Spire Storage West, LLC, Clear Creek Storage Company, L.L.C.; Notice of Applications, 34562-34563 [2018-15556]
Download as PDF
daltland on DSKBBV9HB2PROD with NOTICES
34562
Federal Register / Vol. 83, No. 140 / Friday, July 20, 2018 / Notices
Description: Compliance filing:
Compliance Filing RE: OATT, OA and
RAA OVEC Integration Effective Date to
be effective 12/1/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5087.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–460–002.
Applicants: Ohio Valley Electric
Corporation, PJM Interconnection,
L.L.C.
Description: Compliance filing:
Compliance Filing RE: CTOA OVEC
Integration Effective Date to be effective
12/1/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5092.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2004–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: 3461
Mid-Kansas and City of Anthony, KS
Interconnection Agr to be effective 6/29/
2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5007.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2005–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Cancellation:
Notice of Cancellation of Service
Agreement No. 4411; Queue No. AA1–
059 to be effective 7/23/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5036.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2006–000.
Applicants: Interstate Power and
Light Company, MidAmerican Energy
Company.
Description: § 205(d) Rate Filing:
IPL—MEC Remote LBA Agreement to be
effective 9/10/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5066.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2008–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing: TriState Construct Agmt ? Monolith Tap IC
Rev 2 to be effective 9/11/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5096.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2009–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Revisions to Attachment AE to Enhance
Regulation Deployment of DVERs to be
effective 12/18/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5102.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2010–000.
VerDate Sep<11>2014
18:06 Jul 19, 2018
Jkt 244001
Applicants: Old Dominion Electric
Cooperative.
Description: Tariff Cancellation:
ODEC Notice of Cancellation of Rate
Schedule and Request for Waiver to be
effective 12/31/9998.
Filed Date: 7/12/18.
Accession Number: 20180712–5119.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2011–000.
Applicants: Terra-Gen Dixie Valley,
LLC.
Description: Tariff Cancellation:
Notice of Cancellation to be effective 7/
13/2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5128.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2013–000.
Applicants: Terra-Gen Dixie Valley,
LLC.
Description: Baseline eTariff Filing:
MBR Application to be effective 7/13/
2018.
Filed Date: 7/12/18.
Accession Number: 20180712–5171.
Comments Due: 5 p.m. ET 8/2/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: July 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15493 Filed 7–19–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–520–000; Docket No.
CP18–521–000]
Spire Storage West, LLC, Clear Creek
Storage Company, L.L.C.; Notice of
Applications
Take notice that on July 10, 2018,
Spire Storage West, LLC (Spire), filed an
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
application under section 7(c) of the
Natural Gas Act (NGA) and part 157 of
the Commission’s regulations for a
certificate of public convenience and
necessity authorizing Spire’s acquisition
of the underground natural gas storage
facility currently owned and operated
by the Clear Creek Storage Company,
L.L.C. (Clear Creek) and to operate that
facility (Clear Creek Facility) to provide
storage services in interstate commerce
pursuant to Spire’s FERC Gas Tariff.
Spire further requests the Commission’s
reaffirmation of its authorization for
Spire to charge market-based rates
following its acquisition of the Clear
Creek Facility.
Concurrently with the Spire
application above, Clear Creek filed an
application under section 7(b) of the
Natural Gas Act (NGA) and part 157 of
the Commission’s regulations requesting
authorization to abandon the Clear
Creek Facility by combination with
Spire, an affiliated entity.
Following approval of the proposals
in the above applications and
completion of the consolidation, Spire
will render service through the
combined Spire and Clear Creek
facilities under Spire’s open-access
FERC Gas Tariff. These services will
include service to any customer served
by Clear Creek at the time of the
combination.
Questions regarding the Spire filing in
Docket No. CP18–520–000 may be
directed to James F. Bowe, Jr., King &
Spalding LLP, 1700 Pennsylvania
Avenue NW, Suite 200, Washington, DC
20006; phone (202) 626–9601; FAX
(202) 626–3737; jbowe@kslaw.com.
Questions regarding the Clear Creek
filing in Docket No. CP18–521–000 may
be directed to James F. Bowe, Jr., or
William E. Rice, King & Spalding LLP,
1700 Pennsylvania Avenue NW, Suite
200, Washington, DC 20006; phone
(202)626–9601; FAX (202) 626–3737;
jbowe@kslaw.com; or Castor Armesto,
General Counsel, 700 Market Street, St.
Louis, Missouri 63101; phone (314)
342–3326, castor.armesto@
sapireenergy.com.
These filings are available for review
at the Commission’s Washington, DC
offices, or may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘e-Library’’ link.
Enter the docket number, excluding the
last three digits, in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, or call toll-free at (866) 208–
3676, or for TTY, contact (202) 502–
8659.
