Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization, 17820-17821 [2018-08476]

Download as PDF daltland on DSKBBV9HB2PROD with NOTICES 17820 Federal Register / Vol. 83, No. 79 / Tuesday, April 24, 2018 / Notices Description: Joint Petition for Limited Waiver of Capacity Release Regulations and Tariff Provisions of NRG Canal LLC, et al. Filed Date: 4/12/18. Accession Number: 20180412–5075. Comments Due: 5 p.m. ET 4/24/18. Docket Numbers: RP18–701–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: GT&C Section 14.3 Modification to be effective 5/12/2018. Filed Date: 4/12/18. Accession Number: 20180412–5112. Comments Due: 5 p.m. ET 4/24/18. Docket Numbers: RP18–702–000. Applicants: National Fuel Gas Supply Corporation. Description: § 4(d) Rate Filing: NonConforming Line K Uprate to be effective 6/1/2018. Filed Date: 4/12/18. Accession Number: 20180412–5137. Comments Due: 5 p.m. ET 4/24/18. Docket Numbers: RP17–598–004. Applicants: Great Lakes Gas Transmission Limited Partnership. Description: Compliance filing Settlement Compliance to RP17–598– 001 to be effective 10/1/2017. Filed Date: 4/13/18. Accession Number: 20180413–5108. Comments Due: 5 p.m. ET 4/25/18. Docket Numbers: RP18–703–000. Applicants: Algonquin Gas Transmission, LLC. Description: § 4(d) Rate Filing: Negotiated Rate—Bay State to Macquarie 796310 to be effective 5/1/2018. Filed Date: 4/13/18. Accession Number: 20180413–5002. Comments Due: 5 p.m. ET 4/25/18. Docket Numbers: RP18–704–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: § 4(d) Rate Filing: Negotiated Agreement Update Filing (Conoco Redesignation Apr 18) to be effective 4/16/2018. Filed Date: 4/13/18. Accession Number: 20180413–5169. Comments Due: 5 p.m. ET 4/25/18. Docket Numbers: RP18–705–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Amendment to NRA—Macquarie Energy LLC to be effective 4/13/2018. Filed Date: 4/13/18. Accession Number: 20180413–5182. Comments Due: 5 p.m. ET 4/25/18. Docket Numbers: RP18–706–000. Applicants: Gulf Crossing Pipeline Company LLC. Description: § 4(d) Rate Filing: Cap Rel Neg Rate Agmt (Newfield 18 to Sequent 1971) to be effective 4/12/2018. VerDate Sep<11>2014 17:03 Apr 23, 2018 Jkt 244001 Filed Date: 4/16/18. Accession Number: 20180416–5071. Comments Due: 5 p.m. ET 4/30/18. Docket Numbers: RP18–707–000. Applicants: Guardian Pipeline, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate PAL Agreement— MIECO, INC to be effective 4/16/2018. Filed Date: 4/16/18. Accession Number: 20180416–5150. Comments Due: 5 p.m. ET 4/30/18. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 18, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–08489 Filed 4–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP18–173–000] Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization Take notice that on April 10, 2018, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, filed in Docket No. CP18–173–000 a prior notice request pursuant to sections 157.205 and 157.213(b) of the Commission’s regulations under the Natural Gas Act (NGA), requesting authorization to construct and operate one new horizontal storage well, designated Well 12622, and related pipeline and appurtenances at Columbia’s Weaver Storage Field, located in Ashland, Holmes, Knox, and Richland Counties, Ohio. Columbia estimates the cost of the proposed project to be approximately $2,800,000, PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Linda Farquhar, Manager, Project Determinations & Regulatory Administration, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, by telephone at (832) 320– 5685, by fax at (832) 320–6685, or by email at linda_farquhar@ transcanada.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s EA. E:\FR\FM\24APN1.SGM 24APN1 Federal Register / Vol. 83, No. 79 / Tuesday, April 24, 2018 / Notices Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: April 18, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–08476 Filed 4–23–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 5670–001] daltland on DSKBBV9HB2PROD with NOTICES San Diego County Water Authority; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Amendment of Conduit Exemption. b. Project No.: 5670–001. c. Date filed: April 3, 2018. d. Applicant: San Diego County Water Authority. e. Name of Project: Alvarado Hydroelectric Project. f. Location: The project is located within Alvarado Water Treatment Plant in the city of San Diego, San Diego VerDate Sep<11>2014 17:03 Apr 23, 2018 Jkt 244001 County, California. The land on which all the project facilities are located is owned by the applicant. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Brent Fountain, Engineer, 4677 Overland Avenue, San Diego, California 92123, phone (858) 522–6808. i. FERC Contact: Christopher Chaney, (202) 502–6778 or christopher.chaney@ ferc.gov. j. Deadline for filing responsive documents: Due to the small size of the proposed project, as well as the resource agency consultation letters filed with the application, the 60-day timeframe specified in 18 CFR 4.34(b) for filing all comments, motions to intervene, protests, recommendations, terms and conditions, and prescriptions is shortened to 30 days from the issuance date of this notice. All reply comments must be filed with the Commission within 45 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc. gov/docs-filing/ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–5670–001. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, it must also serve a copy of the document on that resource agency. k. Description of Project: The proposed amendment consists of the rehabilitation of the existing hydroelectric facility by: (1) Replacing the two existing, 1-megawatt (MW) turbine/generating units with a single, 1.7 MW-rated turbine/generating unit, switchgear, and generator protection panels; and (2) installing a flow control PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 17821 bypass line to provide flow to the water treatment plant when the project is offline. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s website at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number, P–5670, in the docket number field to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1– 866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified deadline date for the particular application. n. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title COMMENTS, PROTEST, MOTION TO INTERVENE, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading, the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents E:\FR\FM\24APN1.SGM 24APN1

Agencies

[Federal Register Volume 83, Number 79 (Tuesday, April 24, 2018)]
[Notices]
[Pages 17820-17821]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-08476]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-173-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization

    Take notice that on April 10, 2018, Columbia Gas Transmission, LLC 
(Columbia), 700 Louisiana Street, Suite 700, Houston, Texas 77002-2700, 
filed in Docket No. CP18-173-000 a prior notice request pursuant to 
sections 157.205 and 157.213(b) of the Commission's regulations under 
the Natural Gas Act (NGA), requesting authorization to construct and 
operate one new horizontal storage well, designated Well 12622, and 
related pipeline and appurtenances at Columbia's Weaver Storage Field, 
located in Ashland, Holmes, Knox, and Richland Counties, Ohio. Columbia 
estimates the cost of the proposed project to be approximately 
$2,800,000, all as more fully set forth in the application which is on 
file with the Commission and open to public inspection. The filing may 
also be viewed on the web at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, please 
contact FERC Online Support at [email protected] or toll free 
at (866) 208-3676, or TTY, contact (202) 502-8659.
    Any questions concerning this application may be directed to Linda 
Farquhar, Manager, Project Determinations & Regulatory Administration, 
Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, 
Houston, Texas 77002-2700, by telephone at (832) 320-5685, by fax at 
(832) 320-6685, or by email at [email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.

[[Page 17821]]

    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE, Washington, 
DC 20426.

    Dated: April 18, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-08476 Filed 4-23-18; 8:45 am]
BILLING CODE 6717-01-P