Notice of Application: Rover Pipeline LLC, 29551-29552 [2018-13495]

Download as PDF Federal Register / Vol. 83, No. 122 / Monday, June 25, 2018 / Notices 29551 DOE/FE ORDERS GRANTING IMPORT/EXPORT AUTHORIZATIONS—Continued 4192 ................ 05/22/18 18–57–NG 4193 ................ 05/23/18 18–60–NG 4194 ................ 05/23/18 18–61–NG 4080–A ........... 05/29/18 17–102–NG Tourmaline Oil Marketing Corp. Nexen Energy Marketing U.S.A. Inc. Morgan Stanley Capital Group Inc. Rice Energy Marketing LLC ... 4195 ................ 05/29/18 18–59–NG Jupiter Resources Inc ............ 4196 ................ 05/29/18 18–62–CNG; 16–169–NG Ferus Natural Gas Fuels (CNG) LLC. [FR Doc. 2018–13476 Filed 6–22–18; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP18–500–000] amozie on DSK3GDR082PROD with NOTICES1 Notice of Application: Rover Pipeline LLC Take notice that on June 8, 2018, Rover Pipeline LLC (Rover), 1300 Main Street, Houston, Texas 77002, filed in Docket No. CP18–500–000 an application pursuant to section 7(c) of the Natural Gas Act (NGA) and Part 157 of the Commission’s regulations for authorization to operate a new receipt point consisting of an existing side tap on Rover’s Burgettstown Lateral in Washington County, Pennsylvania (Revolution Receipt Point Project). Rover states that there are no associated construction activities or costs for the Revolution Receipt Point Project because its side tap was installed during the construction of the Burgettstown Lateral. The Revolution Receipt Point will receive up to 525,000 dekatherms per day from ETC Northeast Pipeline LLC, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding this application should be directed to Blair Lichtenwalter, Senior Director, Regulatory Affairs, Rover Pipeline LLC, 1300 Main Street, Houston, Texas 77002 VerDate Sep<11>2014 17:58 Jun 22, 2018 Jkt 244001 Order 4192 granting blanket authority to import natural gas from Canada. Order 4193 granting blanket authority to import/export natural gas from/to Canada/Mexico. Order 4194 granting blanket authority to import/export natural gas from/to Canada/Mexico. Order 4080–A vacating blanket authority to import/export natural gas from/to Canada. Order 4195 granting blanket authority to import natural gas from Canada. Order 4196 granting blanket authority to import/export CNG from/to Canada by truck and vacating prior authorization. at (713) 989–2605 or by email at Blair.Lictenwalter@energytransfer.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice, the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit seven copies of filings made in the proceeding with the Commission and must mail a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: July 9, 2018. E:\FR\FM\25JNN1.SGM 25JNN1 29552 Federal Register / Vol. 83, No. 122 / Monday, June 25, 2018 / Notices amozie on DSK3GDR082PROD with NOTICES1 Dated: June 18, 2018. Kimberly D. Bose, Secretary. L.L.C., Indianapolis Power & Light Company, Mountain View Power Partners, LLC, Mountain View Power Partners IV, LLC, The Dayton Power and [FR Doc. 2018–13495 Filed 6–22–18; 8:45 am] Light Company, 65HK 8me LLC, 67RK BILLING CODE 6717–01–P 8me LLC, 87RL 8me LLC, Antelope Big Sky Ranch LLC, Antelope DSR 1, LLC, Antelope DSR 2, LLC, Bayshore Solar A, DEPARTMENT OF ENERGY LLC, Bayshore Solar B, LLC, Bayshore Federal Energy Regulatory Solar C, LLC, Beacon Solar 1, LLC, Commission Beacon Solar 3, LLC, Beacon Solar 4, LLC, Central Antelope Dry Ranch C Combined Notice of Filings #1 LLC, Elevation Solar C LLC, FTS Master Tenant 1, LLC, Land of the Sky MT, Take notice that the Commission received the following electric corporate LLC, Latigo Wind Park, LLC, North Lancaster Ranch LLC, Pioneer Wind filings: Park I LLC, Sandstone Solar LLC, Sierra Docket Numbers: EC18–63–000. Solar Greenworks LLC, Solverde 1, LLC, Applicants: Bayou Cove Peaking Summer Solar LLC, Western Antelope Power LLC, Big Cajun I Peaking Power Blue Sky Ranch A LLC, Western LLC, CottonWood Energy Company LP, Antelope Blue Sky Ranch B LLC, Louisiana Generating LLC, NRG Western Antelope Dry Ranch LLC. Sterlington Power LLC, NRG Description: Notice of Non-Material Cottonwood Tenant LLC, NRG Power Change in Status of AES MBR Affiliates. Marketing LLC, Cleco Cajun LLC, Cleco Filed Date: 6/15/18. Corporate Holdings LLC, Cleco Group Accession Number: 20180615–5139. LLC, Cleco Partners L.P. Comments Due: 5 p.m. ET 7/6/18. Description: