Panhandle Eastern Pipe Line Company, LP; Notice of Request Under Blanket Authorization, 44613-44614 [2018-18957]
Download as PDF
daltland on DSKBBV9HB2PROD with NOTICES
Federal Register / Vol. 83, No. 170 / Friday, August 31, 2018 / Notices
Description: § 205(d) Rate Filing:
Canaan Station—Interconnection
Agreement to be effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5100.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2297–000.
Applicants: Public Service Company
of New Hampshire.
Description: § 205(d) Rate Filing:
Eastman Falls Station—Interconnection
Agreement to be effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5102.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2298–000.
Applicants: Public Service Company
of New Hampshire.
Description: § 205(d) Rate Filing:
Garvins Falls/Hooksett Station—
Interconnection Agreement to be
effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5104.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2299–000.
Applicants: Public Service Company
of New Hampshire.
Description: § 205(d) Rate Filing:
Gorham Station—Interconnection
Agreement to be effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5106.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2300–000.
Applicants: Public Service Company
of New Hampshire.
Description: § 205(d) Rate Filing:
Jackman Station—Interconnection
Agreement to be effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5108.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2301–000.
Applicants: Public Service Company
of New Hampshire.
Description: § 205(d) Rate Filing:
Smith Station—Interconnection
Agreement to be effective 8/26/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5110.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2302–000.
Applicants: The United Illuminating
Company.
Description: § 205(d) Rate Filing:
Localized Costs Sharing Agreement No.
18 to be effective 1/1/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5127.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2303–000.
Applicants: Adams Wind Farm, LLC.
Description: Baseline eTariff Filing:
MBR Tariff Filing of Adams Wind Farm
LLC to be effective 10/24/2018.
Filed Date: 8/24/18.
VerDate Sep<11>2014
18:42 Aug 30, 2018
Jkt 244001
Accession Number: 20180824–5161.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2304–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing: BPA
Hermiston Interchange Move Agmt to be
effective 8/25/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5162.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2305–000.
Applicants: Bobilli BSS, LLC.
Description: Baseline eTariff Filing:
MBR Tariff Filing of Bobilli BSS, LLC to
be effective 10/24/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5165.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2306–000.
Applicants: Garwind, LLC.
Description: Baseline eTariff Filing:
MBR Tariff Filing of Garwind, LLC to be
effective 10/24/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5168.
Comments Due: 5 p.m. ET 9/14/18.
Docket Numbers: ER18–2307–000.
Applicants: Appalachian Power
Company, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
Appalachian Power submits revised
ILDSA, Service Agreement No. 1252 to
be effective 8/1/2018.
Filed Date: 8/24/18.
Accession Number: 20180824–5171.
Comments Due: 5 p.m. ET 9/14/18.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES18–45–000.
Applicants: Allegheny Generating
Company.
Description: Supplement to July 6,
2018 Application for Authorization
Under Section 204(a) of the Federal
Power Act to Issue Debt, et al. of
Allegheny Generating Company.
Filed Date: 8/23/18.
Accession Number: 20180823–5160.
Comments Due: 5 p.m. ET 9/4/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
44613
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: August 24, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–18956 Filed 8–30–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–540–000]
Panhandle Eastern Pipe Line
Company, LP; Notice of Request Under
Blanket Authorization
Take notice that on August 17, 2018,
Panhandle Eastern Pipe Line Company,
LP (Panhandle), 1300 Main Street,
Houston, Texas 77002, filed in Docket
No. CP18–540–000, a Prior Notice
Request pursuant to sections 157.205,
and 157.216 of the Commission’s
regulations under the Natural Gas Act
(NGA), and Panhandle’s blanket
certificate issued in Docket No. CP83–
83–000, requesting approval to abandon
by sale to ETC Field Services LLC, the
Deer Loop Lateral Facilities, consisting
of approximately 20.64 miles of 12.75inch diameter pipeline and
appurtenances, located in Carson,
Hutchinson and Moore Counties, Texas
(Deer Loop Lateral Abandonment
Project).
The Deer Loop Lateral was originally
constructed to transport high-pressure
gas from Panhandle’s Deer Compressor
Station to its Sneed Compressor Station,
allowing existing Deer to Sneed
facilities to operate as a lower-pressure
gathering system.1 Over the years,
Panhandle abandoned or spun off its
facilities located upstream of the Deer
Loop Lateral when Panhandle
abandoned its gathering function.
Available supply in the vicinity
upstream of the Deer Loop Lateral has
steadily declined, and in recent years,
the line has transported no significant
volume. On June 1, 2018, Panhandle
and ETC Field Services executed an
Asset Sale Agreement (Agreement) in
which Panhandle agreed to sell the Deer
Loop Lateral to ETC Field Services.
Panhandle states that, upon
Commission approval and closing of the
sale, ETC Field Services will physically
integrate the Deer Loop Lateral into its
non-jurisdictional gathering operations.
1 Panhandle Eastern Pipe Line Company, 3 FERC
61,099 (1978); 6 FERC 61,180 (1978).
