Florida Gas Transmission Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Turnpike-Palmetto Road Relocation Project, and Request for Comments on Environmental Issues, 34838-34839 [2018-15703]
Download as PDF
34838
Federal Register / Vol. 83, No. 141 / Monday, July 23, 2018 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF18–5–000]
amozie on DSK3GDR082PROD with NOTICES1
Florida Gas Transmission Company,
LLC; Notice of Intent To Prepare an
Environmental Assessment for the
Planned Turnpike-Palmetto Road
Relocation Project, and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Turnpike-Palmetto Road Relocation
Project involving construction and
operation of facilities by Florida Gas
Transmission Company, LLC (FGT) in
Miami-Dade and Broward Counties,
Florida. The Commission will use this
EA in its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies about issues
regarding the project. The National
Environmental Policy Act (NEPA)
requires the Commission to take into
account the environmental impacts that
could result from its action whenever it
considers the issuance of a Certificate of
Public Convenience and Necessity.
NEPA also requires the Commission to
discover concerns the public may have
about proposals. This process is referred
to as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the EA on the important
environmental issues. By this notice, the
Commission requests public comments
on the scope of the issues to address in
the EA. To ensure that your comments
are timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00 p.m.
Eastern Time on August 16, 2018.
You can make a difference by
submitting your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. Commission staff
will consider all comments filed during
the preparation of the EA.
If you sent comments on this project
to the Commission before the opening of
this docket on May 4, 2018, you will
need to file those comments in Docket
VerDate Sep<11>2014
17:59 Jul 20, 2018
Jkt 244001
No. PF18–5–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, that approval conveys with
it the right of eminent domain.
Therefore, if you and the company do
not reach an easement agreement, the
pipeline company could initiate
condemnation proceedings in court. In
such instances, compensation would be
determined by a judge in accordance
with state law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC website (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. Using eComment is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. With eFiling, you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
the type of filing you are making; a
comment on a particular project is
considered a ‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (PF18–5–000)
with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Summary of the Planned Project
FGT plans to abandon approximately
19.1 miles of existing 18-inch-diameter
mainline pipeline and relocate and
construct approximately 15.4 miles of
24-inch-diameter mainline pipeline and
appurtenances in Broward and MiamiDade Counties, Florida. FGT also plans
to modify existing lateral interconnects
from the 18-inch-diameter mainline
pipeline to the planned 24-inchmainline pipeline.
This Project is designed to resolve
direct conflicts with proposed Florida
Department of Transportation
construction and operation of express
lanes along 21 miles of State Road 826/
Palmetto Expressway and State Road
91/Florida Turnpike and the proposed
system-to-system connection between
the Palmetto Expressway, Interstate 95,
and the Florida Turnpike.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Abandonment and construction of the
planned facilities would disturb about
433.3 acres of land for the aboveground
facilities and the pipelines. Following
construction, FGT would maintain
about 131.7 acres for permanent
operation of the Project’s facilities; the
remaining acreage would be restored
and revert to former uses. All of the
planned pipeline route parallels existing
pipeline, utility, or road rights-of-way.
The EA Process
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371.
E:\FR\FM\23JYN1.SGM
23JYN1
Federal Register / Vol. 83, No. 141 / Monday, July 23, 2018 / Notices
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
Commission staff will also evaluate
possible alternatives to the planned
project or portions of the project, and
make recommendations on how to
lessen or avoid impacts on the various
resource areas.
Although no formal application has
been filed, Commission staff have
already initiated a NEPA review under
the Commission’s pre-filing process.
The purpose of the pre-filing process is
to encourage early involvement of
interested stakeholders and to identify
and resolve issues before the
Commission receives an application. As
part of the pre-filing review,
Commission staff will contact federal
and state agencies to discuss their
involvement in the scoping process and
the preparation of the EA.
The EA will present Commission
staffs’ independent analysis of the
issues. The EA will be available in the
public record through eLibrary.2 The
Commission will publish and distribute
the EA to the public for an allotted
comment period. Commission staff will
consider and address all comments on
the EA before making recommendations
to the Commission. To ensure
Commission staff have the opportunity
to consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues related to this
project to formally cooperate in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
amozie on DSK3GDR082PROD with NOTICES1
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
2 For
instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
VerDate Sep<11>2014
17:59 Jul 20, 2018
Jkt 244001
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
Commission staff will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO(s)
as the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). The EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes: Federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. Commission
staff will update the environmental
mailing list as the analysis proceeds to
ensure that information related to this
environmental review is sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the planned
project.
Copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of a CD version or
would like to remove your name from
the mailing list, please return the
attached ‘‘Mailing List Update Form’’
(appendix 2).
Becoming an Intervenor
Once FGT files its application with
the Commission, you may want to
4 The Advisory Council on Historic Preservation
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
34839
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Only intervenors have the
right to seek rehearing of the
Commission’s decision and be heard by
the courts if they choose to appeal the
Commission’s final ruling. An
intervenor formally participates in the
proceeding by filing a request to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR 385.214). Motions
to intervene are more fully described at
https://www.ferc.gov/resources/guides/
how-to/intervene.asp. Please note that
the Commission will not accept requests
for intervenor status at this time. You
must wait until the Commission
receives a formal application for the
project, after which the Commission
will issue a public notice that
establishes an intervention deadline.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field, excluding the last three digits (i.e.,
PF18–5). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public sessions or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: July 17, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15703 Filed 7–20–18; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\23JYN1.SGM
23JYN1
Agencies
[Federal Register Volume 83, Number 141 (Monday, July 23, 2018)]
[Notices]
[Pages 34838-34839]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-15703]
[[Page 34838]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF18-5-000]
Florida Gas Transmission Company, LLC; Notice of Intent To
Prepare an Environmental Assessment for the Planned Turnpike-Palmetto
Road Relocation Project, and Request for Comments on Environmental
Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Turnpike-Palmetto Road
Relocation Project involving construction and operation of facilities
by Florida Gas Transmission Company, LLC (FGT) in Miami-Dade and
Broward Counties, Florida. The Commission will use this EA in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies about issues regarding the project. The National Environmental
Policy Act (NEPA) requires the Commission to take into account the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. NEPA also requires the Commission to discover concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of the
issues to address in the EA. To ensure that your comments are timely
and properly recorded, please submit your comments so that the
Commission receives them in Washington, DC on or before 5:00 p.m.
