Download as PDF Federal Register / Vol. 83, No. 31 / Wednesday, February 14, 2018 / Notices Dated: February 8, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–03022 Filed 2–13–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: daltland on DSKBBV9HB2PROD with NOTICES Filings Instituting Proceedings Docket Number: PR18–28–000. Applicants: Columbia Gas of Ohio, Inc. Description: Tariff filing per 284.123(b),(e): COH Rates effective 1–31–2018. Filed Date: 2/2/18. Accession Number: 201802025058. Comments/Protests Due: 5 p.m. ET 2/23/18. Docket Numbers: RP18–298–001. Applicants: Columbia Gas Transmission, LLC. Description: Compliance filing Adjusted CCRM 2018—Compliance to be effective 2/1/2018. Filed Date: 2/6/18. Accession Number: 20180206–5046. Comments Due: 5 p.m. ET 2/20/18. Docket Numbers: RP18–428–000. Applicants: Enstor Energy Services, LLC, Castleton Commodities International LLC. Description: Joint Petition of Enstor Energy Services, LLC, et al. for Temporary Waiver of Capacity Release Regulations and Policies and Request for Expedited Treatment. Filed Date: 2/6/18. Accession Number: 20180206–5129. Comments Due: 5 p.m. ET 2/13/18. Docket Numbers: RP18–429–000. Applicants: Rover Pipeline LLC. Description: § 4(d) Rate Filing: NonConforming Agreements—2 in compliance with CP15–93 Order to be effective 3/1/2018. Filed Date: 2/7/18. Accession Number: 20180207–5006. Comments Due: 5 p.m. ET 2/20/18. Docket Numbers: RP18–430–000. Applicants: Rover Pipeline LLC. Description: § 4(d) Rate Filing: NonConforming Agreement List—2 to be effective 3/1/2018. Filed Date: 2/7/18. Accession Number: 20180207–5005. Comments Due: 5 p.m. ET 2/20/18. Docket Numbers: RP18–431–000. VerDate Sep<11>2014 22:07 Feb 13, 2018 Jkt 244001 Applicants: Bear Creek Storage Company, L.L.C. Description: Compliance filing Annual Report on Operational Transactions 2018. Filed Date: 2/7/18. Accession Number: 20180207–5007. Comments Due: 5 p.m. ET 2/20/18. Docket Numbers: RP18–432–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Amended Negotiated Rate Agreement— Tenaska Mktg Ventures to be effective 2/7/2018. Filed Date: 2/7/18. Accession Number: 20180207–5008. Comments Due: 5 p.m. ET 2/20/18. Docket Numbers: RP18–433–000. Applicants: Transcontinental Gas Pipe Line Company. Description: § 4(d) Rate Filing: List of Non-Conforming Service Agreements (VSS II and Clean-Up) to be effective 8/1/2017. Filed Date: 2/7/18. Accession Number: 20180207–5146. Comments Due: 5 p.m. ET 2/20/18. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: February 8, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. BILLING CODE 6717–01–P [Docket No. NJ18–10–000] ISO New England Inc.; Notice of Filing Take notice that on January 30, 2018, ISO New England Inc. submitted its tariff filing: ISO–NE and VEC Service Sfmt 4703 [FR Doc. 2018–03009 Filed 2–13–18; 8:45 am] BILLING CODE 6717–01–P Federal Energy Regulatory Commission Gulf South Pipeline Company, LP; Notice of Application Federal Energy Regulatory Commission Fmt 4703 Dated: February 8, 2018. Kimberly D. Bose, Secretary. [Docket No. CP18–66–000] DEPARTMENT OF ENERGY Frm 00041 Agreement under Schedule 21–VEC of ISO–NE OATT to be effective 1/1/2018. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the eLibrary link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on February 20, 2018. DEPARTMENT OF ENERGY [FR Doc. 2018–03021 Filed 2–13–18; 8:45 am] PO 00000 6547 Take notice that on January 26, 2018, Gulf South Pipeline Company, LP (Gulf South), 9 Greenway Plaza, Suite 2800, Houston, Texas 77046, filed in Docket No. CP18–66–000 an application pursuant to section 7(b) of the Natural Gas Act (NGA) and Part 157 of the E:\FR\FM\14FEN1.SGM 14FEN1 daltland on DSKBBV9HB2PROD with NOTICES 6548 Federal Register / Vol. 83, No. 31 / Wednesday, February 14, 2018 / Notices Commission’s Regulations, requesting authorization to abandon by sale to Tristate NLA, LLC approximately 189.8 miles of various diameter gathering and transmission pipelines, associated meter and regulator stations, and appurtenant facilities located in Gregg, Harrison, and Panola Counties, Texas and Caddo, Bossier, and Webster Parishes, Louisiana, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to J. Kyle Stephens, Vice President, Regulatory Affairs, Gulf South Pipeline Company, LP, 9 Greenway Plaza, Suite 2800, Houston, Texas 77046; by telephone at (713) 479–8033; by fax at (713) 479– 1846; or by email at kyle.stephens@ bwpmlp.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) VerDate Sep<11>2014 22:07 Feb 13, 2018 Jkt 244001 and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit five copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit original and five copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on March 1, 2018. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 Dated: February 8, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–03006 Filed 2–13–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC18–23–000. Applicants: Dynegy Inc., Vistra Energy Corp. Description: Supplement to Joint Application of Dynegy Inc., et al. for Authorization for Merger of Jurisdictional Assets and Purchase of Securities (Delivered Price Test for MISO Region). Filed Date: 2/5/18. Accession Number: 20180205–5179. Comments Due: 5 p.m. ET 2/26/18. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER05–6–118. Applicants: Midwest Independent Transmission System Operator, Inc., PJM Interconnection, L.L.C. Description: Update to September 18, 2017 Refund Report of Midcontinent Independent System Operator, Inc. and PJM Interconnection, L.L.C. Filed Date: 2/2/18. Accession Number: 20180202–5222. Comments Due: 5 p.m. ET 2/23/18. Docket Numbers: ER18–816–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No. 4916; Queue No. AC2–070 to be effective 1/26/2018. Filed Date: 2/7/18. Accession Number: 20180207–5009. Comments Due: 5 p.m. ET 2/28/18. Docket Numbers: ER18–817–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No. 4918; Queue No. AC2–072 to be effective 1/30/2018. Filed Date: 2/7/18. Accession Number: 20180207–5040. Comments Due: 5 p.m. ET 2/28/18. Docket Numbers: ER18–818–000. Applicants: KCP&L Greater Missouri Operations Company. Description: § 205(d) Rate Filing: Rate Schedules 141 to be effective 4/8/2018. Filed Date: 2/7/18. Accession Number: 20180207–5050. E:\FR\FM\14FEN1.SGM 14FEN1

