Notice of Lodging of Proposed Consent Decree Under the Comprehensive Environmental Response, Compensation, and Liability Act, 11247-11248 [2018-05140]
Download as PDF
Federal Register / Vol. 83, No. 50 / Wednesday, March 14, 2018 / Notices
not to reach the issue of whether
Fujifilm has satisfied the economic
prong with respect to its domestic
investments in its LTO–7 DI products.
Accordingly, the Commission has
determined the appropriate remedy is a
limited exclusion order against Sony’s
products that infringe claims 1, 4–9, 11,
and 14 of the ’891 patent, and a cease
and desist order against each of the
Sony respondents. The Commission has
also determined that the public interest
factors enumerated in subsections
337(d)(l) and (f)(1) (19 U.S.C. 1337(d)(l),
(f)(1)) do not preclude issuance of the
limited exclusion order and cease and
desist order. The Commission has,
however, determined to exempt Sony’s
magnetic data storage tapes and
cartridges containing the same that are
imported or used for the purpose of
supporting Sony’s warranty, service,
repair, and compliance verification
obligations. The Commission has further
determined to set a bond at zero (0)
percent of entered value during the
Presidential review period (19 U.S.C.
1337(j)).
The Commission’s orders and opinion
were delivered to the President and to
the United States Trade Representative
on the day of their issuance.
The authority for the Commission’s
determination is contained in section
337 of the Tariff Act of 1930, as
amended (19 U.S.C. 1337), and in Part
210 of the Commission’s Rules of
Practice and Procedure (19 CFR part
210).
By order of the Commission.
Issued: March 8, 2018.
Katherine M. Hiner,
Supervisory Attorney.
Retirement Plan for recovery of past
response costs incurred at the Widefield
PCE Superfund Site (‘‘Site’’) in El Paso
County, Colorado. The Site comprises a
former dry cleaners at 3217 South
Academy Boulevard in Colorado
Springs and related contamination of
soil and groundwater, including of the
Widefield Aquifer. The El Paso County
Retirement Plan was the owner of the
3217 South Academy Boulevard
property at the time of disposal of
hazardous substances. The proposed
Consent Decree requires the El Paso
County Retirement Plan to pay $420,000
in reimbursement of past response costs
incurred by the United States with
respect to the Site. The proposed
Consent Decree provides the El Paso
County Retirement Plan with a covenant
not to sue for past response costs
incurred by the United States in
connection with the Site and
contribution protection under CERCLA.
The publication of this notice opens
a period for public comment on the
proposed Consent Decree. Comments
should be addressed to the Assistant
Attorney General, Environment and
Natural Resources Division, and should
refer to United States v. El Paso County
Retirement Plan, D.J. Ref. No. 90–11–3–
11721/1. All comments must be
submitted no later than thirty (30) days
after the publication date of this notice.
Comments may be submitted either by
email or by mail:
To submit
comments:
By email ......
[FR Doc. 2018–05093 Filed 3–13–18; 8:45 am]
Send them to:
pubcomment-ees.enrd@
usdoj.gov.
Assistant Attorney General,
U.S. DOJ—ENRD, P.O. Box
7611, Washington, DC
20044–7611.
By mail ........
BILLING CODE 7020–02–P
DEPARTMENT OF JUSTICE
daltland on DSKBBV9HB2PROD with NOTICES
Notice of Lodging of Proposed
Consent Decree Under the
Comprehensive Environmental
Response, Compensation and Liability
Act
On March 8, 2018, the Department of
Justice lodged a proposed Consent
Decree with the United States District
Court for the District of Colorado in the
lawsuit entitled United States v. El Paso
County Retirement Plan, Civil Action
No. 1:18–cv–00552.
The proposed Consent Decree
resolves the United States’ claim under
Section 107 of the Comprehensive
Environmental Response, Compensation
and Liability Act (‘‘CERCLA’’), 42 U.S.C.
9607, against the El Paso County
VerDate Sep<11>2014
18:17 Mar 13, 2018
Jkt 244001
During the public comment period,
the proposed Consent Decree may be
examined and downloaded at this
Justice Department website: https://
www.justice.gov/enrd/consent-decrees.
We will provide a paper copy of the
proposed Consent Decree upon written
request and payment of reproduction
costs. Please mail your request and
payment to: Consent Decree Library,
U.S. DOJ—ENRD, P.O. Box 7611,
Washington, DC 20044–7611.
