Download as PDF Federal Register / Vol. 83, No. 77 / Friday, April 20, 2018 / Notices FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 16, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–08307 Filed 4–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2788–017] sradovich on DSK3GMQ082PROD with NOTICES Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions; Goodyear Lake Hydro, LLC Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 2788–017. c. Date filed: February 27, 2017. d. Applicant: Goodyear Lake Hydro, LLC (Goodyear Lake Hydro). e. Name of Project: Colliersville Hydroelectric Project. f. Location: On the Susquehanna River, in the Town of Milford, Otsego County, New York. The project does not occupy lands of the United States. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Mr. Kevin Webb, Hydro Licensing Manager; Enel Green Power North America, Inc., 100 Brickstone Square, Suite 300, Andover, MA 01810; (978) 935–6039; kevin.webb@enel.com. i. FERC Contact: Emily Carter, (202) 502–6512 or emily.carter@ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–2788–017. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted, and is ready for environmental analysis at this time. l. The Colliersville Hydroelectric Project consists of: (1) A 200-foot-long, 35-foot-high reinforced-concrete Ambursen-type dam; (2) a 364-acre reservoir (Goodyear Lake) with a gross storage capacity of 7,800 acre-feet at a normal pool elevation of 1,150.22 feet National Geodetic Vertical Datum of 1929; (3) a 550-foot-long reinforced concrete power canal, approximately 50 feet wide and 6 feet deep at the head gates, extending from a head gate structure adjacent to the dam (i.e., the intake) to the powerhouse; (4) a 103foot-long by 33-foot-wide reinforced concrete powerhouse with trash racks with a clear spacing of 1.5 inches, and containing two turbines rated at 850 horsepower (HP) and 1,150 HP, and two generators having a rated capacity of 650 kilowatts (kW) and 850 kW, respectively; (5) a 300-foot-long and approximately 50- to 60-foot-wide tailrace; (6) approximately 80-foot-long, 4.16-kilovolt underground generator leads or transmission lines from the powerhouse to an adjacent substation owned by the New York State Electric and Gas Corporation; and (7) appurtenant facilities. Goodyear Lake Hydro operates the project in a run-of-river mode. The project experiences substantial seasonal and annual variations in generation, and generates an annual average of 5,985 megawatt-hours. Goodyear Lake Hydro proposes to continue to operate the project in run-of-river mode. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. All filings must (1) bear in all capital letters the title COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or PRESCRIPTIONS; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Deadline for Filing Comments, Recommendations, and Agency Terms and Conditions/Prescriptions ................................. Deadline for filing Reply Comments ........................................................................................................................................ Commission issues EA ............................................................................................................................................................ VerDate Sep<11>2014 17:44 Apr 19, 2018 Jkt 244001 PO 00000 Frm 00028 Fmt 4703 17547 Sfmt 4703 E:\FR\FM\20APN1.SGM 20APN1 June 2018. July 2018. November 2018. 17548 Federal Register / Vol. 83, No. 77 / Friday, April 20, 2018 / Notices Milestone Target date Comments due on EA ............................................................................................................................................................. Dated: April 16, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–08267 Filed 4–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness of Exempt Wholesale Generator Status Docket Nos. GSP Lost Nation LLC .................... GSP Merrimack LLC ..................... GSP Newington LLC ..................... GSP Schiller LLC .......................... GSP White Lake LLC .................... Gray Hawk Solar, LLC .................. Gregory Power Partners LLC ........ Montpelier Generating Station, LLC. Monument Generating Station, LLC. O.H. Hutchings CT, LLC ............... Sidney, LLC ................................... Tait Electric Generating Station, LLC. Yankee Street, LLC ....................... EG18–27–000 EG18–28–000 EG18–29–000 EG18–30–000 EG18–31–000 EG18–32–000 EG18–33–000 EG18–34–000 EG18–35–000 EG18–36–000 EG18–37–000 EG18–38–000 EG18–39–000 Take notice that during the month of March 2018, the status of the abovecaptioned entities as Exempt Wholesale Generators became effective by operation of the Commission’s regulations. 18 CFR 366.7(a)(2017). Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–08306 Filed 4–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission sradovich on DSK3GMQ082PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC18–84–000. Applicants: Star Energy Partners, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act, et al. of Star Energy Partners, LLC. Filed Date: 4/16/18. Accession Number: 20180416–5095. Comments Due: 5 p.m. ET 5/7/18. Take notice that the Commission received the following electric rate filings: VerDate Sep<11>2014 17:44 Apr 19, 2018 Jkt 244001 Docket Numbers: ER10–3297–013. Applicants: Powerex Corp. Description: Compliance filing: Compliance Filing to March 29 Letter Order to be effective 3/29/2018. Filed Date: 4/16/18. Accession Number: 20180416–5129. Comments Due: 5 p.m. ET 5/7/18. Docket Numbers: ER11–3917–001; ER10–2774–004. Applicants: Mojave Solar LLC, Arizona Solar One LLC. Description: Notice of Change in Status of Mojave Solar LLC, et al. Filed Date: 4/13/18. Accession Number: 20180413–5302. Comments Due: 5 p.m. ET 5/4/18. Docket Numbers: ER18–1375–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No. 5052; Queue No. AD1–028 to be effective 4/5/2018. Filed Date: 4/16/18. Accession Number: 20180416–5075. Comments Due: 5 p.m. ET 5/7/18. Docket Numbers: ER18–1376–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2018–04–16_SA 1558 Forward EnergyATC 8th Rev LGIA (G368) to be effective 4/2/2018. Filed Date: 4/16/18. Accession Number: 20180416–5159. Comments Due: 5 p.m. ET 5/7/18. Docket Numbers: ER18–1377–000. Applicants: Bayonne Plant Holding, L.L.C. Description: Tariff Cancellation: Notice of Cancellation to be effective 6/ 1/2018. Filed Date: 4/16/18. Accession Number: 20180416–5165. Comments Due: 5 p.m. ET 5/7/18. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES18–29–000. Applicants: Orange and Rockland Utilities, Inc. Description: Application of Orange and Rockland Utilities, Inc. for an Order Authorizing the Issue and Sale of Shortterm Debt. Filed Date: 4/16/18. Accession Number: 20180416–5092. Comments Due: 5 p.m. ET 5/7/18. Take notice that the Commission received the following qualifying facility filings: Docket Numbers: QF18–610–000. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 December 2018. Applicants: Trustees of Princeton University. Description: Form 556 of Trustees of Princeton University [Plainsboro]. Filed Date: 2/8/18. Accession Number: 20180208–5154. Comments Due: Non Applicable. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: April 16, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–08305 Filed 4–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2337–077] Notice of Availability of Final Environmental Assessment; PacifiCorp In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission) regulations, 18 CFR part 380, the Office of Energy Projects has reviewed the application for new license for the Prospect No. 3 Hydroelectric Project, located on the South Fork Rogue River in Jackson County, Oregon, and has prepared a Final Environmental Assessment (FEA) for the project. The project currently occupies 32.4 acres of federal land managed by the U.S. Forest Service as part of the Rogue RiverSiskiyou National Forest. E:\FR\FM\20APN1.SGM 20APN1