E:\FR\FM\31AUN1.SGM
31AUN1
daltland on DSKBBV9HB2PROD with NOTICES
44614
Federal Register / Vol. 83, No. 170 / Friday, August 31, 2018 / Notices
Panhandle states that authorization of
the requested abandonment will allow it
to avoid the operating and maintenance
costs associated with these facilities and
allow ETC Field Services to avoid
construction of duplicative pipeline
facilities and allow the continued use of
existing pipeline facilities as part of its
non-jurisdictional gathering system all
as more fully set forth in the application
which is on file with the Commission
and open to public inspection. The
filing may also be viewed on the web at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions regarding this prior
notice request may be directed to Blair
Lichtenwalter, Senior Director,
Certificates, Panhandle Eastern Pipe
Line Company, LP, by phone at (713)
989–2605 or by email at
blair.lichtenwalter@energytransfer.com
or Irma S. Jarrett, Manager, Certificates,
Panhandle Eastern Pipe Line Company,
LP, 1300 Main Street, Houston, Texas
77002 by phone at (713) 989–7679
(telephone), or by email at irma.jarrett@
energytransfer.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules (18 CFR 157.9),
within 90 days of this Notice, the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
VerDate Sep<11>2014
18:42 Aug 30, 2018
Jkt 244001
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and seven
copies of the protest or intervention to
the Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426.
Dated: August 24, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–18957 Filed 8–30–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER18–2306–000]
Garwind, LLC; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced proceeding Garwind,
LLC’s application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
PO 00000
Frm 00053
Fmt 4703
Sfmt 9990
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is September
17, 2018.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: August 27, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–18944 Filed 8–30–18; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\31AUN1.SGM
31AUN1
Agencies
[Federal Register Volume 83, Number 170 (Friday, August 31, 2018)]
[Notices]
[Pages 44613-44614]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-18957]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-540-000]
Panhandle Eastern Pipe Line Company, LP; Notice of Request Under
Blanket Authorization
Take notice that on August 17, 2018, Panhandle Eastern Pipe Line
Company, LP (Panhandle), 1300 Main Street, Houston, Texas 77002, filed
in Docket No. CP18-540-000, a Prior Notice Request pursuant to sections
157.205, and 157.216 of the Commission's regulations under the Natural
Gas Act (NGA), and Panhandle's blanket certificate issued in Docket No.
CP83-83-000, requesting approval to abandon by sale to ETC Field
Services LLC, the Deer Loop Lateral Facilities, consisting of
approximately 20.64 miles of 12.75-inch diameter pipeline and
appurtenances, located in Carson, Hutchinson and Moore Counties, Texas
(Deer Loop Lateral Abandonment Project).
The Deer Loop Lateral was originally constructed to transport high-
pressure gas from Panhandle's Deer Compressor Station to its Sneed
Compressor Station, allowing existing Deer to Sneed facilities to
operate as a lower-pressure gathering system.\1\ Over the years,
Panhandle abandoned or spun off its facilities located upstream of the
Deer Loop Lateral when Panhandle abandoned its gathering function.
Available supply in the vicinity upstream of the Deer Loop Lateral has
steadily declined, and in recent years, the line has transported no
significant volume. On June 1, 2018, Panhandle and ETC Field Services
executed an Asset Sale Agreement (Agreement) in which Panhandle agreed
to sell the Deer Loop Lateral to ETC Field Services. Panhandle states
that, upon Commission approval and closing of the sale, ETC Field
Services will physically integrate the Deer Loop Lateral into its non-
jurisdictional gathering operations.
[[Page 44614]]
Panhandle states that authorization of the requested abandonment will
allow it to avoid the operating and maintenance costs associated with
these facilities and allow ETC Field Services to avoid construction of
duplicative pipeline facilities and allow the continued use of existing
pipeline facilities as part of its non-jurisdictional gathering system
all as more fully set forth in the application which is on file with
the Commission and open to public inspection. The filing may also be
viewed on the web at https://www.ferc.gov using the eLibrary link. Enter
the docket number excluding the last three digits in the docket number
field to access the document. For assistance, please contact FERC
Online Support at [email protected] or toll free at (866) 208-
3676, or TTY, contact (202) 502-8659.
---------------------------------------------------------------------------
\1\ Panhandle Eastern Pipe Line Company, 3 FERC 61,099 (1978); 6
FERC 61,180 (1978).
---------------------------------------------------------------------------
Any questions regarding this prior notice request may be directed
to Blair Lichtenwalter, Senior Director, Certificates, Panhandle
Eastern Pipe Line Company, LP, by phone at (713) 989-2605 or by email
at [email protected] or Irma S. Jarrett, Manager,
Certificates, Panhandle Eastern Pipe Line Company, LP, 1300 Main
Street, Houston, Texas 77002 by phone at (713) 989-7679 (telephone), or
by email at [email protected].
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9),
within 90 days of this Notice, the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the EA for this proposal. The filing of the EA in the Commission's
public record for this proceeding or the issuance of a Notice of
Schedule for Environmental Review will serve to notify federal and
state agencies of the timing for the completion of all necessary
reviews, and the subsequent need to complete all federal authorizations
within 90 days of the date of issuance of the Commission staff's EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters, will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original and seven copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
Dated: August 24, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-18957 Filed 8-30-18; 8:45 am]
BILLING CODE 6717-01-P