Rescinding the Notice of Intent for an Environmental Impact Statement; Gadsden, Etowah County, Alabama, 44120 [2018-18669]

Download as PDF 44120 Federal Register / Vol. 83, No. 168 / Wednesday, August 29, 2018 / Notices 10, 2018 at 1:30 p.m. The meeting will be held at the Nebraska Supreme Court, State Capitol, Law Library Reading Room, 1445 K Street, Lincoln, Nebraska. The purpose of this meeting is to consider grant applications for the 4th quarter of FY 2018, and other business. All portions of this meeting are open to the public. ADDRESSES: Nebraska Supreme Court, State Capitol, Law Library Reading Room, 1445 K Street, Lincoln, Nebraska, 68509. FOR FURTHER INFORMATION CONTACT: Jonathan Mattiello, Executive Director, State Justice Institute, 11951 Freedom Drive, Suite 1020, Reston, VA 20190, 571–313–8843, contact@sji.gov. Jonathan D. Mattiello, Executive Director. [FR Doc. 2018–18681 Filed 8–28–18; 8:45 am] BILLING CODE P DEPARTMENT OF TRANSPORTATION Federal Aviation Administration Notice of Intent To Rule on Request To Release Airport Property at the Dallas/ Fort Worth International Airport, DFW, Texas Federal Aviation Administration (FAA), DOT. ACTION: Notice of request to release airport property. AGENCY: The FAA proposes to rule and invite public comment on the release of land at the Dallas/Fort Worth International Airport under the provisions of Section 125 of the Wendell H. Ford Aviation Investment Reform Act for the 21st Century (AIR 21). DATES: Comments must be received on or before (from 30 days of the posting of this Federal Register Notice). ADDRESSES: Comments on this application may be mailed or delivered to the FAA at the following address: Mr. Ben Guttery, Manager, Federal Aviation Administration, Southwest Region, Airports Division, Texas Airports District Office, ASW–650, 10101 Hillwood Parkway, Fort Worth, Texas 76177. In addition, one copy of any comments submitted to the FAA must be mailed or delivered to the at the following address: Mr. Sean Donohue, Chief Executive Officer, Dallas/Fort Worth International Airport, Executive Office, P.O. Box 619428, DFW Airport, Texas 75261. FOR FURTHER INFORMATION CONTACT: Mr. Steven Cooks, Program Manager, sradovich on DSK3GMQ082PROD with NOTICES SUMMARY: VerDate Sep<11>2014 17:04 Aug 28, 2018 Jkt 244001 Federal Aviation Administration, Texas Airports District Office, ASW–650, 10101 Hillwood Parkway, Fort Worth, TX 76177, Telephone: (817) 222–5608, email: Steven.Cooks@faa.gov, fax: (817) 222–5989. The request to release property may be reviewed in person at this same location. The FAA invites public comment on the request to release property at the Dallas/Fort Worth International Airport under the provisions of the AIR 21. The following is a brief overview of the request: The Dallas/Fort Worth International Airport requests the release of 39.737 acres of non-aeronautical airport property for permanent easement to the Fort Worth Transportation Autority. The permanent and temporary easements to be released will enable TRA to construct the Interceptor line which is approximately 9,850 linear feet and continue to maintain the Interceptor in the future and revuenes shall be used to further develop, operate and maintain DFW Airport. Any person may inspect the request in person at the FAA office listed above under FOR FURTHER INFORMATION CONTACT. In addition, any person may, upon request, inspect the application, notice and other documents relevant to the application in person at the: Dallas/Fort Worth International Airport, Telephone Number (972) 973–4646. SUPPLEMENTARY INFORMATION: Issued in Fort Worth, Texas, on August 16, 2018. Ignacio Flores, Director, Airports Division. [FR Doc. 2018–18764 Filed 8–28–18; 8:45 am] BILLING CODE 4910–13–P DEPARTMENT OF TRANSPORTATION Federal Highway Administration Rescinding the Notice of Intent for an Environmental Impact Statement; Gadsden, Etowah County, Alabama Federal Highway Administration (FHWA), DOT. ACTION: Rescind Notice of Intent. Mr. Mark D. Bartlett, Division Administrator, Federal Highway Administration, 9500 Wynlakes Place, Montgomery, Alabama 36117; Email: mark.bartlett@dot.gov; Telephone: (334) 274–6350. SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the Alabama Department of Transportation, is rescinding the NOI to prepare an EIS for Federal-aid project HPP–1602(539). The proposed project was to construct a limited access roadway from the eastern terminus of Interstate Highway 759 (I– 759) near George Wallace Drive to a proposed interchange with U.S. Highway 431 and U.S. Highway 278 in the city of Gadsden. The proposed project would have been a multi-lane roadway on a new location. The NOI for the project was published in the Federal Register on October 4, 2004. The FHWA has determined, in conjunction with ALDOT, the NOI for the project shall be rescinded due to the numerous impacts under Section 4(f) to historic resources identified during the project’s environmental studies and opposition to Section 4(f) avoidance alternatives. Any future Federal-aid actions within this corridor will comply with environmental review requirements of the National Environmental Policy Act (NEPA, 42 U.S.C. 4321, et seq.), FHWA environmental regulations (23 CFR 771) and related authorities, as appropriate. FOR FURTHER INFORMATION CONTACT: Authority: 23 U.S.C. 315; 49 CFR 1.48. (Catalog of Federal Domestic Assistance Program Number 20.205, Highway Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.) Issued on: August 20, 2018. Mark Bartlett, Division Administrator, Federal Highway Administration, Montgomery, Alabama. [FR Doc. 2018–18669 Filed 8–28–18; 8:45 am] BILLING CODE 4910–22–P DEPARTMENT OF TRANSPORTATION AGENCY: The FHWA is issuing this notice to advise the public that the 2004 Notice of Intent (NOI) published in the Federal Register for Federal-aid project HPP–1602(539), the I–759 Extension, in Etowah County, Alabama is being rescinded. An environmental impact statement (EIS) will not be prepared for this project. SUMMARY: PO 00000 Frm 00106 Fmt 4703 Sfmt 4703 Federal Highway Administration Rescinding the Notice of Intent for an Environmental Impact Statement; Multiple Counties, Alabama Federal Highway Administration (FHWA), DOT. ACTION: Rescind Notice of Intent. AGENCY: The FHWA is issuing this notice to advise the public that the 2005 Notice of Intent (NOI) published in the SUMMARY: E:\FR\FM\29AUN1.SGM 29AUN1