Please enclose a check or money order
for $3.75 (25 cents per page
PO 00000
Frm 00080
Fmt 4703
Sfmt 4703
11247
reproduction cost) payable to the United
States Treasury.
Robert Brook,
Assistant Section Chief, Environmental
Enforcement Section, Environment and
Natural Resources Division.
[FR Doc. 2018–05182 Filed 3–13–18; 8:45 am]
BILLING CODE 4410–15–P
DEPARTMENT OF JUSTICE
Notice of Lodging of Proposed
Consent Decree Under the
Comprehensive Environmental
Response, Compensation, and Liability
Act
On February 27, 2018, the Department
of Justice lodged a proposed Consent
Decree with the United States District
Court for the Southern District of Ohio
in the lawsuit entitled United States v.
Bridgestone Americas Tire Operations et
al., Case No. 3:18–cv–00054 (S.D. Ohio).
The proposed consent decree resolves
claims of the United States
Environmental Protection Agency
(‘‘EPA’’) against seven defendants—
Bridgestone Americas Tire Operations,
LLC; Cargill, Inc.; Flowserve
Corporation; Kelsey-Hayes Company;
NCR Corporation; Northrop Grumman
Systems Corporation, and Waste
Management of Ohio (collectively
‘‘Defendants)—for response costs and
injunctive relief with respect to the
North Sanitary (aka ‘‘Valleycrest’’)
Landfill Superfund Site in Dayton, Ohio
(‘‘Site’’). A complaint, which was filed
simultaneously with the proposed
consent decree, alleges that the
Defendants are liable under Sections
106, 107(a), and 113(g)(2) of the
Comprehensive Environmental
Response, Compensation, and Liability
Act (‘‘CERCLA’’), 42 U.S.C. 9606,
9607(a), and 9613(g)(2). Under the
proposed consent decree, the
defendants will perform the remedy
selected by EPA to address
contamination at the Site by, among
other things, designing and constructing
a landfill ‘‘cap’’ that will cover
approximately 70 acres of the Site.
Other significant remedial actions will
include the design and construction of
a system to address landfill gas, as well
as a system to prevent leachate from
contaminating groundwater.
Additionally, the Defendants will
reimburse EPA for its future response
costs, but they will not reimburse EPA
for its future oversight costs unless and
until such costs, together with past
response costs and interim costs
incurred before entry of the consent
decree, exceed $8.37 million. The
proposed consent decree will provide
E:\FR\FM\14MRN1.SGM
14MRN1
11248
Federal Register / Vol. 83, No. 50 / Wednesday, March 14, 2018 / Notices
covenants not to sue to the Defendants,
as well as to numerous other potentially
responsible parties (‘‘Other Settling
Parties’’) who have previously entered
into settlement agreements with one or
more of the Defendants and, in most
instances, received indemnifications
from them, provided that such Other
Settling Parties (listed in Appendix E of
the consent decree) submit signature
pages agreeing to be bound by the
consent decree and, if they own
property likely affected by the remedial
action, cooperate in the implementation
of the consent decree.
The publication of this notice opens
a period for public comment on the
proposed consent decree. Comments
should be addressed to the Assistant
Attorney General, Environment and
Natural Resources Division, and should
refer United States v. Bridgestone
Americas Tire Operations et al., Case
No. 3:18–cv–00054 (S.D. Ohio), D.J. Ref.
No. 90–11–3–11076. All comments must
be submitted no later than thirty (30)
days after the publication date of this
notice. Comments may be submitted
either by email or by mail:
To submit
comments:
Send them to:
By email .......
pubcomment-ees.enrd@
usdoj.gov.
Assistant Attorney General,
U.S. DOJ—ENRD, P.O.
Box 7611, Washington,
D.C. 20044–7611.
daltland on DSKBBV9HB2PROD with NOTICES
By mail .........
During the public comment period,
the proposed consent decree may be
examined and downloaded at this
Justice Department website: https://
www.usdoj.gov/enrd/consentdecrees.html. We will also provide a
paper copy of the proposed consent
decree upon written request and
payment of reproduction costs. Please
mail your request and payment to:
Consent Decree Library, U.S. DOJ—
ENRD, P.O. Box 7611, Washington, DC
20044–7611.
Please enclose a check or money order
for $84.50 (338 pages at 25 cents per
page reproduction cost) payable to the
United States Treasury. For a paper
copy without the Appendices and
signature pages, the cost is $20.75.
