Holtec International HI-STORE Consolidated Interim Storage Facility Project, 14897-14898 [2018-07006]
Download as PDF
14897
Federal Register / Vol. 83, No. 67 / Friday, April 6, 2018 / Notices
environmental impact statement or
environmental assessment need be prepared
in connection with the approval of this
exemption request.
IV. Conclusions.
Accordingly, the Commission has
determined that, pursuant to 10 CFR 50.12(a),
the exemption is authorized by law, will not
present an undue risk to the public health
and safety, and is consistent with the
common defense and security. Also, special
circumstances are present. Therefore, the
Commission hereby grants OPPD an
exemption from the requirements of 10 CFR
50.54(w)(1), to permit the licensee to reduce
its onsite property damage insurance to a
level of $50 million.
The exemption is effective beginning April
7, 2018.
Dated at Rockville, Maryland, this 29th day
of March, 2018.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2018–07034 Filed 4–5–18; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 72–1051; NRC–2018–0052]
Holtec International HI–STORE
Consolidated Interim Storage Facility
Project
Nuclear Regulatory
Commission.
ACTION: Environmental impact
statement; public scoping meetings.
AGENCY:
On March 30, 2018, the U.S.
Nuclear Regulatory Commission (NRC)
published in the Federal Register a
notice of its intent to prepare an
SUMMARY:
environmental impact statement,
conduct scoping, and request comments
for Holtec International’s (Holtec)
application for the HI–STORE
Combined Interim Storage Facility
(CISF). The public scoping comment
period closes on May 29, 2018. The NRC
is announcing public scoping meetings
and an open house schedule. The public
scoping meetings will allow interested
members of the public to develop and
submit their comments.
DATES: April 6, 2018.
ADDRESSES: Please refer to Docket ID
NRC–2018–0052 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2018–0052. Address
questions about NRC dockets to Jennifer
Borges; telephone: 301–287–9127;
email: Jennifer.Borges@nrc.gov. For
technical questions, contact the
individual(s) listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
• Project web page: Information
related to the Holtec HI–STORE CISF
project can be accessed on the NRC’s
Holtec HI–STORE CISF web page at
https://www.nrc.gov/waste/spent-fuelstorage/cis/holtec-international.html.
• Public Libraries: A copy of the
application’s Environmental Report can
be accessed at the following public
libraries: Carlsbad Public Library, 101 S.
Halagueno Street, Carlsbad, NM 88220;
Hobbs Public Library, 509 N Shipp St.,
Hobbs, NM 88240; or Roswell Public
Library, 301 N. Pennsylvania, Roswell,
NM 88201.
FOR FURTHER INFORMATION CONTACT: Jill
Caverly, Office of Nuclear Material
Safety and Safeguards, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
7674; email: Jill.Caverly@nrc.gov.
SUPPLEMENTARY INFORMATION:
On March 30, 2018, the NRC
published in the Federal Register (83
FR 13802), a notice of its intent to
prepare an EIS on Holtec’s proposed
CISF for spent nuclear fuel and
requested public comments on the
scope of the EIS. The NRC is
announcing that staff will hold three
public scoping meetings and one open
house. The public scoping meetings will
be held in Rockville, Maryland;
Carlsbad, New Mexico; and Hobbs, New
Mexico. The dates and times for the
public meetings and open house are
provided below:
Date
Time
Location
Public Scoping Meeting and Webinar ...........
April 25, 2018 ......
7:00 p.m.–9:00 p.m. (EDT) ....
Open House ..................................................
April 30, 2018 ......
4:00 p.m.–7:00 p.m. (MDT) ...
Public Scoping Meeting .................................
May 1, 2018 ........
7:00 p.m.–10:00 p.m. (MDT)
Public Scoping Meeting .................................
daltland on DSKBBV9HB2PROD with NOTICES
Meeting/Open House
May 3, 2018 ........
7:00 p.m.–10:00 p.m. (MDT)
Rockville, Maryland, NRC Headquarters, Address: 11555 Rockville Pike, Rockville,
MD 20852
Roswell, New Mexico, Address: Eastern
New Mexico University—Roswell, Campus
Union Building, Multi-Purpose Room 110,
48 University Blvd., Roswell, NM 88130
Hobbs, New Mexico, Address: Lea County
Event Center, 5101 N. Lovington Highway, Hobbs, NM 88240
Carlsbad, New Mexico, Address: Eddy
County Fire Service, 1400 Commerce
Street, Carlsbad, NM 88220.
