Notice of Revised Schedule for Environmental Review of the Calcasieu Pass Project: Venture Global Calcasieu Pass, LLC; Transcameron Pipeline, LLC, 24103 [2018-11167]

Download as PDF Federal Register / Vol. 83, No. 101 / Thursday, May 24, 2018 / Notices protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on June 4, 2018. Dated: May 18, 2018. Kimberly D. Bose, Secretary. to intervene or protest must serve a copy of that document on the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on May 21, 2018. Dated: May 18, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–11169 Filed 5–23–18; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2018–11164 Filed 5–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Docket Nos. CP15–550–000; CP15–551– 001] [Docket No. EL18–79–000] sradovich on DSK3GMQ082PROD with NOTICES Cheyenne Light, Fuel and Power Company; Notice of Filing Take notice that on April 30, 2018, Cheyenne Light, Fuel and Power Company submitted a response to the March 15, 2018 Show Cause Order.1 Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion 1 Alcoa Power Generation, Inc.—Long Sault Division, et al., 162 FERC ¶ 61,224 (2018) (Show Cause Order). VerDate Sep<11>2014 18:10 May 23, 2018 Jkt 244001 Notice of Revised Schedule for Environmental Review of the Calcasieu Pass Project: Venture Global Calcasieu Pass, LLC; Transcameron Pipeline, LLC May 18, 2018. This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental impact statement (EIS) for Venture Global Calcasieu Pass, LLC and TransCameron Pipeline, LLC’s Calcasieu Pass Project. The first notice of schedule, issued on November 29, 2017, identified July 3, 2018 as the final EIS issuance date. Due to staff’s recent request for supplemental engineering information, staff has revised the schedule for issuance of the final EIS based on an issuance of the draft EIS in June 2018. The forecasted schedule for both the draft and final EIS is based upon Global Calcasieu Pass, LLC and TransCameron Pipeline, LLC providing complete and timely responses to any PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 24103 future data requests. In addition, the schedule assumes that the cooperating agencies will provide input on their areas of responsibility on a timely basis. Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—October 26, 2018 90-Day Federal Authorization Decision Deadline—January 24, 2019 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208– FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP15–550 or CP15–551), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Kimberly D. Bose, Secretary. [FR Doc. 2018–11167 Filed 5–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL18–109–000] Notice of Filing: Portland General Electric Company Take notice that on May 14, 2018, Portland General Electric Company E:\FR\FM\24MYN1.SGM 24MYN1

Agencies

[Federal Register Volume 83, Number 101 (Thursday, May 24, 2018)]
[Notices]
[Page 24103]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-11167]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP15-550-000; CP15-551-001]


Notice of Revised Schedule for Environmental Review of the 
Calcasieu Pass Project: Venture Global Calcasieu Pass, LLC; 
Transcameron Pipeline, LLC

May 18, 2018.
    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental impact 
statement (EIS) for Venture Global Calcasieu Pass, LLC and TransCameron 
Pipeline, LLC's Calcasieu Pass Project. The first notice of schedule, 
issued on November 29, 2017, identified July 3, 2018 as the final EIS 
issuance date. Due to staff's recent request for supplemental 
engineering information, staff has revised the schedule for issuance of 
the final EIS based on an issuance of the draft EIS in June 2018. The 
forecasted schedule for both the draft and final EIS is based upon 
Global Calcasieu Pass, LLC and TransCameron Pipeline, LLC providing 
complete and timely responses to any future data requests. In addition, 
the schedule assumes that the cooperating agencies will provide input 
on their areas of responsibility on a timely basis.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--October 26, 2018
90-Day Federal Authorization Decision Deadline--January 24, 2019

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's
    Office of External Affairs at (866) 208-FERC or on the FERC website 
(www.ferc.gov). Using the ``eLibrary'' link, select ``General Search'' 
from the eLibrary menu, enter the selected date range and ``Docket 
Number'' excluding the last three digits (i.e., CP15-550 or CP15-551), 
and follow the instructions. For assistance with access to eLibrary, 
the helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or 
at [email protected]. The eLibrary link on the FERC website 
also provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-11167 Filed 5-23-18; 8:45 am]
 BILLING CODE 6717-01-P