Download as PDF Federal Register / Vol. 83, No. 133 / Wednesday, July 11, 2018 / Notices daltland on DSKBBV9HB2PROD with NOTICES 385.214, within 21 days of the date of issuance of the order. Filed Date: 7/2/18. Accession Number: 20180702–5054. Comments Due: 5 p.m. ET 7/16/18. Dated: July 2, 2018. Docket Numbers: RP18–952–000. Kimberly D. Bose, Applicants: Equitrans, L.P. Secretary. Description: § 4(d) Rate Filing: [FR Doc. 2018–14773 Filed 7–10–18; 8:45 am] Negotiated Capacity Release BILLING CODE 6717–01–P Agreements—7/1/2018 to be effective 7/1/2018. Filed Date: 7/2/18. DEPARTMENT OF ENERGY Accession Number: 20180702–5127. Comments Due: 5 p.m. ET 7/16/18. Federal Energy Regulatory Docket Numbers: RP18–953–000. Commission Applicants: Gulf South Pipeline Combined Notice of Filings Company, LP. Description: § 4(d) Rate Filing: Take notice that the Commission has Negotiated Rate Agmt (Emera 49472) to received the following Natural Gas Pipeline Rate and Refund Report filings: be effective 7/2/2018. Filed Date: 7/2/18. Filings Instituting Proceedings Accession Number: 20180702–5251. Comments Due: 5 p.m. ET 7/16/18. Docket Numbers: RP10–1398–000. Docket Numbers: RP18–954–000. Applicants: El Paso Natural Gas Applicants: Gulf South Pipeline Company. Description: Report Filing: Refund Company, LP. Description: § 4(d) Rate Filing: Report. Filed Date: 7/2/18. PermCapRel & CapRelNegRateAgmt Accession Number: 20180702–5164. (Pivotal 34691 >ETG 49785, then >So Comments Due: 5 p.m. ET 7/16/18. Jersey 49788) to be effective 7/1/2018. Filed Date: 7/2/18. Docket Numbers: RP15–1022–014. Applicants: Alliance Pipeline L.P. Accession Number: 20180702–5259. Description: Compliance filing Comments Due: 5 p.m. ET 7/16/18. Settlement—Gas Processing to be Docket Numbers: RP18–955–000. effective 8/1/2018. Applicants: Enable Mississippi River Filed Date: 7/2/18. Transmission, LLC. Accession Number: 20180702–5001. Description: § 4(d) Rate Filing: Comments Due: 5 p.m. ET 7/16/18. Negotiated Rate Filing—Ankor—July 1, Docket Numbers: RP18–861–001. 2018 #6032 to be effective 7/1/2018. Applicants: Equitrans, L.P. Filed Date: 7/2/18. Description: Compliance filing Accession Number: 20180702–5267. Scheduling Priority Exemption for Comments Due: 5 p.m. ET 7/16/18. Reservation Charge Credits Compliance Docket Numbers: RP18–891–001. Filing to be effective 7/1/2018. Applicants: Eastern Shore Natural Gas Filed Date: 7/2/18. Company. Accession Number: 20180702–5102. Description: Tariff Amendment: Comments Due: 5 p.m. ET 7/16/18. Amended Non-Conforming Letter Docket Numbers: RP18–940–001. Agreements-Easton/CUC–MD to be Applicants: Empire Pipeline, Inc. effective 5/1/2018. Description: Tariff Amendment: Errata Filed Date: 7/3/18. Empire Rate Case—June 2018 to be Accession Number: 20180703–5108. effective 1/1/2019. Comments Due: 5 p.m. ET 7/16/18. Filed Date: 7/2/18. Docket Numbers: RP18–956–000. Accession Number: 20180702–5101. Applicants: WTG Hugoton, LP. Comments Due: 5 p.m. ET 7/16/18. Description: § 4(d) Rate Filing: Annual Docket Numbers: RP18–950–000. Fuel Retention Percentage Filing 2018– Applicants: Dominion Energy Cove 2019 to be effective 7/2/2018. Point LNG, LP. Filed Date: 7/3/18. Description: Compliance filing Accession Number: 20180703–5000. DECP—2018 Penalty Revenue Comments Due: 5 p.m. ET 7/16/18. Distribution. Docket Numbers: RP18–957–000. Filed Date: 7/2/18. Accession Number: 20180702–5044. Applicants: Midcontinent Express Comments Due: 5 p.m. ET 7/16/18. Pipeline LLC. Description: § 4(d) Rate Filing: Docket Numbers: RP18–951–000. Chesapeake/BCE-Mach LLC Negotiated Applicants: Dominion Energy Rate to be effective 7/1/2018. Transmission, Inc. Filed Date: 7/3/18. Description: Compliance filing DETI— Accession Number: 20180703–5045. 2018 Overrun and Penalty Revenue Comments Due: 5 p.m. ET 7/16/18. Distribution. VerDate Sep<11>2014 16:26 Jul 10, 2018 Jkt 244001 PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 32107 Docket Numbers: RP18–958–000. Applicants: Rockies Express Pipeline LLC. Description: § 4(d) Rate Filing: Neg Rate 2018–07–03 BP (2Ks) to be effective 7/4/2018. Filed Date: 7/3/18. Accession Number: 20180703–5117. Comments Due: 5 p.m. ET 7/16/18. Docket Numbers: RP18–959–000. Applicants: Texas Eastern Transmission, LP. Description: Compliance filing TETLP Notice Regarding Non-Jurisdictional Facilities. Filed Date: 7/3/18. Accession Number: 20180703–5158. Comments Due: 5 p.m. ET 7/16/18. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 5, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–14832 Filed 7–10–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP18–504–000] Notice of Request Under Blanket Authorization; Transwestern Pipeline Company, LLC Take notice that on June 14, 2018, Transwestern Pipeline Company, LLC (Transwestern), 1300 Main Street, Houston, Texas 7700, filed a Prior Notice Request pursuant to sections 157.203, 157.205, and 157.216 of the Commission’s regulations under the Natural Gas Act (NGA) for authorization to abandon in place the Atoka 3 Compressor Station consisting of five natural gas compressor engines, E:\FR\FM\11JYN1.SGM 11JYN1 daltland on DSKBBV9HB2PROD with NOTICES 32108 Federal Register / Vol. 83, No. 133 / Wednesday, July 11, 2018 / Notices compressors, yard and station piping, and ancillary related facilities located in Eddy County, New Mexico (Atoka 3 CS or Project) all as more fully set forth in the application, which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this Application should be directed to Mr. Kelly Allen, Manager, Regulatory Affairs Department for Transwestern Pipeline Company, LLC, 1300 Main Street, Houston, Texas 77002, or call 713–989– 2606, or by email Kelly.Allen@ energytransfer.com. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the NGA (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of VerDate Sep<11>2014 16:26 Jul 10, 2018 Jkt 244001 the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s website (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: July 2, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–14770 Filed 7–10–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #3 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER18–1159–001. Applicants: Midcontinent Independent System Operator, Inc., Pioneer Transmission, LLC. Description: Tariff Amendment: 2018–07–02_Deficiency response re Pioneer Attachment O Filing to be effective 6/1/2018. Filed Date: 7/2/18. Accession Number: 20180702–5179. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1911–000. Applicants: Midcontinent Independent System Operator, Inc. PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 Description: § 205(d) Rate Filing: 2018–07–02_Termination of SA 2893 Black Hawk MPFCA (J233, J274, J278, J279) to be effective 7/3/2018. Filed Date: 7/2/18. Accession Number: 20180702–5028. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1912–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: First Revised ISA SA No. 3041; Queue No. AC2–133 to be effective 6/4/2018. Filed Date: 7/2/18. Accession Number: 20180702–5134. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1913–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Second Revised ISA, SA No. 4109; Queue No. AB2–191 to be effective 8/1/ 2018. Filed Date: 7/2/18. Accession Number: 20180702–5135. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1914–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2018–07–02_SA 2959 Northern States Power-Stoneray Power Partners 1stRevGIA(J426) to be effective 6/20/ 2018. Filed Date: 7/2/18. Accession Number: 20180702–5149. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1915–000. Applicants: Bowfin KeyCon Energy, LLC. Description: Baseline eTariff Filing: Bowfin Energy FERC Electric Tariff, Original Baseline to be effective 8/13/ 2018. Filed Date: 7/2/18. Accession Number: 20180702–5168. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1917–000. Applicants: Bowfin KeyCon Power, LLC. Description: Baseline eTariff Filing: Bowfin Power FERC Electric Tariff, Original Baseline to be effective 8/13/ 2018. Filed Date: 7/2/18. Accession Number: 20180702–5169. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1918–000. Applicants: Kestrel Acquisition, LLC. Description: Baseline eTariff Filing: Notices of succession to be effective 12/ 31/9998. Filed Date: 7/2/18. Accession Number: 20180702–5173. Comments Due: 5 p.m. ET 7/23/18. Docket Numbers: ER18–1919–000. Applicants: Southwest Power Pool, Inc. E:\FR\FM\11JYN1.SGM 11JYN1