Randall M. Stone,
Acting Assistant Section Chief,
Environmental Enforcement Section,
Environment and Natural Resources Division.
[FR Doc. 2018–05140 Filed 3–13–18; 8:45 am]
BILLING CODE 4410–15–P
VerDate Sep<11>2014
18:17 Mar 13, 2018
Jkt 244001
DEPARTMENT OF JUSTICE
Notice of Lodging of Proposed
Modification to Consent Decree Under
The Clean Air Act
On March 6, 2018, the Department of
Justice lodged with the United States
District Court for the District of Kansas
a proposed modification to the consent
decree entered by the Court on March
26, 2010 in the lawsuit entitled United
States of America, et al. v. Westar
Energy, Inc., Civil Action No. 2:09–cv–
02059–JAR.
The consent decree resolved claims
asserted by the United States against
Westar Energy, Inc. (‘‘Westar’’) under
various provisions of the Clean Air Act
(‘‘Act’’). Those claims related to
Westar’s operation of the Jeffrey Energy
Center (‘‘JEC’’), a coal-fired power plant
in St. Marys, Kansas with three electric
generating units, numbered 1 through 3.
The United States alleged in primary
part that Westar made major
modifications to JEC without obtaining
a permit under the Prevention of
Significant Deterioration program.
The Consent Decree requires Westar,
among other things, to install and
operate Selective Catalytic Reduction
(‘‘SCR’’) on one of the JEC units and, at
Westar’s election, either install a second
SCR or meet a plant-wide 30-day rolling
average emission rate of 0.100 lb/
mmBTU NOX. Westar installed the SCR
on JEC Unit 1 and elected to meet a
plant-wide 30-day rolling average
emission rate of 0.100 lb/mmBTU NOX.
To meet this limit, Westar must operate
JEC Unit 1 (the unit with the SCR) at all
times when it is available, even when it
would not otherwise be dispatched by
the Regional Transmission
Organization. This results in
unnecessary emissions of NOX, sulfur
dioxide, particulate matter and other
pollutants from JEC.
The proposed modification to the
Consent Decree would require Westar to
meet a 30-Day Rolling Average Unit
Emission Rate for NOX of 0.150 lb/
mmBTU, on an individual unit basis,
when JEC Unit 1 is not operating.
Overall emissions from JEC, including
emissions of NOX, are expected to
decrease as a result of the change
because JEC Unit 1 would no longer be
forced to operate to meet the Consent
Decree NOX Plant-Wide Operating Day
emission limitation. To help ensure that
NOX emissions do not increase, the
modification would also require Westar
to comply with a new NOX 12-Month
Rolling Tonnage Limitation for JEC
Units 2 and 3.
The publication of this notice opens
a period for public comment on the
PO 00000
Frm 00081
Fmt 4703
Sfmt 4703
modification to the consent decree.
Comments should be addressed to the
Assistant Attorney General,
Environment and Natural Resources
Division, and should refer to United
States, et al. v. Westar Energy, Inc., D.J.
Ref. No. 90–5–2–1–08242. All
comments must be submitted no later
than thirty (30) days after the
publication date of this notice.
Comments may be submitted either by
email or by mail:
To submit
comments:
Send them to:
By email .......
pubcomment-ees.enrd@
usdoj.gov.
Assistant Attorney General,
U.S. DOJ—ENRD, P.O.
Box 7611, Washington, DC
20044–7611.
By mail .........
During the public comment period,
the modification to the consent decree
may be examined and downloaded at
this Justice Department website: https://
www.justice.gov/enrd/consent-decrees.
We will provide a paper copy of the
modification to the consent decree upon
written request and payment of
reproduction costs. Please mail your
request and payment to: Consent Decree
Library, U.S. DOJ—ENRD, P.O. Box
7611, Washington, DC 20044–7611.
Please enclose a check or money order
for $4.25 (25 cents per page
reproduction cost) payable to the United
States Treasury.
Susan M. Akers,
Assistant Section Chief, Environmental
Enforcement Section, Environment and
Natural Resources Division.
[FR Doc. 2018–05184 Filed 3–13–18; 8:45 am]
BILLING CODE 4410–15–P
DEPARTMENT OF LABOR
Office of the Secretary
Agency Information Collection
Activities; Submission for OMB
Review; Comment Request; DavisBacon Certified Payroll
Notice of availability; request
for comments.
