Notice of Intent To Prepare an Environmental Assessment for the Proposed Portland Xpress Project, and Request for Comments on Environmental Issues: Portland Natural Gas Transmission System, 33928-33930 [2018-15321]
Download as PDF
amozie on DSK3GDR082PROD with NOTICES1
33928
Federal Register / Vol. 83, No. 138 / Wednesday, July 18, 2018 / Notices
previously authorized by the
Commission in Docket No. CP12–508–
000. This new pipeline would be
capable of supplying feed gas to, and
bringing natural gas from, the Stage 3
LNG Facilities. The Stage 3 Pipeline
would be integrated and operated as
part of the Corpus Christi Pipeline
system, all as more fully set forth in the
application which is on file with the
Commission and open for public
inspection.
On June 9, 2015, the Commission staff
granted the applicants’ request to utilize
the National Environmental Policy Act
(NEPA) Pre-Filing Process and assigned
Docket No. PF15–26–000 to staff
activities involving the project. Now, as
of the filing of this application on June
28, 2018, the NEPA Pre-Filing Process
for this project has ended. From this
time forward, this proceeding will be
conducted in Docket Nos. CP18–512–
000 and CP18–513–000, as noted in the
caption of this Notice.
The filing may also be viewed on the
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC at FERCOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or TTY,
(202) 502–8659.
Any questions regarding the proposed
project should be directed to Karri
Mahmoud, Cheniere Energy, Inc., 700
Milam Street, Suite 1900, Houston,
Texas 77002, or by calling (713) 375–
5000 or by email at Karri.Mahmoud@
cheniere.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
VerDate Sep<11>2014
19:19 Jul 17, 2018
Jkt 244001
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
PO 00000
Frm 00012
Fmt 4703
Sfmt 4703
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426.
Comment Date: August 2, 2018.
Dated: July 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15322 Filed 7–17–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–506–000]
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Portland Xpress Project, and
Request for Comments on
Environmental Issues: Portland
Natural Gas Transmission System
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Portland Xpress Project involving
construction and operation of facilities
by Portland Natural Gas Transmission
Systems (Portland) to Portland owned,
and Portland and Maritime jointly
owned, facilities in Cumberland and
York Counties, Maine and Middlesex
County, Massachusetts. The
Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies about issues
regarding the project. The National
Environmental Policy Act (NEPA)
requires the Commission to take into
account the environmental impacts that
could result from its action whenever it
considers the issuance of a Certificate of
Public Convenience and Necessity.
NEPA also requires the Commission to
discover concerns the public may have
about proposals. This process is referred
to as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the EA on the important
environmental issues. By this notice, the
Commission requests public comments
on the scope of the issues to address in
the EA. To ensure that your comments
are timely and properly recorded, please
submit your comments so that the
Commission receives them in
Washington, DC on or before 5:00 p.m.
Eastern Time on August 13, 2018.
E:\FR\FM\18JYN1.SGM
18JYN1
Federal Register / Vol. 83, No. 138 / Wednesday, July 18, 2018 / Notices
You can make a difference by
submitting your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. Commission staff
will consider and address all filed
comments during the preparation of the
EA.
If you sent comments on this project
to the Commission before the opening of
this docket on June 19, 2018, you will
need to file those comments in Docket
No. CP18–506–000 to ensure they are
considered as part of this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, that approval conveys with
it the right of eminent domain.
Therefore, if you and the company do
not reach an easement agreement, the
pipeline company could initiate
condemnation proceedings in court. In
such instances, compensation would be
determined by a judge in accordance
with state law.
Portland provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC website
(www.ferc.gov).
amozie on DSK3GDR082PROD with NOTICES1
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
VerDate Sep<11>2014
19:19 Jul 17, 2018
Jkt 244001
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. Using eComment is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. With eFiling, you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making; a
comment on a particular project is
considered a ‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (CP18–506–
000) with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Portland proposes to perform the
following activities for construction of
the project to provide 24,375 million
cubic feet per day (Mcf/d) to Portland
owned facilities, and 22,339 Mcf/d on
Portland and Maritimes jointly owned
facilities.
Westbrook Compressor Station (CS),
Cumberland County, Maine
• Install a new electrical control
building with motor control center,
emergency generator building and
generator and ancillary equipment; and
Eliot CS, York County, Maine
• Expansion of the existing building
to include one new 6,300 horsepower
(hp) gas-fired compression unit and
ancillary equipment; and
• Install an auxiliary building
housing a replacement emergency
generator and boiler.
Dracut Meter and Regulator (M&R)
Station, Middlesex County,
Massachusetts
• Install a low flow meter and
transmitters and replace ultrasonic
meter assemblies;
• Install a new 86-hp emergency
generator; and
• Installation of ancillary equipment.
