 3
Project (Project) and would provide gas and processing to produce up to
11.45 million tonnes per annum of LNG for export.
On July 12, 2018, the Federal Energy Regulatory Commission (FERC or
Commission) issued its Notice of Application for the Project. Among
other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on the request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for completion of the EA
for the Project. The forecasted schedule for the EA is based upon
Cheniere providing complete and timely responses to any data requests.
In addition, the schedule assumes that the cooperating agencies will
provide input on their areas of responsibility on a timely basis.
Schedule for Environmental Review
Issuance of EA: February 8, 2019
90-Day Federal Authorization Decision Deadline: May 9, 2019
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
Cheniere proposes to install seven mid-scale liquefaction trains
and one new LNG storage tank expanding the previously authorized and
currently under construction Corpus Christi Liquefaction Project in
Nueces County, Texas. The proposed LNG facilities would be located
primarily within areas previously disturbed for construction and/or
operation of the Corpus Christi Liquefaction Project. Cheniere would
also construct a new 21-mile-long, 42-inch-diameter natural gas
pipeline from the recently completed Sinton Compressor Station (FERC
Docket No. CP12-508-000) to the proposed Stage 3 liquefaction
facilities, all of which would be located within Nueces County, Texas.
The Project would also include the addition of two compressor units
totaling approximately 44,000 horsepower at the Sinton Compressor
Station. No new marine facilities would be installed as part of the
Project; however, Cheniere anticipates that an annual increase of 100
LNG carriers would utilize the LNG terminal during operation of the
Project.
Background
On June 9, 2015, the Commission staff granted Cheniere's request to
use the FERC's pre-filing environmental review process and assigned the
Stage 3 Project Docket No. PF15-26-000. On August 17, 2015, the
Commission issued a Notice of Intent to Prepare an Environmental
Assessment for the Planned Stage 3 Project, and Request for Comments on
Environmental Issues (NOI). The NOI was issued during the pre-filing
review of the Project in Docket No. PF15-26-000 and was sent to
federal, state, and local government agencies; elected officials;
affected landowners; environmental and public interest groups; Native
American tribes and regional organizations; commenters and other
interested parties; and local libraries and newspapers. In response to
the NOI, the Commission received comments from the U.S. Fish and
Wildlife Service, U.S. Environmental Protection Agency, Tonkawa Tribe
of Oklahoma, Federal Emergency Management Agency, and Texas Parks and
Wildlife Department. The primary issues raised by the commenters
include effects on threatened and endangered species and vegetation,
water quality impacts, greenhouse gas emissions, and cumulative
impacts.
The U.S. Department of Transportation Pipeline and Hazardous
Materials Administration, U.S. Coast Guard, U.S. Department of Energy,
U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, and U.S.
Environmental Protection Agency are cooperating agencies in the
preparation of the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the eLibrary link, select General
Search from the eLibrary menu, enter the selected date range and Docket
Number excluding the last three digits (i.e., CP18-512 and CP18-513),
and follow the instructions. For assistance with access to eLibrary,
the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or
at FERCOnlin[email protected]. The eLibrary link on the FERC website
also provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rulemakings.
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19406 Filed 9-6-18; 8:45 am]
BILLING CODE 6717-01-P