Northern Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Planned Northern Lights 2019 Expansion Project and Request for Comments on Environmental Issues, 6016-6018 [2018-02774]
Download as PDF
6016
Federal Register / Vol. 83, No. 29 / Monday, February 12, 2018 / Notices
Docket No.
File date
5. P–2100–000 .............................................................................................................
1 Senators
[FR Doc. 2018–02775 Filed 2–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14672–001]
Lock +TM Hydro Friends Fund III;
Notice of Surrender of Preliminary
Permit
Take notice that Lock +TM Hydro
Friends Fund III, permittee for the
proposed Selden Lock and Dam
Hydroelectric Project, has requested that
its preliminary permit be terminated.
The permit was issued on June 3, 2016,
and would have expired on May 31,
2019.1 The project would have been
located on the Black Warrior River, in
Green and Hale Counties, Alabama.
The preliminary permit for Project
No. 14672 will remain in effect until the
close of business, March 8, 2018. If the
Commission is closed on this day, then
the permit remains in effect until the
close of business on the next day in
which the Commission is open.2 New
applications for this site may not be
submitted until after the permit
surrender is effective.
Dated: February 6, 2018.
Kimberly D. Bose,
Secretary.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2839–015]
daltland on DSKBBV9HB2PROD with NOTICES
Village of Lyndonville Electric
Department; Notice of Technical
Meeting
a. Date and Time of Meeting: February
21, 2018 at 9:00 a.m. Eastern Standard
Time.
b. Place: Telephone conference.
1 154
FERC 62,094 (2016).
CFR 385.2007(a)(2) (2017).
19:23 Feb 09, 2018
Jkt 244001
c. FERC Contact: Bill Connelly at
william.connelly@ferc.gov, or (202) 502–
8587.
d. Purpose of Meeting: Commission
Staff is hosting a technical meeting to
discuss the findings of the Village of
Lyndonville Electric Department’s
Archeological Resource Assessment and
Historic Properties Assessment filed on
August 25, 2017 and the concerns about
the Project Area of Potential Effect
(APE) expressed by the State of
Vermont, Division for Historic
Preservation, filed October 30, 2017.
e. A summary of the meeting will be
prepared and filed in the Commission’s
public file for the project.
f. All local, state, and federal agencies,
Indian tribes, and other interested
parties are invited to participate by
phone. Please call Bill Connelly at (202)
502–8587 by February 20, 2018, to
RSVP and to receive specific
instructions on how to participate.
Dated: February 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–02783 Filed 2–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF18–1–000]
Northern Natural Gas Company; Notice
of Intent To Prepare an Environmental
Assessment for the Planned Northern
Lights 2019 Expansion Project and
Request for Comments on
Environmental Issues
[FR Doc. 2018–02790 Filed 2–9–18; 8:45 am]
VerDate Sep<11>2014
2–1–2018
City of Live Oak, California.
Mayor Alesksandra M. Tica.
Orrin Hatch and Mike Lee. House Representatives Rob Bishop, Chris Stewart, Mia Love, and John Curtis.
Dated: February 6, 2018.
Kimberly D. Bose,
Secretary.
2 18
Presenter or requester
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Northern Lights 2019 Expansion
Project involving construction and
operation of facilities by Northern
Natural Gas Company (Northern) in
Olmsted, Freeborn, Mower, Morrison,
Carver, Hennepin, Wright, Le Sueur,
Rice, and Steele Counties, Minnesota.
The Commission will use this EA in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before March 8,
2018.
If you sent comments on this project
to the Commission before the opening of
this docket on October 10, 2017, you
will need to file those comments in
Docket No. PF18–1–000 to ensure they
are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC website (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
E:\FR\FM\12FEN1.SGM
12FEN1
Federal Register / Vol. 83, No. 29 / Monday, February 12, 2018 / Notices
daltland on DSKBBV9HB2PROD with NOTICES
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on eRegister. If you are filing a
comment on a particular project, please
select ‘‘Comment on a Filing’’ as the
filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (PF18–1–000)
with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Summary of the Planned Project
The Northern Lights 2019 Expansion
Project includes two components in
Minnesota— the Rochester Expansion
and the Northern Lights 2019
Expansion. For the Rochester Expansion
component, Northern plans to:
• Construct 12.3 miles of 16-inchdiameter pipeline, referred to as the
Rochester greenfield lateral;
• increase the maximum allowable
operating pressure (MAOP) of 8 miles of
the La Crosse branch line;
• relocate the La Crosse MAOP
control valve assembly; and
• construct the Rochester Town
Border Station.