The general location of the project
facilities is shown in appendix 1.1
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
PO 00000
Frm 00013
Fmt 4703
Sfmt 4703
33929
Land Requirements for Construction
Construction of the proposed facilities
would disturb 21.6 acres of land for the
aboveground facilities. The Westbrook
CS would utilize 8.4 acres, the Eliot CS
would require 11.9 acres, and the Dracut
M&R would disrupt 1.3 acres during
construction. Construction access to
each of the three sites would be from
existing permanent access roads. No
land outside the existing compressor
station or meter station properties
would be impacted for construction or
operations of the Project.
The EA Process
The EA will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project, and
make recommendations on how to
lessen or avoid impacts on the various
resource areas.
The EA will present Commission
staffs’ independent analysis of the
issues. The EA will be available in the
public record through eLibrary.
Commission staff will consider and
address all comments on the EA before
making recommendations to the
Commission. To ensure Commission
staff have the opportunity to address
your comments, please carefully follow
the instructions in the Public
Participation section, beginning on page
2.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the EA.2 Agencies that would like to
request cooperating agency status
should follow the instructions for filing
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
2 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
E:\FR\FM\18JYN1.SGM
18JYN1
33930
Federal Register / Vol. 83, No. 138 / Wednesday, July 18, 2018 / Notices
comments provided under the Public
Participation section of this notice.
amozie on DSK3GDR082PROD with NOTICES1
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Offices (SHPO), and to
solicit their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.3
Commission staff will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPOs
as the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). The EA for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. Commission
staff will update the environmental
mailing list as the analysis proceeds to
ensure that information related to this
environmental review is sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If the Commission publishes and
distributes the EA, copies will be sent
to the environmental mailing list for
public review and comment. If you
would prefer to receive a paper copy of
3 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
19:19 Jul 17, 2018
Jkt 244001
the document instead of a CD version or
would like to remove your name from
the mailing list, please return the
attached ‘‘Mailing List Update Form’’
(appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number in the ‘‘Docket
Number’’ field, excluding the last three
digits (i.e., CP18–506). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public sessions or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: July 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–15321 Filed 7–17–18; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OAR–2017–0639; FRL—9980–77–
OEI]
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request;
Production, Import, Export,
Destruction, Transhipment, and
Exempted Uses of Ozone-Depleting
Substances (Renewal)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency (EPA) has submitted an
SUMMARY:
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
information collection request (ICR),
Production, Import, Export, Destruction,
Transhipment, and Exempted Uses of
Ozone-Depleting Substances (EPA ICR
No. 1432.34, OMB Control No. 2060–
0170), to the Office of Management and
Budget (OMB) for review and approval
in accordance with the Paperwork
Reduction Act. This is a proposed
revision of the ICR, which is currently
approved through October 2018. Public
comments were previously requested
via the Federal Register on January 19,
2018 during a 60-day comment period.
This notice allows for an additional 30
days for public comments. A fuller
description of the ICR is given below,
including its estimated burden and cost
to the public. An agency may not
conduct or sponsor and a person is not
required to respond to a collection of
information unless it displays a
currently valid OMB control number.
DATES: Additional comments may be
submitted on or before August 17, 2018.
ADDRESSES: Submit your comments,
referencing Docket ID Number EPA–
HW–OAR–2017–0639, to EPA online
using www.regulations.gov or by mail
to: EPA Docket Center, Environmental
Protection Agency, Mail Code 28221T,
1200 Pennsylvania Ave. NW,
Washington, DC 20460, and OMB via
email to oira_submission@omb.eop.gov.
Address comments to OMB Desk Officer
for EPA.
EPA’s policy is that all comments
received will be included in the public
docket without change including any
personal information provided, unless
the comment includes profanity, threats,
information claimed to be Confidential
Business Information (CBI) or other
information whose disclosure is
restricted by statute.
FOR FURTHER INFORMATION CONTACT:
Katherine Sleasman, Stratospheric
Protection Division, (6205T),
Environmental Protection Agency, 1200
Pennsylvania Ave. NW, Washington, DC
20460; telephone number: (202) 564–
7716; fax number: (202) 343–2338;
email address: sleasman.katherine@
epa.gov.
SUPPLEMENTARY INFORMATION:
Supporting documents, which explain
in detail the information that the EPA
will be collecting, are available in the
public docket for this ICR. The docket
can be viewed online at
www.regulations.gov or in person at the
EPA Docket Center, WJC West, Room
3334, 1301 Constitution Ave. NW,
Washington, DC. The telephone number
for the Docket Center is 202–566–1744.
For additional information about EPA’s
public docket, visit https://
www.epa.gov/dockets.