Agencies

[Federal Register Volume 83, Number 168 (Wednesday, August 29, 2018)]
[Notices]
[Page 44120]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-18669]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Rescinding the Notice of Intent for an Environmental Impact 
Statement; Gadsden, Etowah County, Alabama

AGENCY: Federal Highway Administration (FHWA), DOT.

ACTION: Rescind Notice of Intent.

-----------------------------------------------------------------------

SUMMARY: The FHWA is issuing this notice to advise the public that the 
2004 Notice of Intent (NOI) published in the Federal Register for 
Federal-aid project HPP-1602(539), the I-759 Extension, in Etowah 
County, Alabama is being rescinded. An environmental impact statement 
(EIS) will not be prepared for this project.

FOR FURTHER INFORMATION CONTACT: Mr. Mark D. Bartlett, Division 
Administrator, Federal Highway Administration, 9500 Wynlakes Place, 
Montgomery, Alabama 36117; Email: [email protected]; Telephone: 
(334) 274-6350.

SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the Alabama 
Department of Transportation, is rescinding the NOI to prepare an EIS 
for Federal-aid project HPP-1602(539). The proposed project was to 
construct a limited access roadway from the eastern terminus of 
Interstate Highway 759 (I-759) near George Wallace Drive to a proposed 
interchange with U.S. Highway 431 and U.S. Highway 278 in the city of 
Gadsden. The proposed project would have been a multi-lane roadway on a 
new location.
    The NOI for the project was published in the Federal Register on 
October 4, 2004. The FHWA has determined, in conjunction with ALDOT, 
the NOI for the project shall be rescinded due to the numerous impacts 
under Section 4(f) to historic resources identified during the 
project's environmental studies and opposition to Section 4(f) 
avoidance alternatives.
    Any future Federal-aid actions within this corridor will comply 
with environmental review requirements of the National Environmental 
Policy Act (NEPA, 42 U.S.C. 4321, et seq.), FHWA environmental 
regulations (23 CFR 771) and related authorities, as appropriate.

    Authority: 23 U.S.C. 315; 49 CFR 1.48.

(Catalog of Federal Domestic Assistance Program Number 20.205, 
Highway Planning and Construction. The regulations implementing 
Executive Order 12372 regarding intergovernmental consultation on 
Federal programs and activities apply to this program.)

     Issued on: August 20, 2018.
Mark Bartlett,
Division Administrator, Federal Highway Administration, Montgomery, 
Alabama.
[FR Doc. 2018-18669 Filed 8-28-18; 8:45 am]
 BILLING CODE 4910-22-P