For the Northern Lights 2019
Expansion component, Northern plans
to construct:
• 4.2 miles of 8-inch-diameter
pipeline extending the existing
Alexandria branch line;
• 3.1 miles of 24-inch-diameter
looping 1 of the existing Wilmar D
branch line;
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
VerDate Sep<11>2014
19:23 Feb 09, 2018
Jkt 244001
• 9.9 miles of 24-inch-diameter
pipeline, referred to as the Rockford to
Buffalo greenfield lateral;
• 1.6 miles of 16-inch-diameter
looping of the existing New Prague
branch line;
• a 15,900-horsepower Solar Mars
turbine compressor unit at the existing
Faribault Compressor Station;
• a 15,900-horsepower Solar Mars
turbine compressor unit and
appurtenant facilities at the existing
Owatonna Compressor Station; and
• a new 11,153-horsepower
compressor station near Carver,
Minnesota.
The Rochester Expansion component
of the project would provide 37,093
dekatherms per day of incremental
capacity to meet the future growth
needs in the area of Rochester,
Minnesota. The Northern Lights 2019
Expansion component would help
Northern meet the incremental natural
gas needs of Minnesota. According to
Northern, its project is designed to
optimize the placement of facilities to
meet customer needs.
The general location of the project
facilities is shown in appendix 1.2
Land Requirements for Construction
Construction of the planned facilities
would disturb about 627 acres of land
for the aboveground facilities and the
pipeline. Following construction,
Northern would maintain about 204
acres for permanent operation of the
project’s facilities; the remaining
acreage would be restored and revert to
former uses. About 38 percent of the
planned pipeline route parallels existing
pipeline, utility, or road rights-of-way.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 3 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
2 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called eLibrary or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
3 We, us, and our refer to the environmental staff
of the Commission’s Office of Energy Projects.
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
6017
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• socioeconomics;
• public safety; and
• cumulative impacts.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
the FERC receives an application. As
part of our pre-filing review, we have
begun to contact some federal and state
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues related to this
project to formally cooperate with us in
the preparation of the EA.4 Agencies
that would like to request cooperating
agency status should follow the
instructions for filing comments
4 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
E:\FR\FM\12FEN1.SGM
12FEN1
6018
Federal Register / Vol. 83, No. 29 / Monday, February 12, 2018 / Notices
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
Minnesota State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.5 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
daltland on DSKBBV9HB2PROD with NOTICES
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
planned facilities and the
environmental information provided by
Northern. This preliminary list of issues
may change based on your comments
and our analysis.
• Impact on landowners from noise
and dust during construction of the
pipelines.
• Compatibility of pipelines with
existing and future land uses, including
zoning restrictions on adjacent
properties.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
5 The Advisory Council on Historic Preservation
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
19:23 Feb 09, 2018
Jkt 244001
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
Once Northern files its application
with the Commission, you may want to
become an intervenor which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Motions to intervene are
more fully described at https://
www.ferc.gov/resources/guides/how-to/
intervene.asp. Instructions for becoming
an intervenor are in the Document-less
Intervention Guide under the e-filing
link on the Commission’s website.
Please note that the Commission will
not accept requests for intervenor status
at this time. You must wait until the
Commission receives a formal
application for the project.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on General Search and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF18–1). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
PO 00000
Frm 00044
Fmt 4703
Sfmt 4703
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public sessions or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: February 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–02774 Filed 2–9–18; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OW–2003–0033; FRL–9974–08–
OEI]
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request;
Modification of Secondary Treatment
Requirements for Discharges Into
Marine Waters
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency (EPA) has submitted an
information collection request (ICR),
‘‘Modification of Secondary Treatment
Requirements for Discharges into
Marine Waters’’ (EPA ICR No. 0138.11,
OMB Control No. 2040–0088) to the
Office of Management and Budget
(OMB) for review and approval in
accordance with the Paperwork
Reduction Act. Public comments were
previously requested via the Federal
Register on June 29, 2017, during a 60day comment period. This notice allows
for an additional 30 days for public
comments. A fuller description of the
ICR is given below, including its
estimated burden and cost to the public.
An agency may not conduct or sponsor
and a person is not required to respond
to a collection of information unless it
displays a currently valid OMB control
number.
DATES: Additional comments may be
submitted on or before March 14, 2018.