There are two ways to become
involved in the Commission’s review of
E:\FR\FM\20JYN1.SGM
20JYN1
daltland on DSKBBV9HB2PROD with NOTICES
Federal Register / Vol. 83, No. 140 / Friday, July 20, 2018 / Notices
this Project. First, any person wishing to
obtain legal status by becoming a party
to the proceeding for this project should
file with the Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426, a motion to
intervene in accordance with the
requirements of the Commission’s Rules
of Practice and Procedure, 18 CFR
385.214, 385.211 (2016), by the
comment date below. A person
obtaining party status will be placed on
the service list maintained by the
Secretary of the Commission, and will
receive copies of all documents filed by
the applicant and by all other parties. A
party must submit filings made with the
Commission by mail, hand delivery, or
internet, in accordance with Rule 2001
of the Commission’s Rules of Practice
and Procedure, id. 385.2001. A copy
must be served on every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene to have comments considered.
The second way to participate is by
filing with the Secretary of the
Commission, as soon as possible, an
original and two copies of comments in
support of or in opposition to this
project. The Commission will consider
these comments in determining the
appropriate action to be taken, but the
filing of a comment alone will not serve
to make the filer a party to the
proceeding. The Commission’s rules
require that persons filing comments in
opposition to the project provide copies
of their protests only to the party or
parties directly involved in the protest.
Protests and interventions may be
filed electronically via the internet in
lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s website under the
‘‘e-filing’’ link. The Commission
strongly encourages electronic filings.
As of the February 27, 2018 date of
the Commission’s order in Docket No.
CP16–4–001, the Commission will
apply its revised practice concerning
out-of-time motions to intervene in any
new Natural Gas Act section 3 or section
7 proceeding.1 Persons desiring to
become a party to a certificate
proceeding are to intervene in a timely
manner. If seeking to intervene out-oftime, the movant is required to ‘‘show
good cause why the time limitation
should be waived,’’ and should provide
justification by reference to factors set
forth in Rule 214(d)(1) of the
Commission’s Rules and Regulations.2
1 Tennessee Gas Pipeline Company, L.L.C., 162
FERC ¶61,167 at ¶50 (2018).
2 18 CFR 385.214(d)(1).
VerDate Sep<11>2014
18:06 Jul 19, 2018
Jkt 244001
If the Commission decides to set the
application for a formal hearing before
an Administrative Law Judge, the
Commission will issue another notice
describing that process. At the end of
the Commission’s review process, a
final Commission order approving or
denying the requested authorizations
will be issued.
Comment Date: 5:00 p.m. Eastern
Time, August 9, 2018.
Dated: July 16, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15556 Filed 7–19–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1827–006;
ER10–1533–016.
Applicants: Cleco Power LLC,
Macquarie Energy LLC.
Description: Supplement to December
22, 2017 Updated Market Power
Analysis for the Central Region of Cleco
Power LLC, et al.
Filed Date: 7/13/18.
Accession Number: 20180713–5042.
Comments Due: 5 p.m. ET 8/3/18.
Docket Numbers: ER18–1632–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
Amended Filing—Major Maintenance
Cost Component to Mitigated Offers to
be effective 1/15/2019.
Filed Date: 7/12/18.
Accession Number: 20180712–5174.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–1898–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
1534R8 Kansas Municipal Energy
Agency NITSA NOA—Amended to be
effective 6/1/2018.
Filed Date: 7/13/18.
Accession Number: 20180713–5129.
Comments Due: 5 p.m. ET 8/3/18.
Docket Numbers: ER18–2012–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Request of PJM
Interconnection, L.L.C. for Limited
Waiver.
Filed Date: 7/12/18.
Accession Number: 20180712–5131.
Comments Due: 5 p.m. ET 7/23/18.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
34563
Docket Numbers: ER18–2014–000.
Applicants: Ohio Valley Electric
Corporation.
Description: Request of Ohio Valley
Electric Corporation for Limited
Waivers and Expedited Treatment.
Filed Date: 7/12/18.
Accession Number: 20180712–5176.
Comments Due: 5 p.m. ET 8/2/18.
Docket Numbers: ER18–2015–000.
Applicants: New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing:
Amended & Restated Operating
Agreement re: NYISO and New York
Transco to be effective 5/23/2016.
Filed Date: 7/13/18.
Accession Number: 20180713–5078.
Comments Due: 5 p.m. ET 8/3/18.
Docket Numbers: ER18–2016–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original WMPA, SA No. 5147; Queue
No. AD1–144 to be effective 6/15/2018.
Filed Date: 7/13/18.
Accession Number: 20180713–5104.
Comments Due: 5 p.m. ET 8/3/18.
Docket Numbers: ER18–2017–000.
Applicants: Northern States Power
Company, a Minnesota corporation.
Description: Notice of Cancellation of
the Operation and Maintenance
Agreement (Rates Schedule No. 501) of
Northern States Power Company, a
Minnesota corporation.
