Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3, 37529 [2018-16402]
Download as PDF
Federal Register / Vol. 83, No. 148 / Wednesday, August 1, 2018 / Notices
9. The estimated number of hours
needed annually to comply with the
information collection requirement or
request: 75 hours.
10. Abstract: The Debt Collection
Improvement Act of 1996 requires that
agencies collect TINs from individuals
who do business with the Government,
including contractors and recipients of
credit, licenses, permits, and benefits.
The TIN will be used to process all
electronic payments (refunds) made to
licensees by electronic funds transfer by
the Department of the Treasury. The
Department of the Treasury will use the
TIN to determine whether the refund
can be used to administratively offset
any delinquent debts reported to the
Treasury by other government agencies.
In addition, the TIN will be used to
collect and report to the Department of
the Treasury any delinquent
indebtedness arising out of the
licensee’s or applicant’s relationship
with the NRC.
III. Specific Requests for Comments
The NRC is seeking comments that
address the following questions:
1. Is the proposed collection of
information necessary for the NRC to
properly perform its functions? Does the
information have practical utility?
2. Is the estimate of the burden of the
information collection accurate?
3. Is there a way to enhance the
quality, utility, and clarity of the
information to be collected?
4. How can the burden of the
information collection on respondents
be minimized, including the use of
automated collection techniques or
other forms of information technology?
Dated at Rockville, Maryland, this 26th day
of July 2018.
For the Nuclear Regulatory Commission.
David Cullison,
NRC Clearance Officer, Office of the Chief
Information Officer.
[FR Doc. 2018–16401 Filed 7–31–18; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
sradovich on DSK3GMQ082PROD with NOTICES
[Docket Nos. 50–277 and 50–278; NRC–
2018–0130]
Exelon Generation Company, LLC;
Peach Bottom Atomic Power Station
Units 2 and 3
Nuclear Regulatory
Commission.
ACTION: License renewal application;
receipt.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has received an
SUMMARY:
VerDate Sep<11>2014
20:07 Jul 31, 2018
Jkt 244001
application for the subsequent license
renewal of Renewed Facility Operating
License Nos. DPR–44 and DPR–56,
which authorize Exelon Generation
Company, LLC (the applicant) to operate
Peach Bottom Atomic Power Station
Units 2 and 3 (Peach Bottom). The
renewed licenses would authorize the
applicant to operate Peach Bottom for
an additional 20 years beyond the
period specified in each of the current
renewed licenses. The current renewed
operating licenses for Peach Bottom
expire as follows: Unit 2 on August 8,
2033, and Unit 3 on July 2, 2034.
DATES: The license renewal application
referenced in this document was
submitted on July 10, 2018.
ADDRESSES: Please refer to Docket ID
NRC–2018–0130 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2018–0130. Address
questions about NRC dockets to Jennifer
Borges; telephone: 301–287–9127;
email: Jennifer.Borges@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Bennett M. Brady, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
2941, email: Bennett.Brady@nrc.gov.
SUPPLEMENTARY INFORMATION: The NRC
has received an application (ADAMS
Package Accession No. ML18193A689)
from Exelon Generation Company, LLC
PO 00000
Frm 00071
Fmt 4703
Sfmt 4703
37529
(Exelon or the applicant), dated July 10,
2018, filed pursuant to Section 103 of
the Atomic Energy Act of 1954, as
amended, and part 54 of title 10 of the
Code of Federal Regulations, to renew
the operating licenses for Peach Bottom.
Renewal of the licenses would authorize
the applicant to operate the facility for
an additional 20-year period beyond the
period specified in the respective
current renewed operating licenses. The
current renewed operating licenses for
Peach Bottom expire as follows: Unit 2
on August 8, 2033, and Unit 3 on July
2, 2034. The Peach Bottom units are
boiling water reactors located in Delta,
PA, about 17.9 miles south of Lancaster,
PA. The acceptability of the tendered
application for docketing, and other
matters, including an opportunity to
request a hearing, will be the subject of
subsequent Federal Register notices.
