Black Bear Hydro Partners, LLC.; Notice of Authorization for Continued Project Operation, 4044 [2018-01588]
Download as PDF
sradovich on DSK3GMQ082PROD with NOTICES
4044
Federal Register / Vol. 83, No. 19 / Monday, January 29, 2018 / Notices
Filed Date: 1/19/18.
Accession Number: 20180119–5029.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–680–000.
Applicants: PJM Interconnection,
L.L.C.
Description: Compliance filing:
Revisions to OATT Sch. 12-Appx and
Appx A re: Linden/HTP’s cost
responsibility to be effective 1/1/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5069.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–681–000.
Applicants: NorthWestern
Corporation.
Description: Tariff Cancellation:
Notice of Cancellation: SA 793, Utilities
Agreement with MDT (West Laurel) to
be effective 1/20/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5071.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–682–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing: 3
Phases Renewables (OR D.A.) to be
effective 1/1/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5079.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–683–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: GIA
and Distrib Serv Agmt, Difwind Farms
Limited V Project SA 991 992
WDT1130QFC to be effective 1/17/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5097.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–684–000.
Applicants: Nevada Power Company.
Description: Initial rate filing: Rate
Schedule No. 158 NPC/Desertlink O &
M Agree to be effective 3/21/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5135.
Comments Due: 5 p.m. ET 2/9/18.
Docket Numbers: ER18–685–000.
Applicants: Nevada Power Company.
Description: Initial rate filing: Rate
Schedule No. 159 NPC/Desertlink
License & Sale Agr to be effective
3/21/2018.
Filed Date: 1/19/18.
Accession Number: 20180119–5144.
Comments Due: 5 p.m. ET 2/9/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
VerDate Sep<11>2014
18:19 Jan 26, 2018
Jkt 244001
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: January 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–01586 Filed 1–26–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2727–000]
Black Bear Hydro Partners, LLC.;
Notice of Authorization for Continued
Project Operation
On December 30, 2015, Black Bear
Hydro Partners, LLC., licensee for the
Ellsworth Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Ellsworth Hydroelectric Project
facility is located on the Union River in
Hancock County, Maine.
The license for Project No. 2727 was
issued for a period ending December 31,
2017. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2727
is issued to the licensee for a period
effective January 1, 2018 through
December 31, 2018 or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before December 31, 2018,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Black Bear Hydro
Partners, LLC., is authorized to continue
operation of the Ellsworth Hydroelectric
Project, until such time as the
Commission acts on its application for
a subsequent license.
Dated: January 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–01588 Filed 1–26–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3342–022]
Briar Hydro Associates; Notice of
Application Accepted for Filing,
Soliciting Comments, Protests and
Motions To Intervene
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Proceeding: Extension of
License Term.
b. Project No.: P–3342–022.
c. Date Filed: January 9, 2018.
d. Licensee: Briar Hydro Associates.
e. Names and Locations of Project:
Penacook Lower Falls Hydroelectric
Project No. 3342, located on the
Contoocook River, in Merrimack
County, New Hampshire.
f. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
g. Licensee Contact Information:
Andrew J. Locke, Briar Hydro
Associates, c/o Essex Hydro Associates,
LLC, 55 Union Street, Boston, MA
02108; Telephone: (617) 367–0032;
Email: alocke@essexhydro.com.
E:\FR\FM\29JAN1.SGM
29JAN1
Agencies
[Federal Register Volume 83, Number 19 (Monday, January 29, 2018)]
[Notices]
[Page 4044]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-01588]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2727-000]
Black Bear Hydro Partners, LLC.; Notice of Authorization for
Continued Project Operation
On December 30, 2015, Black Bear Hydro Partners, LLC., licensee for
the Ellsworth Hydroelectric Project, filed an Application for a New
License pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Ellsworth Hydroelectric Project facility is
located on the Union River in Hancock County, Maine.
The license for Project No. 2727 was issued for a period ending
December 31, 2017. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2727 is issued to
the licensee for a period effective January 1, 2018 through December
31, 2018 or until the issuance of a new license for the project or
other disposition under the FPA, whichever comes first. If issuance of
a new license (or other disposition) does not take place on or before
December 31, 2018, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, Black Bear Hydro Partners, LLC., is
authorized to continue operation of the Ellsworth Hydroelectric
Project, until such time as the Commission acts on its application for
a subsequent license.
Dated: January 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-01588 Filed 1-26-18; 8:45 am]