Filed Date: 7/13/18.
Accession Number: 20180713–5126.
Comments Due: 5 p.m. ET 8/3/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: July 13, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15483 Filed 7–19–18; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\20JYN1.SGM
20JYN1
Agencies
[Federal Register Volume 83, Number 140 (Friday, July 20, 2018)]
[Notices]
[Pages 34562-34563]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-15556]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-520-000; Docket No. CP18-521-000]
Spire Storage West, LLC, Clear Creek Storage Company, L.L.C.;
Notice of Applications
Take notice that on July 10, 2018, Spire Storage West, LLC (Spire),
filed an application under section 7(c) of the Natural Gas Act (NGA)
and part 157 of the Commission's regulations for a certificate of
public convenience and necessity authorizing Spire's acquisition of the
underground natural gas storage facility currently owned and operated
by the Clear Creek Storage Company, L.L.C. (Clear Creek) and to operate
that facility (Clear Creek Facility) to provide storage services in
interstate commerce pursuant to Spire's FERC Gas Tariff. Spire further
requests the Commission's reaffirmation of its authorization for Spire
to charge market-based rates following its acquisition of the Clear
Creek Facility.
Concurrently with the Spire application above, Clear Creek filed an
application under section 7(b) of the Natural Gas Act (NGA) and part
157 of the Commission's regulations requesting authorization to abandon
the Clear Creek Facility by combination with Spire, an affiliated
entity.
Following approval of the proposals in the above applications and
completion of the consolidation, Spire will render service through the
combined Spire and Clear Creek facilities under Spire's open-access
FERC Gas Tariff. These services will include service to any customer
served by Clear Creek at the time of the combination.
Questions regarding the Spire filing in Docket No. CP18-520-000 may
be directed to James F. Bowe, Jr., King & Spalding LLP, 1700
Pennsylvania Avenue NW, Suite 200, Washington, DC 20006; phone (202)
626-9601; FAX (202) 626-3737; [email protected]. Questions regarding the
Clear Creek filing in Docket No. CP18-521-000 may be directed to James
F. Bowe, Jr., or William E. Rice, King & Spalding LLP, 1700
Pennsylvania Avenue NW, Suite 200, Washington, DC 20006; phone
(202)626-9601; FAX (202) 626-3737; [email protected]; or Castor Armesto,
General Counsel, 700 Market Street, St. Louis, Missouri 63101; phone
(314) 342-3326, [email protected].
These filings are available for review at the Commission's
Washington, DC offices, or may be viewed on the Commission's website at
https://www.ferc.gov using the ``e-Library'' link. Enter the docket
number, excluding the last three digits, in the docket number field to
access the document. For assistance, please contact FERC Online Support
at [email protected], or call toll-free at (866) 208-3676, or
for TTY, contact (202) 502-8659.
There are two ways to become involved in the Commission's review of
[[Page 34563]]
this Project. First, any person wishing to obtain legal status by
becoming a party to the proceeding for this project should file with
the Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426, a motion to intervene in accordance with the
requirements of the Commission's Rules of Practice and Procedure, 18
CFR 385.214, 385.211 (2016), by the comment date below. A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission, and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit filings made with the Commission by mail, hand delivery, or
internet, in accordance with Rule 2001 of the Commission's Rules of
Practice and Procedure, id. 385.2001. A copy must be served on every
other party in the proceeding. Only parties to the proceeding can ask
for court review of Commission orders in the proceeding.
However, a person does not have to intervene to have comments
considered. The second way to participate is by filing with the
Secretary of the Commission, as soon as possible, an original and two
copies of comments in support of or in opposition to this project. The
Commission will consider these comments in determining the appropriate
action to be taken, but the filing of a comment alone will not serve to
make the filer a party to the proceeding. The Commission's rules
require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Protests and interventions may be filed electronically via the
internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's website under the ``e-filing'' link.
The Commission strongly encourages electronic filings.
As of the February 27, 2018 date of the Commission's order in
Docket No. CP16-4-001, the Commission will apply its revised practice
concerning out-of-time motions to intervene in any new Natural Gas Act
section 3 or section 7 proceeding.\1\ Persons desiring to become a
party to a certificate proceeding are to intervene in a timely manner.
If seeking to intervene out-of-time, the movant is required to ``show
good cause why the time limitation should be waived,'' and should
provide justification by reference to factors set forth in Rule
214(d)(1) of the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------
\1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC ]61,167 at
]50 (2018).
\2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------
If the Commission decides to set the application for a formal
hearing before an Administrative Law Judge, the Commission will issue
another notice describing that process. At the end of the Commission's
review process, a final Commission order approving or denying the
requested authorizations will be issued.
Comment Date: 5:00 p.m. Eastern Time, August 9, 2018.
Dated: July 16, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-15556 Filed 7-19-18; 8:45 am]
BILLING CODE 6717-01-P