Response of Bayou Cove Docket Numbers: ER13–102–015. Peaking Power, LLC, et al. to May 16, Applicants: New York Independent 2018 Deficiency Letter. System Operator, Inc. Filed Date: 6/15/18. Description: Compliance filing: Accession Number: 20180615–5249. Correction of tariff record for 4/1/16 Comments Due: 5 p.m. ET 7/6/18. effective date—Order 1000 to be Docket Numbers: EC18–104–000. effective 4/1/2016. Applicants: Vectren Corporation, Filed Date: 6/18/18. CenterPoint Energy. Accession Number: 20180618–5055. Description: Joint Application for Comments Due: 5 p.m. ET 7/9/18. Authorization Under Section 203 of the Docket Numbers: ER18–1160–001. Federal Power Act of Vectren Applicants: NRG Cottonwood Tenant Corporation, et al. LLC. Filed Date: 6/15/18. Description: Tariff Amendment: Accession Number: 20180615–5252. Comments Due: 5 p.m. ET 7/6/18. Response to Request for Additional Information to be effective 4/1/2018. Take notice that the Commission Filed Date: 6/18/18. received the following electric rate Accession Number: 20180618–5078. filings: Comments Due: 5 p.m. ET 7/9/18. Docket Numbers: ER10–3145–011; Docket Numbers: ER18–1260–001. ER10–3116–011; ER13–1544–008; Applicants: Midcontinent ER10–3120–011; ER11–2036–011; ER16–930–005; ER10–3128–011; ER10– Independent System Operator, Inc., 1800–012; ER10–3136–011; ER11–2701– Entergy Services, Inc. Description: Tariff Amendment: 013; ER10–1728–011; ER15–1582–011; 2018–06–18_Entergy Deficiency ER15–1579–010; ER15–1914–012; Response re Att O Revisions For Tax ER16–1255–006; ER16–2201–005; Rate Change to be effective 6/1/2018. ER16–1955–006; ER17–1864–004; Filed Date: 6/18/18. ER17–1871–004; ER17–1909–004; Accession Number: 20180618–5079. ER17–544–005; ER17–306–005; ER16– Comments Due: 5 p.m. ET 7/9/18. 1738–006; ER16–474–007; ER16–1901– Docket Numbers: ER18–1769–001. 006; ER16–468–006; ER15–2668–001; Applicants: PJM Interconnection, ER15–2679–008; ER16–2578–006; L.L.C. ER16–2541–005; ER15–2680–008; Description: Tariff Amendment: ER15–762–012; ER16–2224–005; ER16– Supplemental Filing for First Revised 890–007; ER15–760–011; ER16–1973– ISA No. 4623, Queue No. AC1–152 006; ER16–1956–006. AC1–172 to be effective 5/10/2018. Applicants: AES Alamitos, LLC, AES Filed Date: 6/15/18. Energy Storage, LLC, AES ES Tait, LLC, Accession Number: 20180615–5167. AES Huntington Beach, L.L.C., AES Comments Due: 5 p.m. ET 7/6/18. Laurel Mountain, LLC, AES Ohio Generation, LLC, AES Redondo Beach, Docket Numbers: ER18–1790–000. VerDate Sep<11>2014 17:58 Jun 22, 2018 Jkt 244001 PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 Applicants: Puget Sound Energy, Inc. Description: § 205(d) Rate Filing: Powerex PTP SA 880 to be effective 9/1/2018. Filed Date: 6/15/18. Accession Number: 20180615–5166. Comments Due: 5 p.m. ET 7/6/18. Docket Numbers: ER18–1791–000. Applicants: Duke Energy Florida, LLC. Description: Tariff Cancellation: DEF Notice of Termination (US EcoGen Polk, LLC LGIA SA–180) to be effective 8/15/ 2018. Filed Date: 6/15/18. Accession Number: 20180615–5168. Comments Due: 5 p.m. ET 7/6/18. Docket Numbers: ER18–1792–000. Applicants: PacifiCorp. Description: § 205(d) Rate Filing: RS 560 Hurricane Filing to Comply With Docket No. ER18–1254–000 to be effective 8/15/2018. Filed Date: 6/15/18. Accession Number: 20180615–5246. Comments Due: 5 p.m. ET 7/6/18. Docket Numbers: ER18–1793–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to WMPA SA No. 3202; Queue No. W3–077 to be effective 4/30/ 2014. Filed Date: 6/18/18. Accession Number: 20180618–5053. Comments Due: 5 p.m. ET 7/9/18. Docket Numbers: ER18–1794–000. Applicants: Southwestern Electric Power Company. Description: § 205(d) Rate Filing: Bentonville PSA to be effective 5/31/ 2018. Filed Date: 6/18/18. Accession Number: 20180618–5070. Comments Due: 5 p.m. ET 7/9/18. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES18–40–000. Applicants: ITC Midwest LLC. Description: Application under Section 204 of the Federal Power Act of ITC Midwest LLC for authorization to issue debt securities. Filed Date: 6/15/18. Accession Number: 20180615–5150. Comments Due: 5 p.m. ET 7/6/18. Take notice that the Commission received the following PURPA 210(m)(3) filings: Docket Numbers: QM18–10–000. Applicants: Cooperative Energy. Description: Response of Cooperative Energy to May 18, 2018 Deficiency Letter. Filed Date: 6/18/18. Accession Number: 20180618–5056. E:\FR\FM\25JNN1.SGM 25JNN1