E:\FR\FM\18JYN1.SGM
18JYN1
Agencies
[Federal Register Volume 83, Number 138 (Wednesday, July 18, 2018)]
[Notices]
[Pages 33928-33930]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-15321]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-506-000]
Notice of Intent To Prepare an Environmental Assessment for the
Proposed Portland Xpress Project, and Request for Comments on
Environmental Issues: Portland Natural Gas Transmission System
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Portland Xpress Project
involving construction and operation of facilities by Portland Natural
Gas Transmission Systems (Portland) to Portland owned, and Portland and
Maritime jointly owned, facilities in Cumberland and York Counties,
Maine and Middlesex County, Massachusetts. The Commission will use this
EA in its decision-making process to determine whether the project is
in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies about issues regarding the project. The National Environmental
Policy Act (NEPA) requires the Commission to take into account the
environmental impacts that could result from its action whenever it
considers the issuance of a Certificate of Public Convenience and
Necessity. NEPA also requires the Commission to discover concerns the
public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of the
issues to address in the EA. To ensure that your comments are timely
and properly recorded, please submit your comments so that the
Commission receives them in Washington, DC on or before 5:00 p.m.
Eastern Time on August 13, 2018.
[[Page 33929]]
You can make a difference by submitting your specific comments or
concerns about the project. Your comments should focus on the potential
environmental effects, reasonable alternatives, and measures to avoid
or lessen environmental impacts. Your input will help the Commission
staff determine what issues they need to evaluate in the EA. Commission
staff will consider and address all filed comments during the
preparation of the EA.
If you sent comments on this project to the Commission before the
opening of this docket on June 19, 2018, you will need to file those
comments in Docket No. CP18-506-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, that approval conveys with it the right of
eminent domain. Therefore, if you and the company do not reach an
easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with state law.
Portland provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC website (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. Using eComment is an easy
method for submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(CP18-506-000) with your submission: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A,
Washington, DC 20426.
Summary of the Proposed Project
Portland proposes to perform the following activities for
construction of the project to provide 24,375 million cubic feet per
day (Mcf/d) to Portland owned facilities, and 22,339 Mcf/d on Portland
and Maritimes jointly owned facilities.
Westbrook Compressor Station (CS), Cumberland County, Maine
Install a new electrical control building with motor
control center, emergency generator building and generator and
ancillary equipment; and
Eliot CS, York County, Maine
Expansion of the existing building to include one new
6,300 horsepower (hp) gas-fired compression unit and ancillary
equipment; and
Install an auxiliary building housing a replacement
emergency generator and boiler.
Dracut Meter and Regulator (M&R) Station, Middlesex County,
Massachusetts
Install a low flow meter and transmitters and replace
ultrasonic meter assemblies;
Install a new 86-hp emergency generator; and
Installation of ancillary equipment.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE, Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb 21.6 acres of
land for the aboveground facilities. The Westbrook CS would utilize 8.4
acres, the Eliot CS would require 11.9 acres, and the Dracut M&R would
disrupt 1.3 acres during construction. Construction access to each of
the three sites would be from existing permanent access roads. No land
outside the existing compressor station or meter station properties
would be impacted for construction or operations of the Project.
The EA Process
The EA will discuss impacts that could occur as a result of the
construction and operation of the proposed project under these general
headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project, and make recommendations
on how to lessen or avoid impacts on the various resource areas.
The EA will present Commission staffs' independent analysis of the
issues. The EA will be available in the public record through eLibrary.
Commission staff will consider and address all comments on the EA
before making recommendations to the Commission. To ensure Commission
staff have the opportunity to address your comments, please carefully
follow the instructions in the Public Participation section, beginning
on page 2.
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the EA.\2\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
[[Page 33930]]
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\2\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Offices
(SHPO), and to solicit their views and those of other government
agencies, interested Indian tribes, and the public on the project's
potential effects on historic properties.\3\ Commission staff will
define the project-specific Area of Potential Effects (APE) in
consultation with the SHPOs as the project develops. On natural gas
facility projects, the APE at a minimum encompasses all areas subject
to ground disturbance (examples include construction right-of-way,
contractor/pipe storage yards, compressor stations, and access roads).
The EA for this project will document findings on the impacts on
historic properties and summarize the status of consultations under
section 106.
---------------------------------------------------------------------------
\3\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. Commission staff will update the environmental
mailing list as the analysis proceeds to ensure that information
related to this environmental review is sent to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project.
If the Commission publishes and distributes the EA, copies will be
sent to the environmental mailing list for public review and comment.
If you would prefer to receive a paper copy of the document instead of
a CD version or would like to remove your name from the mailing list,
please return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field, excluding the last three digits (i.e.,
CP18-506). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or (866) 208-3676, or for TTY, contact (202)
502-8659. The eLibrary link also provides access to the texts of all
formal documents issued by the Commission, such as orders, notices, and
rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public sessions or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: July 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-15321 Filed 7-17-18; 8:45 am]