Eastern Time on August 16, 2018.
You can make a difference by submitting your specific comments or
concerns about the project. Your comments should focus on the potential
environmental effects, reasonable alternatives, and measures to avoid
or lessen environmental impacts. Your input will help the Commission
staff determine what issues they need to evaluate in the EA. Commission
staff will consider all comments filed during the preparation of the
EA.
If you sent comments on this project to the Commission before the
opening of this docket on May 4, 2018, you will need to file those
comments in Docket No. PF18-5-000 to ensure they are considered as part
of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, that approval conveys with it the right of
eminent domain. Therefore, if you and the company do not reach an
easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC website (www.ferc.gov). This fact sheet addresses a
number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. Using eComment is an easy
method for submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(PF18-5-000) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426.
Summary of the Planned Project
FGT plans to abandon approximately 19.1 miles of existing 18-inch-
diameter mainline pipeline and relocate and construct approximately
15.4 miles of 24-inch-diameter mainline pipeline and appurtenances in
Broward and Miami-Dade Counties, Florida. FGT also plans to modify
existing lateral interconnects from the 18-inch-diameter mainline
pipeline to the planned 24-inch-mainline pipeline.
This Project is designed to resolve direct conflicts with proposed
Florida Department of Transportation construction and operation of
express lanes along 21 miles of State Road 826/Palmetto Expressway and
State Road 91/Florida Turnpike and the proposed system-to-system
connection between the Palmetto Expressway, Interstate 95, and the
Florida Turnpike.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE, Washington,
DC 20426, or call (202) 502-8371.
---------------------------------------------------------------------------
Land Requirements for Construction
Abandonment and construction of the planned facilities would
disturb about 433.3 acres of land for the aboveground facilities and
the pipelines. Following construction, FGT would maintain about 131.7
acres for permanent operation of the Project's facilities; the
remaining acreage would be restored and revert to former uses. All of
the planned pipeline route parallels existing pipeline, utility, or
road rights-of-way.
The EA Process
The EA will discuss impacts that could occur as a result of the
construction and operation of the planned project under these general
headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
[[Page 34839]]
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
Commission staff will also evaluate possible alternatives to the
planned project or portions of the project, and make recommendations on
how to lessen or avoid impacts on the various resource areas.
Although no formal application has been filed, Commission staff
have already initiated a NEPA review under the Commission's pre-filing
process. The purpose of the pre-filing process is to encourage early
involvement of interested stakeholders and to identify and resolve
issues before the Commission receives an application. As part of the
pre-filing review, Commission staff will contact federal and state
agencies to discuss their involvement in the scoping process and the
preparation of the EA.
The EA will present Commission staffs' independent analysis of the
issues. The EA will be available in the public record through
eLibrary.\2\ The Commission will publish and distribute the EA to the
public for an allotted comment period. Commission staff will consider
and address all comments on the EA before making recommendations to the
Commission. To ensure Commission staff have the opportunity to consider
and address your comments, please carefully follow the instructions in
the Public Participation section, beginning on page 2.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues related to this project to formally cooperate in
the preparation of the EA.\3\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ Commission staff will define the
project-specific Area of Potential Effects (APE) in consultation with
the SHPO(s) as the project develops. On natural gas facility projects,
the APE at a minimum encompasses all areas subject to ground
disturbance (examples include construction right-of-way, contractor/
pipe storage yards, compressor stations, and access roads). The EA for
this project will document our findings on the impacts on historic
properties and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes: Federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. Commission staff will update the environmental
mailing list as the analysis proceeds to ensure that information
related to this environmental review is sent to all individuals,
organizations, and government entities interested in and/or potentially
affected by the planned project.
Copies of the EA will be sent to the environmental mailing list for
public review and comment. If you would prefer to receive a paper copy
of the document instead of a CD version or would like to remove your
name from the mailing list, please return the attached ``Mailing List
Update Form'' (appendix 2).
Becoming an Intervenor
Once FGT files its application with the Commission, you may want to
become an ``intervenor'' which is an official party to the Commission's
proceeding. Only intervenors have the right to seek rehearing of the
Commission's decision and be heard by the courts if they choose to
appeal the Commission's final ruling. An intervenor formally
participates in the proceeding by filing a request to intervene
pursuant to Rule 214 of the Commission's Rules of Practice and
Procedures (18 CFR 385.214). Motions to intervene are more fully
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Please note that the Commission will not accept requests for intervenor
status at this time. You must wait until the Commission receives a
formal application for the project, after which the Commission will
issue a public notice that establishes an intervention deadline.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field, excluding the last three digits (i.e.,
PF18-5). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public sessions or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 17, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-15703 Filed 7-20-18; 8:45 am]
BILLING CODE 6717-01-P