San Diego County Water Authority; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions, 17821-17822 [2018-08479]

Download as PDF Federal Register / Vol. 83, No. 79 / Tuesday, April 24, 2018 / Notices Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: April 18, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–08476 Filed 4–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 5670–001] daltland on DSKBBV9HB2PROD with NOTICES San Diego County Water Authority; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Amendment of Conduit Exemption. b. Project No.: 5670–001. c. Date filed: April 3, 2018. d. Applicant: San Diego County Water Authority. e. Name of Project: Alvarado Hydroelectric Project. f. Location: The project is located within Alvarado Water Treatment Plant in the city of San Diego, San Diego VerDate Sep<11>2014 17:03 Apr 23, 2018 Jkt 244001 County, California. The land on which all the project facilities are located is owned by the applicant. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Brent Fountain, Engineer, 4677 Overland Avenue, San Diego, California 92123, phone (858) 522–6808. i. FERC Contact: Christopher Chaney, (202) 502–6778 or christopher.chaney@ ferc.gov. j. Deadline for filing responsive documents: Due to the small size of the proposed project, as well as the resource agency consultation letters filed with the application, the 60-day timeframe specified in 18 CFR 4.34(b) for filing all comments, motions to intervene, protests, recommendations, terms and conditions, and prescriptions is shortened to 30 days from the issuance date of this notice. All reply comments must be filed with the Commission within 45 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–5670–001. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, it must also serve a copy of the document on that resource agency. k. Description of Project: The proposed amendment consists of the rehabilitation of the existing hydroelectric facility by: (1) Replacing the two existing, 1-megawatt (MW) turbine/generating units with a single, 1.7 MW-rated turbine/generating unit, switchgear, and generator protection panels; and (2) installing a flow control PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 17821 bypass line to provide flow to the water treatment plant when the project is offline. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s website at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number, P–5670, in the docket number field to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1– 866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified deadline date for the particular application. n. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title COMMENTS, PROTEST, MOTION TO INTERVENE, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading, the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents E:\FR\FM\24APN1.SGM 24APN1 17822 Federal Register / Vol. 83, No. 79 / Tuesday, April 24, 2018 / Notices with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: April 18, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–08479 Filed 4–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD18–5–000] GenH, Inc.; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene On April 12, 2018, GenH, Inc. filed a notice of intent to construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act (FPA), as amended by section 4 of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Mohawk Hydro Station Project would have an installed capacity of up to 150 kilowatts (kW), and would be located at an existing unnamed drop along the Wellton-Mohawk Canal in Roll, Yuma County, Arizona. Applicant Contact: Robert Freda, 306 Bellevue St., Boston, MA 02132, Phone No. (617) 435–6288. FERC Contact: Christopher Chaney, Phone No. (202) 502–6778, email: Christopher.Chaney@ferc.gov. Qualifying Conduit Hydropower Facility Description: The proposed project would consist of: (1) Up to 10 15-kW Turgo turbine units with a total installed capacity of up to 150 kW located at an unnamed drop along the Wellton-Mohawk Canal; and (2) appurtenant facilities. The proposed project would have an estimated annual generating capacity of up to approximately 1,336,000 kilowatt-hours. A qualifying conduit hydropower facility is one that is determined or deemed to meet all of the criteria shown in the table below. TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A), as amended by HREA .. The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit.. The facility has an installed capacity that does not exceed 5 megawatts. ................. Y FPA 30(a)(3)(C)(i), as amended by HREA daltland on DSKBBV9HB2PROD with NOTICES FPA 30(a)(3)(C)(ii), as amended HREA. FPA 30(a)(3)(C)(iii), as amended HREA. by by On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.. Preliminary Determination: The proposed addition of the hydroelectric project along the existing irrigation canal will not alter its primary purpose. Therefore, based upon the above information and criteria, Commission staff preliminarily determines that the proposal satisfies the requirements for a qualifying conduit hydropower facility, which is not required to be licensed or exempted from licensing. Comments and Motions to Intervene: Deadline for filing comments contesting whether the facility meets the qualifying criteria is 45 days from the issuance date of this notice. Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. VerDate Sep<11>2014 17:03 Apr 23, 2018 Jkt 244001 Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY or MOTION TO INTERVENE, as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior 1 18 PO 00000 CFR 385.2001–2005 (2017). Frm 00035 Fmt 4703 Sfmt 4703 Y Y Y registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Locations of Notice of Intent: Copies of the notice of intent can be obtained directly from the applicant or such copies can be viewed and reproduced at the Commission in its Public Reference Room, Room 2A, 888 First Street NE, Washington, DC 20426. The filing may also be viewed on the web at https:// www.ferc.gov/docs-filing/elibrary.asp E:\FR\FM\24APN1.SGM 24APN1