Agencies

[Federal Register Volume 83, Number 133 (Wednesday, July 11, 2018)]
[Notices]
[Pages 32107-32108]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-14770]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-504-000]


Notice of Request Under Blanket Authorization; Transwestern 
Pipeline Company, LLC

    Take notice that on June 14, 2018, Transwestern Pipeline Company, 
LLC (Transwestern), 1300 Main Street, Houston, Texas 7700, filed a 
Prior Notice Request pursuant to sections 157.203, 157.205, and 157.216 
of the Commission's regulations under the Natural Gas Act (NGA) for 
authorization to abandon in place the Atoka 3 Compressor Station 
consisting of five natural gas compressor engines,

[[Page 32108]]

compressors, yard and station piping, and ancillary related facilities 
located in Eddy County, New Mexico (Atoka 3 CS or Project) all as more 
fully set forth in the application, which is on file with the 
Commission and open to public inspection. The filing may also be viewed 
on the web at https://www.ferc.gov using the ``eLibrary'' link. Enter 
the docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Any questions regarding this Application should be directed to Mr. 
Kelly Allen, Manager, Regulatory Affairs Department for Transwestern 
Pipeline Company, LLC, 1300 Main Street, Houston, Texas 77002, or call 
713-989-2606, or by email [email protected].
    Any person may, within 60 days after the issuance of the instant 
notice by the Commission, file pursuant to Rule 214 of the Commission's 
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of 
intervention. Any person filing to intervene or the Commission's staff 
may, pursuant to section 157.205 of the Commission's Regulations under 
the NGA (18 CFR 157.205) file a protest to the request. If no protest 
is filed within the time allowed therefore, the proposed activity shall 
be deemed to be authorized effective the day after the time allowed for 
protest. If a protest is filed and not withdrawn within 30 days after 
the time allowed for filing a protest, the instant request shall be 
treated as an application for authorization pursuant to section 7 of 
the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
website (www.ferc.gov) under the ``e-Filing'' link. Persons unable to 
file electronically should submit an original and 5 copies of the 
protest or intervention to the Federal Energy regulatory Commission, 
888 First Street NE, Washington, DC 20426.

    Dated: July 2, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-14770 Filed 7-10-18; 8:45 am]