Agencies

[Federal Register Volume 83, Number 31 (Wednesday, February 14, 2018)]
[Notices]
[Pages 6547-6548]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-03006]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-66-000]


Gulf South Pipeline Company, LP; Notice of Application

    Take notice that on January 26, 2018, Gulf South Pipeline Company, 
LP (Gulf South), 9 Greenway Plaza, Suite 2800, Houston, Texas 77046, 
filed in Docket No. CP18-66-000 an application pursuant to section 7(b) 
of the Natural Gas Act (NGA) and Part 157 of the

[[Page 6548]]

Commission's Regulations, requesting authorization to abandon by sale 
to Tristate NLA, LLC approximately 189.8 miles of various diameter 
gathering and transmission pipelines, associated meter and regulator 
stations, and appurtenant facilities located in Gregg, Harrison, and 
Panola Counties, Texas and Caddo, Bossier, and Webster Parishes, 
Louisiana, all as more fully set forth in the application which is on 
file with the Commission and open to public inspection.
    The filing may also be viewed on the web at https://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Any questions concerning this application may be directed to J. 
Kyle Stephens, Vice President, Regulatory Affairs, Gulf South Pipeline 
Company, LP, 9 Greenway Plaza, Suite 2800, Houston, Texas 77046; by 
telephone at (713) 479-8033; by fax at (713) 479-1846; or by email at 
[email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit original and five copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on March 1, 2018.

    Dated: February 8, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-03006 Filed 2-13-18; 8:45 am]
 BILLING CODE 6717-01-P