Kenai Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 6544 [2018-03011]
Download as PDF
6544
Federal Register / Vol. 83, No. 31 / Wednesday, February 14, 2018 / Notices
Dated: February 8, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–03010 Filed 2–13–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13212–005]
daltland on DSKBBV9HB2PROD with NOTICES
Kenai Hydro, LLC; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Application
for Original License for Major Project—
Unconstructed.
b. Project No.: P–13212–005.
c. Date filed: April 18, 2016, and
amended on January 16, 2018.
d. Applicant: Kenia Hydro, LLC.
e. Name of Project: Grant Lake
Hydroelectric Project.
f. Location: On Grant Creek, near the
Town of Moose Pass, Kenai Peninsula
Borough, Alaska. The proposed project
would occupy 1,741.3 acres of federal
land within the Chugach National
Forest managed by the U.S. Forest
Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Mikel Salzetti,
Manager of Fuel Supply & Renewable
Energy Development, 280 Airport Way,
Kenai, AK 99611. (907) 283–2375.
i. FERC Contact: Kenneth Hogan,
(202) 502–8434; Kenneth.Hogan@
ferc.gov .
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
VerDate Sep<11>2014
22:07 Feb 13, 2018
Jkt 244001
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–13212–005.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The proposed Grant Lake
Hydroelectric Project would consists of:
(1) An intake structure within Grant
Lake; (2) a 3,300-foot-long water
conveyance; (3) a 72-inch-diameter, 150feet-long, welded steel penstock; (3) a
power house containing two 2.5
megawatt Francis turbine/generator
units; (4) a 95-foot-long open channel
tailrace; (5) a 3.6-acre tailrace detention
pond; (6) a 1.1-mile-long, 115-kilovolt
transmission line; and (7) appurtenant
facilities. The project is estimated to
generate an average of 18,600 megawatt
hours (MWh) annually
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title COMMENTS, REPLY
COMMENTS, RECOMMENDATIONS,
TERMS AND CONDITIONS, or
PRESCRIPTIONS; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
p. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate (project coordinator will
replace the days with actual months/
years according to the specific project).
Commission issues draft EIS, October
2018.
Comments on draft EIS, December
2018.
Commission issues final EIS, April
2019.
Dated: February 8, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–03011 Filed 2–13–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Conference Call
E:\FR\FM\14FEN1.SGM
14FEN1
Agencies
[Federal Register Volume 83, Number 31 (Wednesday, February 14, 2018)]
[Notices]
[Page 6544]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-03011]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13212-005]
Kenai Hydro, LLC; Notice of Application Ready for Environmental
Analysis and Soliciting Comments, Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Application for Original License for Major
Project--Unconstructed.
b. Project No.: P-13212-005.
c. Date filed: April 18, 2016, and amended on January 16, 2018.
d. Applicant: Kenia Hydro, LLC.
e. Name of Project: Grant Lake Hydroelectric Project.
f. Location: On Grant Creek, near the Town of Moose Pass, Kenai
Peninsula Borough, Alaska. The proposed project would occupy 1,741.3
acres of federal land within the Chugach National Forest managed by the
U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Mikel Salzetti, Manager of Fuel Supply &
Renewable Energy Development, 280 Airport Way, Kenai, AK 99611. (907)
283-2375.
i. FERC Contact: Kenneth Hogan, (202) 502-8434;
[email protected] .
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426. The first page of any filing should include
docket number P-13212-005.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. The proposed Grant Lake Hydroelectric Project would consists of:
(1) An intake structure within Grant Lake; (2) a 3,300-foot-long water
conveyance; (3) a 72-inch-diameter, 150-feet-long, welded steel
penstock; (3) a power house containing two 2.5 megawatt Francis
turbine/generator units; (4) a 95-foot-long open channel tailrace; (5)
a 3.6-acre tailrace detention pond; (6) a 1.1-mile-long, 115-kilovolt
transmission line; and (7) appurtenant facilities. The project is
estimated to generate an average of 18,600 megawatt hours (MWh)
annually
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or
PRESCRIPTIONS; (2) set forth in the heading the name of the applicant
and the project number of the application to which the filing responds;
(3) furnish the name, address, and telephone number of the person
submitting the filing; and (4) otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005. All comments, recommendations,
terms and conditions or prescriptions must set forth their evidentiary
basis and otherwise comply with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the application directly from the
applicant. Each filing must be accompanied by proof of service on all
persons listed on the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 4.34(b), and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
p. Procedural schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate (project coordinator will replace the days with actual
months/years according to the specific project).
Commission issues draft EIS, October 2018.
Comments on draft EIS, December 2018.
Commission issues final EIS, April 2019.
Dated: February 8, 2018.
Kimberly D. Bose,
Secretary.