Agencies

[Federal Register Volume 83, Number 77 (Friday, April 20, 2018)]
[Notices]
[Pages 17547-17548]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-08267]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2788-017]


Notice of Application Ready for Environmental Analysis and 
Soliciting Comments, Recommendations, Terms and Conditions, and 
Prescriptions; Goodyear Lake Hydro, LLC

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 2788-017.
    c. Date filed: February 27, 2017.
    d. Applicant: Goodyear Lake Hydro, LLC (Goodyear Lake Hydro).
    e. Name of Project: Colliersville Hydroelectric Project.
    f. Location: On the Susquehanna River, in the Town of Milford, 
Otsego County, New York. The project does not occupy lands of the 
United States.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Mr. Kevin Webb, Hydro Licensing Manager; Enel 
Green Power North America, Inc., 100 Brickstone Square, Suite 300, 
Andover, MA 01810; (978) 935-6039; [email protected].
    i. FERC Contact: Emily Carter, (202) 502-6512 or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-2788-017.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted, and is ready for 
environmental analysis at this time.
    l. The Colliersville Hydroelectric Project consists of: (1) A 200-
foot-long, 35-foot-high reinforced-concrete Ambursen-type dam; (2) a 
364-acre reservoir (Goodyear Lake) with a gross storage capacity of 
7,800 acre-feet at a normal pool elevation of 1,150.22 feet National 
Geodetic Vertical Datum of 1929; (3) a 550-foot-long reinforced 
concrete power canal, approximately 50 feet wide and 6 feet deep at the 
head gates, extending from a head gate structure adjacent to the dam 
(i.e., the intake) to the powerhouse; (4) a 103-foot-long by 33-foot-
wide reinforced concrete powerhouse with trash racks with a clear 
spacing of 1.5 inches, and containing two turbines rated at 850 
horsepower (HP) and 1,150 HP, and two generators having a rated 
capacity of 650 kilowatts (kW) and 850 kW, respectively; (5) a 300-
foot-long and approximately 50- to 60-foot-wide tailrace; (6) 
approximately 80-foot-long, 4.16-kilovolt underground generator leads 
or transmission lines from the powerhouse to an adjacent substation 
owned by the New York State Electric and Gas Corporation; and (7) 
appurtenant facilities.
    Goodyear Lake Hydro operates the project in a run-of-river mode. 
The project experiences substantial seasonal and annual variations in 
generation, and generates an annual average of 5,985 megawatt-hours. 
Goodyear Lake Hydro proposes to continue to operate the project in run-
of-river mode.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at https://www.ferc.gov using the eLibrary link. 
Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, contact FERC 
Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or 
PRESCRIPTIONS; (2) set forth in the heading the name of the applicant 
and the project number of the application to which the filing responds; 
(3) furnish the name, address, and telephone number of the person 
submitting the filing; and (4) otherwise comply with the requirements 
of 18 CFR 385.2001 through 385.2005. All comments, recommendations, 
terms and conditions or prescriptions must set forth their evidentiary 
basis and otherwise comply with the requirements of 18 CFR 4.34(b). 
Agencies may obtain copies of the application directly from the 
applicant. Each filing must be accompanied by proof of service on all 
persons listed on the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Deadline for Filing Comments,               June 2018.
 Recommendations, and Agency Terms and
 Conditions/Prescriptions.
Deadline for filing Reply Comments........  July 2018.
Commission issues EA......................  November 2018.

[[Page 17548]]

 
Comments due on EA........................  December 2018.
------------------------------------------------------------------------


    Dated: April 16, 2018.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-08267 Filed 4-19-18; 8:45 am]
 BILLING CODE 6717-01-P