Notice of Schedule for Environmental Review of the Texas LNG Brownsville LLC Texas LNG Project, 45437-45438 [2018-19390]

Download as PDF Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices instant notice identifies the FERC staff’s planned schedule for completion of the final EIS for the Project, which is based on an issuance of the draft EIS in November 2018. The forecasted schedule for both the draft and final EIS is based upon Plaquemines LNG and Gator Express Pipeline providing complete and timely responses to any future data requests. In addition, the schedule assumes that the cooperating agencies will provide input on their areas of responsibility on a timely basis. Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—May 3, 2019 90-Day Federal Authorization Decision Deadline—August 1, 2019 If a schedule change becomes necessary for the final EIS, an additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Project Description Plaquemines LNG plans to construct an LNG terminal on a 632-acre site on the Mississippi River in Plaquemines Parish, Louisiana. Gator Express Pipeline plans to construct two parallel 42-inch-diameter gas lateral pipelines totaling approximately 26.8 miles, also in Plaquemines Parish, Louisiana. These pipelines would connect the LNG terminal to the existing interstate natural gas grid. Each pipeline would have a nominal gas supply capability of 1.97 standard billion cubic feet per day. The Project would consist of a liquefaction plant, aboveground storage tanks, marine loading berthing docks, a utility dock, and air-cooled electric power generation facilities, in addition to the two lateral pipelines. daltland on DSKBBV9HB2PROD with NOTICES Background On July 2, 2015, the Commission staff granted Plaquemines LNG and Gator Express Pipeline’s request to use the FERC’s pre-filing environmental review process and assigned the Plaquemines LNG and Gator Express Pipeline Project Docket No. PF15–27–000. On October 5, 2015, the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement for the Proposed Plaquemines LNG and Gator Express Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meetings (NOI). On September 14, 2016, the FERC sent a letter to potentially-affected landowners informing them of changes that Plaquemines LNG and Gator Express Pipeline had made to the planned pipelines since the initiation of the prefiling process. VerDate Sep<11>2014 17:55 Sep 06, 2018 Jkt 244001 The NOI and pipeline modification letter were issued during the pre-filing review of the Project in Docket No. PF15–27–000 was sent to federal, state, and local government agencies; elected officials; affected landowners; environmental and public interest groups; Native American tribes and regional organizations; commentors and other interested parties; and local libraries and newspapers. Major issues raised during scoping include potential impacts to the river floodway and the flood protection levee from terminal construction, construction and wetland fill in the Coastal Zone, saltwater intrusion from marsh pipeline construction, impacts on productivity of Barataria Bay estuary, greenhouse gas emissions from project operation, and noise and light pollution impacts on nearby sensitive areas. The U.S. Army Corps of Engineers, U.S. Coast Guard, U.S. Department of Energy, U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration, and U.S. Environmental Protection Agency are cooperating agencies in the preparation of the EIS. Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–66 and CP17–67), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: August 31, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–19394 Filed 9–6–18; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 45437 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP16–116–000] Notice of Schedule for Environmental Review of the Texas LNG Brownsville LLC Texas LNG Project On March 31, 2016, Texas LNG Brownsville LLC (Texas LNG) filed an application in Docket No. CP16–116– 000 requesting authorization pursuant to Section 3(a) of the Natural Gas Act to site, construct, modify, and operate liquefied natural gas (LNG) export facilities located on the Brownsville Ship Channel in Cameron County, Texas. The proposed project is known as the Texas LNG Project (Project) and would include a new LNG export terminal capable of producing up to 4 million tonnes per annum of LNG for export. The terminal would receive natural gas to the export facilities from a third-party intrastate pipeline. On September 24, 2015, in Order No. 3716, the U.S. Department of Energy, Office of Fossil Energy, granted to Texas LNG a long-term, multi-contract authorization to export LNG to Free Trade Agreement nations. On April 14, 2016, the Federal Energy Regulatory Commission (FERC or Commission) issued its Notice of Application for the Project. Among other things, that notice alerted other agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on the request for a federal authorization within 90 days of the date of issuance of the Commission staff’s final Environmental Impact Statement (EIS) for the Texas LNG Project. This instant notice identifies the FERC staff’s planned schedule for completion of the final EIS for the Project, which is based on an issuance of the draft EIS in October 2018. The forecasted schedule for both the draft and final EIS is based upon Texas LNG providing complete and timely responses to any future data requests. In addition, the schedule assumes that the cooperating agencies will provide input on their areas of responsibility on a timely basis. Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—March 15, 2019 90-Day Federal Authorization Decision Deadline—June 13, 2019 If a schedule change becomes necessary for the final EIS, an additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. E:\FR\FM\07SEN1.SGM 07SEN1 45438 Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices Project Description Texas LNG’s proposed facilities include two liquefaction trains, each capable of producing 2 million tonnes per annum, one new LNG storage tank, and a single marine berth capable of accommodating LNG carriers with capacities up to 180,000 cubic meters. The Project would be constructed on about 285 acres of a 625-acre parcel of land, on the north side of the Brownsville Ship Channel near mile marker 4. An additional 26.5 acres would be located outside of the 625-acre parcel to provide deepwater access to the Brownsville Ship Channel. Background On April 14, 2015, the Commission staff granted Texas LNG’s request to use the FERC’s Pre-filing environmental review process and assigned the Texas LNG Project Docket No. PF15–14–000. On July 23, 2015, the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement for the Planned Texas LNG Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting (NOI). The NOI was issued during the prefiling review of the project in Docket No. PF15–14–000 and was sent to federal, state, and local government agencies; elected officials; affected landowners; environmental and public interest groups; Native American tribes and regional organizations; commenters and other interested parties; and local libraries and newspapers. Major issues raised during scoping include threatened and endangered species, LNG safety, land use, water quality, air quality, and cumulative impacts. The U.S. Department of Energy, U.S. Coast Guard, U.S. Department of Transportation, U.S. Army Corps of Engineers, U.S. Environmental Protection Agency, U.S. Fish and Wildlife Service, National Park Service, National Marine Fisheries Service, and Federal Aviation Administration are cooperating agencies in the preparation of the EIS. daltland on DSKBBV9HB2PROD with NOTICES Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. VerDate Sep<11>2014 17:55 Sep 06, 2018 Jkt 244001 Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP16–116), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: August 31, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–19390 Filed 9–6–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–178–000] Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–178), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Notice of Revised Schedule for Environmental Review of the Alaska Gasline Development Corporation Alaska LNG Project Dated: August 31, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. This notice identifies the Federal Energy Regulatory Commission (FERC) staff’s revised schedule for the completion of the environmental impact statement (EIS) for the Alaska LNG Project (Project). The first notice of schedule, issued on March 12, 2018, identified December 9, 2019 as the final EIS issuance date. Staff has revised the schedule for issuance of the final EIS, based on an issuance of the draft EIS in February 2019. The forecasted schedule for both the draft and final EIS is based upon the Alaska Gasline Development Corporation providing complete and timely responses to any future data requests. In addition, the schedule assumes that the cooperating agencies will provide input on their areas of responsibility on a timely basis. BILLING CODE 6717–01–P Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—November 8, 2019 90-Day Federal Authorization Decision Deadline—February 6, 2020 If a schedule change becomes necessary for the final EIS, an additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 [FR Doc. 2018–19401 Filed 9–6–18; 8:45 am] DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC18–145–000. Applicants: Choice Energy, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act, et al. of Choice Energy LLC. Filed Date: 8/29/18. Accession Number: 20180829–5158. Comments Due: 5 p.m. ET 9/19/18. Docket Numbers: EC18–146–000. Applicants: PPL Electric Utilities Corporation. Description: Application for Authorization under Section 203 of the Federal Power Act of PPL Electric Utilities Corporation. Filed Date: 8/30/18. Accession Number: 20180830–5169. Comments Due: 5 p.m. ET 9/20/18. E:\FR\FM\07SEN1.SGM 07SEN1

