Download as PDF 34568 Federal Register / Vol. 83, No. 140 / Friday, July 20, 2018 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP18–518–000] daltland on DSKBBV9HB2PROD with NOTICES Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization Take notice that on July 6, 2018, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Houston, Texas 77002–2700, filed in Docket No. CP18–518–000 a prior notice request pursuant to sections 157.205, and 157.216 of the Commission’s regulations under the Natural Gas Act for authorization to abandon 12 injection/withdrawal wells and associated pipelines and appurtenances at five of Columbia’s Ohio storage fields located in Ashland, Medina, and Richland counties, Ohio. Columbia proposes to abandon these facilities under authorities granted by its blanket certificate issued in Docket No. CP83– 76–000, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Linda Farquhar, Manager, Project Determinations & Regulatory Administration, Columbia Gas Transmission, LLC, 700 Louisiana Street, Houston, Texas 77002–2700 at (832) 320–5685 or at linda_farquhar@ transcanada.com. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the NGA (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for VerDate Sep<11>2014 18:06 Jul 19, 2018 Jkt 244001 authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenter will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s website (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: July 16, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–15559 Filed 7–19–18; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness of Exempt Wholesale Generator Status Docket Nos. Stella Wind Farm, LLC ................ Calpine Mid-Merit II, LLC ............ GenOn Holdco 10, LLC ............... CED Upton County Solar, LLC ... CED Wistaria Solar, LLC ............. Walnut Ridge Wind, LLC ............. Pine River Wind Energy LLC ...... Sholes Wind Energy, LLC ........... EG18–72–000 EG18–73–000 EG18–74–000 EG18–75–000 EG18–76–000 EG18–77–000 EG18–78–000 EG18–79–000 Take notice that during the month of June 2018, the status of the abovecaptioned entities as Exempt Wholesale Generators Companies became effective by operation of the Commission’s regulations. 18 CFR 366.7(a) (2017). Dated: July 16, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–15558 Filed 7–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD18–5–000] Billing Procedures for Annual Charges for the Costs of Other Federal Agencies for Administering Part I of the Federal Power Act; Notice Reporting Costs for Other Federal Agencies’ Administrative Annual Charges for Fiscal Year 2017 1. The Federal Energy Regulatory Commission (Commission) is required to determine the reasonableness of costs incurred by other Federal agencies (OFAs) 1 in connection with their participation in the Commission’s proceedings under the Federal Power Act (FPA) Part I 2 when those agencies seek to include such costs in the administrative charges licensees must pay to reimburse the United States for the cost of administering Part I.3 The Commission’s Order on Remand and 1 The OFAs include: the U.S. Department of the Interior (Bureau of Indian Affairs, Bureau of Land Management, Bureau of Reclamation, National Park Service, U.S. Fish and Wildlife Service, Office of the Solicitor, Office of Environmental Policy & Compliance, Office of Hearings and Appeals, and Office of Policy Analysis); the U.S. Department of Agriculture (U.S. Forest Service); the U.S. Department of Commerce (National Marine Fisheries Service); and the U.S. Army Corps of Engineers. 2 16 U.S.C. 791a–823d (2012). 3 See id. 803(e)(1) and 42 U.S.C. 7178. E:\FR\FM\20JYN1.SGM 20JYN1

Agencies

[Federal Register Volume 83, Number 140 (Friday, July 20, 2018)]
[Notices]
[Page 34568]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-15559]



[[Page 34568]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-518-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization

    Take notice that on July 6, 2018, Columbia Gas Transmission, LLC 
(Columbia), 700 Louisiana Street, Houston, Texas 77002-2700, filed in 
Docket No. CP18-518-000 a prior notice request pursuant to sections 
157.205, and 157.216 of the Commission's regulations under the Natural 
Gas Act for authorization to abandon 12 injection/withdrawal wells and 
associated pipelines and appurtenances at five of Columbia's Ohio 
storage fields located in Ashland, Medina, and Richland counties, Ohio. 
Columbia proposes to abandon these facilities under authorities granted 
by its blanket certificate issued in Docket No. CP83-76-000, all as 
more fully set forth in the application which is on file with the 
Commission and open to public inspection. The filing may also be viewed 
on the web at https://www.ferc.gov using the ``eLibrary'' link. Enter 
the docket number excluding the last three digits in the docket number 
field to access the document. For assistance, please contact FERC 
Online Support at [email protected] or toll free at (866) 208-
3676, or TTY, contact (202) 502-8659.
    Any questions concerning this application may be directed to Linda 
Farquhar, Manager, Project Determinations & Regulatory Administration, 
Columbia Gas Transmission, LLC, 700 Louisiana Street, Houston, Texas 
77002-2700 at (832) 320-5685 or at [email protected].
    Any person may, within 60 days after the issuance of the instant 
notice by the Commission, file pursuant to Rule 214 of the Commission's 
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of 
intervention. Any person filing to intervene or the Commission's staff 
may, pursuant to section 157.205 of the Commission's Regulations under 
the NGA (18 CFR 157.205) file a protest to the request. If no protest 
is filed within the time allowed therefore, the proposed activity shall 
be deemed to be authorized effective the day after the time allowed for 
protest. If a protest is filed and not withdrawn within 30 days after 
the time allowed for filing a protest, the instant request shall be 
treated as an application for authorization pursuant to section 7 of 
the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenter will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
website (www.ferc.gov) under the ``e-Filing'' link. Persons unable to 
file electronically should submit an original and 5 copies of the 
protest or intervention to the Federal Energy regulatory Commission, 
888 First Street NE, Washington, DC 20426.

    Dated: July 16, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-15559 Filed 7-19-18; 8:45 am]
 BILLING CODE 6717-01-P