ADDRESSES: Submit your comments,
referencing Docket ID Number EPA–
HQ–OW–2003–0033, to (1) EPA online
using www.regulations.gov (our
preferred method), by email to OWDocket@epa.gov, or by mail to: EPA
Docket Center, Environmental
SUMMARY:
E:\FR\FM\12FEN1.SGM
12FEN1
Agencies
[Federal Register Volume 83, Number 29 (Monday, February 12, 2018)]
[Notices]
[Pages 6016-6018]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-02774]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF18-1-000]
Northern Natural Gas Company; Notice of Intent To Prepare an
Environmental Assessment for the Planned Northern Lights 2019 Expansion
Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Northern Lights 2019 Expansion
Project involving construction and operation of facilities by Northern
Natural Gas Company (Northern) in Olmsted, Freeborn, Mower, Morrison,
Carver, Hennepin, Wright, Le Sueur, Rice, and Steele Counties,
Minnesota. The Commission will use this EA in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before March 8, 2018.
If you sent comments on this project to the Commission before the
opening of this docket on October 10, 2017, you will need to file those
comments in Docket No. PF18-1-000 to ensure they are considered as part
of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC website (www.ferc.gov). This fact sheet addresses a
number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
[[Page 6017]]
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or [email protected]. Please carefully follow
these instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's website (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
eRegister. If you are filing a comment on a particular project, please
select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(PF18-1-000) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426.
Summary of the Planned Project
The Northern Lights 2019 Expansion Project includes two components
in Minnesota-- the Rochester Expansion and the Northern Lights 2019
Expansion. For the Rochester Expansion component, Northern plans to:
Construct 12.3 miles of 16-inch-diameter pipeline,
referred to as the Rochester greenfield lateral;
increase the maximum allowable operating pressure (MAOP)
of 8 miles of the La Crosse branch line;
relocate the La Crosse MAOP control valve assembly; and
construct the Rochester Town Border Station.
For the Northern Lights 2019 Expansion component, Northern plans to
construct:
4.2 miles of 8-inch-diameter pipeline extending the
existing Alexandria branch line;
3.1 miles of 24-inch-diameter looping \1\ of the existing
Wilmar D branch line;
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
9.9 miles of 24-inch-diameter pipeline, referred to as the
Rockford to Buffalo greenfield lateral;
1.6 miles of 16-inch-diameter looping of the existing New
Prague branch line;
a 15,900-horsepower Solar Mars turbine compressor unit at
the existing Faribault Compressor Station;
a 15,900-horsepower Solar Mars turbine compressor unit and
appurtenant facilities at the existing Owatonna Compressor Station; and
a new 11,153-horsepower compressor station near Carver,
Minnesota.
The Rochester Expansion component of the project would provide
37,093 dekatherms per day of incremental capacity to meet the future
growth needs in the area of Rochester, Minnesota. The Northern Lights
2019 Expansion component would help Northern meet the incremental
natural gas needs of Minnesota. According to Northern, its project is
designed to optimize the placement of facilities to meet customer
needs.
The general location of the project facilities is shown in appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called eLibrary or from the Commission's
Public Reference Room, 888 First Street NE, Washington, DC 20426, or
call (202) 502-8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 627
acres of land for the aboveground facilities and the pipeline.
Following construction, Northern would maintain about 204 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored and revert to former uses. About 38 percent of the
planned pipeline route parallels existing pipeline, utility, or road
rights-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\3\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\3\ We, us, and our refer to the environmental staff of the
Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
socioeconomics;
public safety; and
cumulative impacts.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review, we
have begun to contact some federal and state agencies to discuss their
involvement in the scoping process and the preparation of the EA.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before we make our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this project to formally cooperate with us in the
preparation of the EA.\4\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments
[[Page 6018]]
provided under the Public Participation section of this notice.
---------------------------------------------------------------------------
\4\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the Minnesota State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\5\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Northern. This preliminary
list of issues may change based on your comments and our analysis.
Impact on landowners from noise and dust during
construction of the pipelines.
Compatibility of pipelines with existing and future land
uses, including zoning restrictions on adjacent properties.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
Once Northern files its application with the Commission, you may
want to become an intervenor which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Motions to intervene are more fully described at
https://www.ferc.gov/resources/guides/how-to/intervene.asp. Instructions
for becoming an intervenor are in the Document-less Intervention Guide
under the e-filing link on the Commission's website. Please note that
the Commission will not accept requests for intervenor status at this
time. You must wait until the Commission receives a formal application
for the project.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on General Search and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF18-
1). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public sessions or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: February 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-02774 Filed 2-9-18; 8:45 am]
BILLING CODE 6717-01-P