Agencies

[Federal Register Volume 83, Number 79 (Tuesday, April 24, 2018)]
[Notices]
[Pages 17821-17822]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-08479]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 5670-001]


San Diego County Water Authority; Notice of Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, Protests, 
Recommendations, and Terms and Conditions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Amendment of Conduit Exemption.
    b. Project No.: 5670-001.
    c. Date filed: April 3, 2018.
    d. Applicant: San Diego County Water Authority.
    e. Name of Project: Alvarado Hydroelectric Project.
    f. Location: The project is located within Alvarado Water Treatment 
Plant in the city of San Diego, San Diego County, California. The land 
on which all the project facilities are located is owned by the 
applicant.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Brent Fountain, Engineer, 4677 Overland 
Avenue, San Diego, California 92123, phone (858) 522-6808.
    i. FERC Contact: Christopher Chaney, (202) 502-6778 or 
[email protected].
    j. Deadline for filing responsive documents: Due to the small size 
of the proposed project, as well as the resource agency consultation 
letters filed with the application, the 60-day timeframe specified in 
18 CFR 4.34(b) for filing all comments, motions to intervene, protests, 
recommendations, terms and conditions, and prescriptions is shortened 
to 30 days from the issuance date of this notice. All reply comments 
must be filed with the Commission within 45 days from the issuance date 
of this notice.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please 
send a paper copy to: Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Washington, DC 20426. The first page of any filing 
should include docket number P-5670-001.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, it must also serve a 
copy of the document on that resource agency.
    k. Description of Project: The proposed amendment consists of the 
rehabilitation of the existing hydroelectric facility by: (1) Replacing 
the two existing, 1-megawatt (MW) turbine/generating units with a 
single, 1.7 MW-rated turbine/generating unit, switchgear, and generator 
protection panels; and (2) installing a flow control bypass line to 
provide flow to the water treatment plant when the project is offline.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 
20426, or by calling (202) 502-8371. This filing may also be viewed on 
the Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number, P-5670, in the docket number 
field to access the document. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of 
new filings and issuances related to this or other pending projects. 
For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
and .214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
deadline date for the particular application.
    n. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title COMMENTS, PROTEST, MOTION TO 
INTERVENE, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or 
PRESCRIPTIONS; (2) set forth in the heading, the name of the applicant 
and the project number of the application to which the filing responds; 
(3) furnish the name, address, and telephone number of the person 
protesting or intervening; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, motions 
to intervene, or protests must set forth their evidentiary basis and 
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may 
obtain copies of the application directly from the applicant. A copy of 
any protest or motion to intervene must be served upon each 
representative of the applicant specified in the particular 
application. If an intervener files comments or documents

[[Page 17822]]

with the Commission relating to the merits of an issue that may affect 
the responsibilities of a particular resource agency, they must also 
serve a copy of the document on that resource agency. A copy of all 
other filings in reference to this application must be accompanied by 
proof of service on all persons listed in the service list prepared by 
the Commission in this proceeding, in accordance with 18 CFR 4.34(b) 
and 385.2010.

    Dated: April 18, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-08479 Filed 4-23-18; 8:45 am]
BILLING CODE 6717-01-P