Notice of Schedule for Environmental Review of the Texas LNG Brownsville LLC Texas LNG Project, 45437-45438 [2018-19390]
Download as PDF
Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices
instant notice identifies the FERC staff’s
planned schedule for completion of the
final EIS for the Project, which is based
on an issuance of the draft EIS in
November 2018. The forecasted
schedule for both the draft and final EIS
is based upon Plaquemines LNG and
Gator Express Pipeline providing
complete and timely responses to any
future data requests. In addition, the
schedule assumes that the cooperating
agencies will provide input on their
areas of responsibility on a timely basis.
Schedule for Environmental Review
Issuance of Notice of Availability of the
final EIS—May 3, 2019
90-Day Federal Authorization Decision
Deadline—August 1, 2019
If a schedule change becomes
necessary for the final EIS, an additional
notice will be provided so that the
relevant agencies are kept informed of
the Project’s progress.
Project Description
Plaquemines LNG plans to construct
an LNG terminal on a 632-acre site on
the Mississippi River in Plaquemines
Parish, Louisiana. Gator Express
Pipeline plans to construct two parallel
42-inch-diameter gas lateral pipelines
totaling approximately 26.8 miles, also
in Plaquemines Parish, Louisiana. These
pipelines would connect the LNG
terminal to the existing interstate
natural gas grid. Each pipeline would
have a nominal gas supply capability of
1.97 standard billion cubic feet per day.
The Project would consist of a
liquefaction plant, aboveground storage
tanks, marine loading berthing docks, a
utility dock, and air-cooled electric
power generation facilities, in addition
to the two lateral pipelines.
daltland on DSKBBV9HB2PROD with NOTICES
Background
On July 2, 2015, the Commission staff
granted Plaquemines LNG and Gator
Express Pipeline’s request to use the
FERC’s pre-filing environmental review
process and assigned the Plaquemines
LNG and Gator Express Pipeline Project
Docket No. PF15–27–000. On October 5,
2015, the Commission issued a Notice of
Intent to Prepare an Environmental
Impact Statement for the Proposed
Plaquemines LNG and Gator Express
Pipeline Project, Request for Comments
on Environmental Issues, and Notice of
Public Scoping Meetings (NOI). On
September 14, 2016, the FERC sent a
letter to potentially-affected landowners
informing them of changes that
Plaquemines LNG and Gator Express
Pipeline had made to the planned
pipelines since the initiation of the prefiling process.
VerDate Sep<11>2014
17:55 Sep 06, 2018
Jkt 244001
The NOI and pipeline modification
letter were issued during the pre-filing
review of the Project in Docket No.
PF15–27–000 was sent to federal, state,
and local government agencies; elected
officials; affected landowners;
environmental and public interest
groups; Native American tribes and
regional organizations; commentors and
other interested parties; and local
libraries and newspapers. Major issues
raised during scoping include potential
impacts to the river floodway and the
flood protection levee from terminal
construction, construction and wetland
fill in the Coastal Zone, saltwater
intrusion from marsh pipeline
construction, impacts on productivity of
Barataria Bay estuary, greenhouse gas
emissions from project operation, and
noise and light pollution impacts on
nearby sensitive areas.
The U.S. Army Corps of Engineers,
U.S. Coast Guard, U.S. Department of
Energy, U.S. Department of
Transportation Pipeline and Hazardous
Materials Safety Administration, and
U.S. Environmental Protection Agency
are cooperating agencies in the
preparation of the EIS.
Additional Information
In order to receive notification of the
issuance of the EIS and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP17–66 and CP17–67), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–19394 Filed 9–6–18; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
45437
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP16–116–000]
Notice of Schedule for Environmental
Review of the Texas LNG Brownsville
LLC Texas LNG Project
On March 31, 2016, Texas LNG
Brownsville LLC (Texas LNG) filed an
application in Docket No. CP16–116–
000 requesting authorization pursuant
to Section 3(a) of the Natural Gas Act to
site, construct, modify, and operate
liquefied natural gas (LNG) export
facilities located on the Brownsville
Ship Channel in Cameron County,
Texas. The proposed project is known
as the Texas LNG Project (Project) and
would include a new LNG export
terminal capable of producing up to 4
million tonnes per annum of LNG for
export. The terminal would receive
natural gas to the export facilities from
a third-party intrastate pipeline. On
September 24, 2015, in Order No. 3716,
the U.S. Department of Energy, Office of
Fossil Energy, granted to Texas LNG a
long-term, multi-contract authorization
to export LNG to Free Trade Agreement
nations.