Persons interested in attending these
meeting should check the NRC’s Public
Meeting Schedule web page at https://
www.nrc.gov/pmns/mtg for additional
information, agendas for the meetings,
and access information for the webinar.
VerDate Sep<11>2014
19:21 Apr 05, 2018
Jkt 244001
For the meeting in Rockville, Maryland,
the NRC will transmit the public
meeting via webinar and provide a
telephone bridgeline for members of the
public who cannot attend the meeting in
person.
PO 00000
Frm 00056
Fmt 4703
Sfmt 4703
Dated at Rockville, Maryland, on April 2,
2018.
E:\FR\FM\06APN1.SGM
06APN1
14898
Federal Register / Vol. 83, No. 67 / Friday, April 6, 2018 / Notices
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Fuel Cycle Safety,
Safeguards, and Environmental Review,
Office of Nuclear Material Safety and
Safeguards.
[FR Doc. 2018–07006 Filed 4–5–18; 8:45 am]
BILLING CODE 7509–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2018–0001]
Sunshine Act Meeting Notice
Week of April 2, 2018.
Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public.
DATE:
PLACE:
Week of April 2
Thursday, April 5, 2018
daltland on DSKBBV9HB2PROD with NOTICES
Additional Information
By a vote of 3–0 on April 4, 2018, the
Commission determined pursuant to
U.S.C. 552b(e) and § 9.107(a) of the
Commission’s rules that the above
referenced Affirmation Session be held
with less than one week notice to the
public. The meeting is scheduled on
April 5, 2018.
*
*
*
*
*
The schedule for Commission
meetings is subject to change on short
notice. For more information or to verify
the status of meetings, contact Denise
McGovern at 301–415–0981 or via email
at Denise.McGovern@nrc.gov.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
19:21 Apr 05, 2018
Dated: April 4, 2018.
Glenn Ellmers,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2018–07246 Filed 4–4–18; 4:15 pm]
9:55 a.m. Affirmation Session (Public
Meeting) (Tentative)
a. Unitech Services Group, Inc.
(Export of Low-Level Waste)
(Petition Seeking Leave to Intervene
and Request for Hearing)
(Tentative).
b. Florida Power & Light Co. (Turkey
Point Nuclear Generating Units 6
and 7), Docket Nos. 52–040–COL &
52–041–COL, Mandatory Hearing
Decision (Tentative).
This meeting will be webcast live at
the web address—https://www.nrc.gov/.
*
*
*
*
*
VerDate Sep<11>2014
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.,
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0739, by
videophone at 240–428–3217, or by
email at Kimberly.Meyer-Chambers@
nrc.gov. Determinations on requests for
reasonable accommodation will be
made on a case-by-case basis.
*
*
*
*
*
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
Regulatory Commission, Office of the
Secretary, Washington, DC 20555 (301–
415–1969), or email Wendy.Moore@
nrc.gov or Patricia.Jimenez@nrc.gov.
Jkt 244001
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–285; NRC–2018–0067]
Omaha Public Power District; Fort
Calhoun Station, Unit No. 1
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued an
exemption from the requirement to
maintain a specified level of onsite
property damage insurance in response
to a request from Omaha Public Power
District (OPPD or the licensee) dated
April 28, 2017. Specifically, OPPD
requested an exemption from the
regulatory requirements to permit Fort
Calhoun Station (FCS) to reduce its
onsite insurance from $1.06 billion to
$50 million.
DATES: The exemption was issued on
March 29, 2018.
ADDRESSES: Please refer to Docket ID
NRC–2018–0067 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web Site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2018–0067. Address
questions about NRC dockets to Jennifer
Borges; telephone: 301–287–9127;
email: Jennifer.Borges@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
SUMMARY:
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
James S. Kim, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone: 301–415–4125, email:
James.Kim@nrc.gov.
SUPPLEMENTARY INFORMATION: The text of
the exemption is attached.
INFORMATION CONTACT
Dated at Rockville, Maryland, this 3rd day
of April, 2018.
For the Nuclear Regulatory Commission.
James S. Kim,
Project Manager, Special Projects and Process
Branch, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
Attachment—Exemption
NUCLEAR REGULATORY COMMISSION
Docket No. 50-285
Omaha Public Power District
Fort Calhoun Station, Unit No. 1
Exemption
I. Background.
The Fort Calhoun Station, Unit 1 (FCS) site
is located midway between Fort Calhoun and
Blair, Nebraska, on the west bank of the
Missouri River. The FCS facility includes one
Combustion Engineering pressurized water
reactor licensed to operate at power levels
not to exceed 1500 megawatts thermal. The
distance from the reactor containment to the
nearest site boundary is approximately 910
meters (.6 miles). Except for the city of Blair
and the villages of Fort Calhoun and
Kennard, the land use within the 10-mile
radius of FCS is devoted to general farming.