ACTION:
The Department of Labor
(DOL) is submitting the Wage and Hour
Division (WHD) sponsored information
collection request (ICR) titled, ‘‘DavisBacon Certified Payroll,’’ to the Office of
Management and Budget (OMB) for
review and approval for continued use,
without change, in accordance with the
Paperwork Reduction Act of 1995
(PRA). Public comments on the ICR are
invited.
SUMMARY:
E:\FR\FM\14MRN1.SGM
14MRN1
Agencies
[Federal Register Volume 83, Number 50 (Wednesday, March 14, 2018)]
[Notices]
[Pages 11247-11248]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-05140]
-----------------------------------------------------------------------
DEPARTMENT OF JUSTICE
Notice of Lodging of Proposed Consent Decree Under the
Comprehensive Environmental Response, Compensation, and Liability Act
On February 27, 2018, the Department of Justice lodged a proposed
Consent Decree with the United States District Court for the Southern
District of Ohio in the lawsuit entitled United States v. Bridgestone
Americas Tire Operations et al., Case No. 3:18-cv-00054 (S.D. Ohio).
The proposed consent decree resolves claims of the United States
Environmental Protection Agency (``EPA'') against seven defendants--
Bridgestone Americas Tire Operations, LLC; Cargill, Inc.; Flowserve
Corporation; Kelsey-Hayes Company; NCR Corporation; Northrop Grumman
Systems Corporation, and Waste Management of Ohio (collectively
``Defendants)--for response costs and injunctive relief with respect to
the North Sanitary (aka ``Valleycrest'') Landfill Superfund Site in
Dayton, Ohio (``Site''). A complaint, which was filed simultaneously
with the proposed consent decree, alleges that the Defendants are
liable under Sections 106, 107(a), and 113(g)(2) of the Comprehensive
Environmental Response, Compensation, and Liability Act (``CERCLA''),
42 U.S.C. 9606, 9607(a), and 9613(g)(2). Under the proposed consent
decree, the defendants will perform the remedy selected by EPA to
address contamination at the Site by, among other things, designing and
constructing a landfill ``cap'' that will cover approximately 70 acres
of the Site. Other significant remedial actions will include the design
and construction of a system to address landfill gas, as well as a
system to prevent leachate from contaminating groundwater.
Additionally, the Defendants will reimburse EPA for its future response
costs, but they will not reimburse EPA for its future oversight costs
unless and until such costs, together with past response costs and
interim costs incurred before entry of the consent decree, exceed $8.37
million. The proposed consent decree will provide
[[Page 11248]]
covenants not to sue to the Defendants, as well as to numerous other
potentially responsible parties (``Other Settling Parties'') who have
previously entered into settlement agreements with one or more of the
Defendants and, in most instances, received indemnifications from them,
provided that such Other Settling Parties (listed in Appendix E of the
consent decree) submit signature pages agreeing to be bound by the
consent decree and, if they own property likely affected by the
remedial action, cooperate in the implementation of the consent decree.
The publication of this notice opens a period for public comment on
the proposed consent decree. Comments should be addressed to the
Assistant Attorney General, Environment and Natural Resources Division,
and should refer United States v. Bridgestone Americas Tire Operations
et al., Case No. 3:18-cv-00054 (S.D. Ohio), D.J. Ref. No. 90-11-3-
11076. All comments must be submitted no later than thirty (30) days
after the publication date of this notice. Comments may be submitted
either by email or by mail:
------------------------------------------------------------------------
To submit comments: Send them to:
------------------------------------------------------------------------
By email............................ [email protected].
By mail............................. Assistant Attorney General, U.S.
DOJ--ENRD, P.O. Box 7611,
Washington, D.C. 20044-7611.
------------------------------------------------------------------------
During the public comment period, the proposed consent decree may
be examined and downloaded at this Justice Department website: https://www.usdoj.gov/enrd/consent-decrees.html. We will also provide a paper
copy of the proposed consent decree upon written request and payment of
reproduction costs. Please mail your request and payment to: Consent
Decree Library, U.S. DOJ--ENRD, P.O. Box 7611, Washington, DC 20044-
7611.
Please enclose a check or money order for $84.50 (338 pages at 25
cents per page reproduction cost) payable to the United States
Treasury. For a paper copy without the Appendices and signature pages,
the cost is $20.75.
Randall M. Stone,
Acting Assistant Section Chief, Environmental Enforcement Section,
Environment and Natural Resources Division.
[FR Doc. 2018-05140 Filed 3-13-18; 8:45 am]
BILLING CODE 4410-15-P