On April 14, 2016, the Federal Energy
Regulatory Commission (FERC or
Commission) issued its Notice of
Application for the Project. Among
other things, that notice alerted other
agencies issuing federal authorizations
of the requirement to complete all
necessary reviews and to reach a final
decision on the request for a federal
authorization within 90 days of the date
of issuance of the Commission staff’s
final Environmental Impact Statement
(EIS) for the Texas LNG Project. This
instant notice identifies the FERC staff’s
planned schedule for completion of the
final EIS for the Project, which is based
on an issuance of the draft EIS in
October 2018. The forecasted schedule
for both the draft and final EIS is based
upon Texas LNG providing complete
and timely responses to any future data
requests. In addition, the schedule
assumes that the cooperating agencies
will provide input on their areas of
responsibility on a timely basis.
Schedule for Environmental Review
Issuance of Notice of Availability of the
final EIS—March 15, 2019
90-Day Federal Authorization Decision
Deadline—June 13, 2019
If a schedule change becomes
necessary for the final EIS, an additional
notice will be provided so that the
relevant agencies are kept informed of
the Project’s progress.
E:\FR\FM\07SEN1.SGM
07SEN1
45438
Federal Register / Vol. 83, No. 174 / Friday, September 7, 2018 / Notices
Project Description
Texas LNG’s proposed facilities
include two liquefaction trains, each
capable of producing 2 million tonnes
per annum, one new LNG storage tank,
and a single marine berth capable of
accommodating LNG carriers with
capacities up to 180,000 cubic meters.
The Project would be constructed on
about 285 acres of a 625-acre parcel of
land, on the north side of the
Brownsville Ship Channel near mile
marker 4. An additional 26.5 acres
would be located outside of the 625-acre
parcel to provide deepwater access to
the Brownsville Ship Channel.
Background
On April 14, 2015, the Commission
staff granted Texas LNG’s request to use
the FERC’s Pre-filing environmental
review process and assigned the Texas
LNG Project Docket No. PF15–14–000.
On July 23, 2015, the Commission
issued a Notice of Intent to Prepare an
Environmental Impact Statement for the
Planned Texas LNG Project, Request for
Comments on Environmental Issues,
and Notice of Public Scoping Meeting
(NOI).
The NOI was issued during the prefiling review of the project in Docket
No. PF15–14–000 and was sent to
federal, state, and local government
agencies; elected officials; affected
landowners; environmental and public
interest groups; Native American tribes
and regional organizations; commenters
and other interested parties; and local
libraries and newspapers. Major issues
raised during scoping include
threatened and endangered species,
LNG safety, land use, water quality, air
quality, and cumulative impacts.
The U.S. Department of Energy, U.S.
Coast Guard, U.S. Department of
Transportation, U.S. Army Corps of
Engineers, U.S. Environmental
Protection Agency, U.S. Fish and
Wildlife Service, National Park Service,
National Marine Fisheries Service, and
Federal Aviation Administration are
cooperating agencies in the preparation
of the EIS.
daltland on DSKBBV9HB2PROD with NOTICES
Additional Information
In order to receive notification of the
issuance of the EIS and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
VerDate Sep<11>2014
17:55 Sep 06, 2018
Jkt 244001
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP16–116), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–19390 Filed 9–6–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–178–000]
Additional Information
In order to receive notification of the
issuance of the EIS and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP17–178), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Notice of Revised Schedule for
Environmental Review of the Alaska
Gasline Development Corporation
Alaska LNG Project
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
This notice identifies the Federal
Energy Regulatory Commission (FERC)
staff’s revised schedule for the
completion of the environmental impact
statement (EIS) for the Alaska LNG
Project (Project). The first notice of
schedule, issued on March 12, 2018,
identified December 9, 2019 as the final
EIS issuance date. Staff has revised the
schedule for issuance of the final EIS,
based on an issuance of the draft EIS in
February 2019. The forecasted schedule
for both the draft and final EIS is based
upon the Alaska Gasline Development
Corporation providing complete and
timely responses to any future data
requests. In addition, the schedule
assumes that the cooperating agencies
will provide input on their areas of
responsibility on a timely basis.
BILLING CODE 6717–01–P
Schedule for Environmental Review
Issuance of Notice of Availability of the
final EIS—November 8, 2019
90-Day Federal Authorization Decision
Deadline—February 6, 2020
If a schedule change becomes
necessary for the final EIS, an additional
notice will be provided so that the
relevant agencies are kept informed of
the Project’s progress.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
[FR Doc. 2018–19401 Filed 9–6–18; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC18–145–000.
Applicants: Choice Energy, LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Choice
Energy LLC.
Filed Date: 8/29/18.
Accession Number: 20180829–5158.
Comments Due: 5 p.m. ET 9/19/18.