Agencies

[Federal Register Volume 83, Number 122 (Monday, June 25, 2018)]
[Notices]
[Pages 29551-29552]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-13495]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-500-000]


Notice of Application: Rover Pipeline LLC

    Take notice that on June 8, 2018, Rover Pipeline LLC (Rover), 1300 
Main Street, Houston, Texas 77002, filed in Docket No. CP18-500-000 an 
application pursuant to section 7(c) of the Natural Gas Act (NGA) and 
Part 157 of the Commission's regulations for authorization to operate a 
new receipt point consisting of an existing side tap on Rover's 
Burgettstown Lateral in Washington County, Pennsylvania (Revolution 
Receipt Point Project). Rover states that there are no associated 
construction activities or costs for the Revolution Receipt Point 
Project because its side tap was installed during the construction of 
the Burgettstown Lateral. The Revolution Receipt Point will receive up 
to 525,000 dekatherms per day from ETC Northeast Pipeline LLC, all as 
more fully set forth in the application which is on file with the 
Commission and open to public inspection. The filing is available for 
review at the Commission in the Public Reference Room or may be viewed 
on the Commission's website web at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding this application should be directed to 
Blair Lichtenwalter, Senior Director, Regulatory Affairs, Rover 
Pipeline LLC, 1300 Main Street, Houston, Texas 77002 at (713) 989-2605 
or by email at [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit seven copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: July 9, 2018.


[[Page 29552]]


    Dated: June 18, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-13495 Filed 6-22-18; 8:45 am]
 BILLING CODE 6717-01-P