Omaha Public Power District (OPPD) is the
holder of Renewed Facility Operating
License No. DPR-40. The license provides,
among other things, that the facility is subject
to all rules, regulations, and orders of the
NRC now or hereafter in effect.
E:\FR\FM\06APN1.SGM
06APN1
Agencies
[Federal Register Volume 83, Number 67 (Friday, April 6, 2018)]
[Notices]
[Pages 14897-14898]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-07006]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 72-1051; NRC-2018-0052]
Holtec International HI-STORE Consolidated Interim Storage
Facility Project
AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental impact statement; public scoping meetings.
-----------------------------------------------------------------------
SUMMARY: On March 30, 2018, the U.S. Nuclear Regulatory Commission
(NRC) published in the Federal Register a notice of its intent to
prepare an environmental impact statement, conduct scoping, and request
comments for Holtec International's (Holtec) application for the HI-
STORE Combined Interim Storage Facility (CISF). The public scoping
comment period closes on May 29, 2018. The NRC is announcing public
scoping meetings and an open house schedule. The public scoping
meetings will allow interested members of the public to develop and
submit their comments.
DATES: April 6, 2018.
ADDRESSES: Please refer to Docket ID NRC-2018-0052 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2018-0052. Address
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact
the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
Project web page: Information related to the Holtec HI-
STORE CISF project can be accessed on the NRC's Holtec HI-STORE CISF
web page at https://www.nrc.gov/waste/spent-fuel-storage/cis/holtec-international.html.
Public Libraries: A copy of the application's
Environmental Report can be accessed at the following public libraries:
Carlsbad Public Library, 101 S. Halagueno Street, Carlsbad, NM 88220;
Hobbs Public Library, 509 N Shipp St., Hobbs, NM 88240; or Roswell
Public Library, 301 N. Pennsylvania, Roswell, NM 88201.
FOR FURTHER INFORMATION CONTACT: Jill Caverly, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone: 301-415-7674; email:
[email protected].
SUPPLEMENTARY INFORMATION:
On March 30, 2018, the NRC published in the Federal Register (83 FR
13802), a notice of its intent to prepare an EIS on Holtec's proposed
CISF for spent nuclear fuel and requested public comments on the scope
of the EIS. The NRC is announcing that staff will hold three public
scoping meetings and one open house. The public scoping meetings will
be held in Rockville, Maryland; Carlsbad, New Mexico; and Hobbs, New
Mexico. The dates and times for the public meetings and open house are
provided below:
----------------------------------------------------------------------------------------------------------------
Meeting/Open House Date Time Location
----------------------------------------------------------------------------------------------------------------
Public Scoping Meeting and April 25, 2018......... 7:00 p.m.-9:00 p.m. (EDT)............ Rockville,
Webinar. Maryland, NRC
Headquarters,
Address: 11555
Rockville Pike,
Rockville, MD
20852
Open House.................... April 30, 2018......... 4:00 p.m.-7:00 p.m. (MDT)............ Roswell, New
Mexico,
Address:
Eastern New
Mexico
University--Ros
well, Campus
Union Building,
Multi-Purpose
Room 110, 48
University
Blvd., Roswell,
NM 88130
Public Scoping Meeting........ May 1, 2018............ 7:00 p.m.-10:00 p.m. (MDT)........... Hobbs, New
Mexico,
Address: Lea
County Event
Center, 5101 N.
Lovington
Highway, Hobbs,
NM 88240
Public Scoping Meeting........ May 3, 2018............ 7:00 p.m.-10:00 p.m. (MDT)........... Carlsbad, New
Mexico,
Address: Eddy
County Fire
Service, 1400
Commerce
Street,
Carlsbad, NM
88220.
----------------------------------------------------------------------------------------------------------------
Persons interested in attending these meeting should check the
NRC's Public Meeting Schedule web page at https://www.nrc.gov/pmns/mtg
for additional information, agendas for the meetings, and access
information for the webinar. For the meeting in Rockville, Maryland,
the NRC will transmit the public meeting via webinar and provide a
telephone bridgeline for members of the public who cannot attend the
meeting in person.
Dated at Rockville, Maryland, on April 2, 2018.
[[Page 14898]]
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Fuel Cycle Safety, Safeguards, and Environmental
Review, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2018-07006 Filed 4-5-18; 8:45 am]
BILLING CODE 7509-01-P