Docket Numbers: EC18–146–000.
Applicants: PPL Electric Utilities
Corporation.
Description: Application for
Authorization under Section 203 of the
Federal Power Act of PPL Electric
Utilities Corporation.
Filed Date: 8/30/18.
Accession Number: 20180830–5169.
Comments Due: 5 p.m. ET 9/20/18.
E:\FR\FM\07SEN1.SGM
07SEN1
Agencies
[Federal Register Volume 83, Number 174 (Friday, September 7, 2018)]
[Notices]
[Pages 45437-45438]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-19390]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP16-116-000]
Notice of Schedule for Environmental Review of the Texas LNG
Brownsville LLC Texas LNG Project
On March 31, 2016, Texas LNG Brownsville LLC (Texas LNG) filed an
application in Docket No. CP16-116-000 requesting authorization
pursuant to Section 3(a) of the Natural Gas Act to site, construct,
modify, and operate liquefied natural gas (LNG) export facilities
located on the Brownsville Ship Channel in Cameron County, Texas. The
proposed project is known as the Texas LNG Project (Project) and would
include a new LNG export terminal capable of producing up to 4 million
tonnes per annum of LNG for export. The terminal would receive natural
gas to the export facilities from a third-party intrastate pipeline. On
September 24, 2015, in Order No. 3716, the U.S. Department of Energy,
Office of Fossil Energy, granted to Texas LNG a long-term, multi-
contract authorization to export LNG to Free Trade Agreement nations.
On April 14, 2016, the Federal Energy Regulatory Commission (FERC
or Commission) issued its Notice of Application for the Project. Among
other things, that notice alerted other agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on the request for a federal authorization
within 90 days of the date of issuance of the Commission staff's final
Environmental Impact Statement (EIS) for the Texas LNG Project. This
instant notice identifies the FERC staff's planned schedule for
completion of the final EIS for the Project, which is based on an
issuance of the draft EIS in October 2018. The forecasted schedule for
both the draft and final EIS is based upon Texas LNG providing complete
and timely responses to any future data requests. In addition, the
schedule assumes that the cooperating agencies will provide input on
their areas of responsibility on a timely basis.
Schedule for Environmental Review
Issuance of Notice of Availability of the final EIS--March 15, 2019
90-Day Federal Authorization Decision Deadline--June 13, 2019
If a schedule change becomes necessary for the final EIS, an
additional notice will be provided so that the relevant agencies are
kept informed of the Project's progress.
[[Page 45438]]
Project Description
Texas LNG's proposed facilities include two liquefaction trains,
each capable of producing 2 million tonnes per annum, one new LNG
storage tank, and a single marine berth capable of accommodating LNG
carriers with capacities up to 180,000 cubic meters. The Project would
be constructed on about 285 acres of a 625-acre parcel of land, on the
north side of the Brownsville Ship Channel near mile marker 4. An
additional 26.5 acres would be located outside of the 625-acre parcel
to provide deepwater access to the Brownsville Ship Channel.
Background
On April 14, 2015, the Commission staff granted Texas LNG's request
to use the FERC's Pre-filing environmental review process and assigned
the Texas LNG Project Docket No. PF15-14-000. On July 23, 2015, the
Commission issued a Notice of Intent to Prepare an Environmental Impact
Statement for the Planned Texas LNG Project, Request for Comments on
Environmental Issues, and Notice of Public Scoping Meeting (NOI).
The NOI was issued during the pre-filing review of the project in
Docket No. PF15-14-000 and was sent to federal, state, and local
government agencies; elected officials; affected landowners;
environmental and public interest groups; Native American tribes and
regional organizations; commenters and other interested parties; and
local libraries and newspapers. Major issues raised during scoping
include threatened and endangered species, LNG safety, land use, water
quality, air quality, and cumulative impacts.
The U.S. Department of Energy, U.S. Coast Guard, U.S. Department of
Transportation, U.S. Army Corps of Engineers, U.S. Environmental
Protection Agency, U.S. Fish and Wildlife Service, National Park
Service, National Marine Fisheries Service, and Federal Aviation
Administration are cooperating agencies in the preparation of the EIS.
Additional Information
In order to receive notification of the issuance of the EIS and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the eLibrary link, select General
Search from the eLibrary menu, enter the selected date range and Docket
Number excluding the last three digits (i.e., CP16-116), and follow the
instructions. For assistance with access to eLibrary, the helpline can
be reached at (866) 208-3676, TTY (202) 502-8659, or at
[email protected]. The eLibrary link on the FERC website also
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rule makings.
Dated: August 31, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19390 Filed 9-6-18; 8:45 am]
BILLING CODE 6717-01-P