Agencies

[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Pages 45437-45438]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-19390]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-116-000]


Notice of Schedule for Environmental Review of the Texas LNG 
Brownsville LLC Texas LNG Project

    On March 31, 2016, Texas LNG Brownsville LLC (Texas LNG) filed an 
application in Docket No. CP16-116-000 requesting authorization 
pursuant to Section 3(a) of the Natural Gas Act to site, construct, 
modify, and operate liquefied natural gas (LNG) export facilities 
located on the Brownsville Ship Channel in Cameron County, Texas. The 
proposed project is known as the Texas LNG Project (Project) and would 
include a new LNG export terminal capable of producing up to 4 million 
tonnes per annum of LNG for export. The terminal would receive natural 
gas to the export facilities from a third-party intrastate pipeline. On 
September 24, 2015, in Order No. 3716, the U.S. Department of Energy, 
Office of Fossil Energy, granted to Texas LNG a long-term, multi-
contract authorization to export LNG to Free Trade Agreement nations.
    On April 14, 2016, the Federal Energy Regulatory Commission (FERC 
or Commission) issued its Notice of Application for the Project. Among 
other things, that notice alerted other agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on the request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's final 
Environmental Impact Statement (EIS) for the Texas LNG Project. This 
instant notice identifies the FERC staff's planned schedule for 
completion of the final EIS for the Project, which is based on an 
issuance of the draft EIS in October 2018. The forecasted schedule for 
both the draft and final EIS is based upon Texas LNG providing complete 
and timely responses to any future data requests. In addition, the 
schedule assumes that the cooperating agencies will provide input on 
their areas of responsibility on a timely basis.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--March 15, 2019

90-Day Federal Authorization Decision Deadline--June 13, 2019

    If a schedule change becomes necessary for the final EIS, an 
additional notice will be provided so that the relevant agencies are 
kept informed of the Project's progress.

[[Page 45438]]

Project Description

    Texas LNG's proposed facilities include two liquefaction trains, 
each capable of producing 2 million tonnes per annum, one new LNG 
storage tank, and a single marine berth capable of accommodating LNG 
carriers with capacities up to 180,000 cubic meters. The Project would 
be constructed on about 285 acres of a 625-acre parcel of land, on the 
north side of the Brownsville Ship Channel near mile marker 4. An 
additional 26.5 acres would be located outside of the 625-acre parcel 
to provide deepwater access to the Brownsville Ship Channel.

Background

    On April 14, 2015, the Commission staff granted Texas LNG's request 
to use the FERC's Pre-filing environmental review process and assigned 
the Texas LNG Project Docket No. PF15-14-000. On July 23, 2015, the 
Commission issued a Notice of Intent to Prepare an Environmental Impact 
Statement for the Planned Texas LNG Project, Request for Comments on 
Environmental Issues, and Notice of Public Scoping Meeting (NOI).
    The NOI was issued during the pre-filing review of the project in 
Docket No. PF15-14-000 and was sent to federal, state, and local 
government agencies; elected officials; affected landowners; 
environmental and public interest groups; Native American tribes and 
regional organizations; commenters and other interested parties; and 
local libraries and newspapers. Major issues raised during scoping 
include threatened and endangered species, LNG safety, land use, water 
quality, air quality, and cumulative impacts.
    The U.S. Department of Energy, U.S. Coast Guard, U.S. Department of 
Transportation, U.S. Army Corps of Engineers, U.S. Environmental 
Protection Agency, U.S. Fish and Wildlife Service, National Park 
Service, National Marine Fisheries Service, and Federal Aviation 
Administration are cooperating agencies in the preparation of the EIS.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP16-116), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19390 Filed 9-6-18; 8:45 am]
 BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.