A copy of the subsequent license
renewal application for Peach Bottom is
also available for inspection near the
site at the Harford County Public
Library: Whiteford Branch, 2407
Whiteford Rd, Whiteford, MD 21160.
Dated at Rockville, Maryland, this 26th day
of July 2018.
For the Nuclear Regulatory Commission.
Emmanuel C. Sayoc,
Acting Chief, License Renewal Projects
Branch, Division of Materials and License
Renewal, Office of Nuclear Reactor
Regulation.
[FR Doc. 2018–16402 Filed 7–31–18; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2018–0159]
Interim Staff Guidance for
Decommissioning Funding Plans for
Materials Licensees
Nuclear Regulatory
Commission.
ACTION: Draft interim staff guidance;
request for comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is soliciting public
comment on its draft Interim Staff
Guidance (ISG) on Decommissioning
Funding Plans (DFP) for materials
licensees. The purpose of this ISG is to
provide the NRC staff and the industry
with guidance based on recent
developments and lessons learned in
financial assurance since the last update
to NUREG–1757, Vol. 3, Rev. 1,
‘‘Consolidated Decommissioning
Guidance Financial Assurance,
Recordkeeping, and Timeliness’’
(NUREG–1757, Vol. 3).
SUMMARY:
E:\FR\FM\01AUN1.SGM
01AUN1
Agencies
[Federal Register Volume 83, Number 148 (Wednesday, August 1, 2018)]
[Notices]
[Page 37529]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-16402]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-277 and 50-278; NRC-2018-0130]
Exelon Generation Company, LLC; Peach Bottom Atomic Power Station
Units 2 and 3
AGENCY: Nuclear Regulatory Commission.
ACTION: License renewal application; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has received an
application for the subsequent license renewal of Renewed Facility
Operating License Nos. DPR-44 and DPR-56, which authorize Exelon
Generation Company, LLC (the applicant) to operate Peach Bottom Atomic
Power Station Units 2 and 3 (Peach Bottom). The renewed licenses would
authorize the applicant to operate Peach Bottom for an additional 20
years beyond the period specified in each of the current renewed
licenses. The current renewed operating licenses for Peach Bottom
expire as follows: Unit 2 on August 8, 2033, and Unit 3 on July 2,
2034.
DATES: The license renewal application referenced in this document was
submitted on July 10, 2018.
ADDRESSES: Please refer to Docket ID NRC-2018-0130 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2018-0130. Address
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Bennett M. Brady, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-2941, email: [email protected].
SUPPLEMENTARY INFORMATION: The NRC has received an application (ADAMS
Package Accession No. ML18193A689) from Exelon Generation Company, LLC
(Exelon or the applicant), dated July 10, 2018, filed pursuant to
Section 103 of the Atomic Energy Act of 1954, as amended, and part 54
of title 10 of the Code of Federal Regulations, to renew the operating
licenses for Peach Bottom. Renewal of the licenses would authorize the
applicant to operate the facility for an additional 20-year period
beyond the period specified in the respective current renewed operating
licenses. The current renewed operating licenses for Peach Bottom
expire as follows: Unit 2 on August 8, 2033, and Unit 3 on July 2,
2034. The Peach Bottom units are boiling water reactors located in
Delta, PA, about 17.9 miles south of Lancaster, PA. The acceptability
of the tendered application for docketing, and other matters, including
an opportunity to request a hearing, will be the subject of subsequent
Federal Register notices.
A copy of the subsequent license renewal application for Peach
Bottom is also available for inspection near the site at the Harford
County Public Library: Whiteford Branch, 2407 Whiteford Rd, Whiteford,
MD 21160.
Dated at Rockville, Maryland, this 26th day of July 2018.
For the Nuclear Regulatory Commission.
Emmanuel C. Sayoc,
Acting Chief, License Renewal Projects Branch, Division of Materials
and License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2018-16402 Filed 7-31-18; 8:45 am]