Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 2973 [2018-01018]

Download as PDF Federal Register / Vol. 83, No. 14 / Monday, January 22, 2018 / Notices Docket No. ER18–332, Southwest Power Pool, Inc. Docket No. ER18–352, Southwest Power Pool, Inc. Docket No. ER18–364, Southwest Power Pool, Inc. Docket No. ER18–374, Southwest Power Pool, Inc. Docket No. ER18–381, Southwest Power Pool, Inc. Docket No. ER18–401, Southwestern Public Service Company Docket No. ER18–421, Southwest Power Pool, Inc. Docket No. ER18–478, Southwest Power Pool, Inc. Docket No. ER18–495, Southwestern Public Service Co. Docket No. ER18–499, Southwestern Electric Power Company Docket No. ER18–500, Southwestern Electric Power Company Docket No. ER18–590, Southwest Power Pool, Inc. Docket No. ER18–421, Southwest Power Pool, Inc. Docket No. ER18–594, Southwest Power Pool, Inc. Docket No. ER18–592, Southwest Power Pool, Inc. Docket No. ER18–599, Southwest Power Pool, Inc. Docket No. EL18–9–000, Xcel Energy Services, Inc. v. Southwest Power Pool, Inc. Docket No. EL18–20–000, Indicated SPP Transmission Owners v. Southwest Power Pool, Inc. Docket No. EL18–26, EDF Renewable Energy, Inc. v. Midcontinent Independent System Operator, Inc., Southwest Power Pool, Inc., and PJM Interconnection, L.L.C. Docket No. EL18–35, Southwest Power Pool, Inc. ethrower on DSK3G9T082PROD with NOTICES These meetings are open to the public. For more information, contact Patrick Clarey, Office of Energy Market Regulation, Federal Energy Regulatory Commission at (317) 249–5937 or patrick.clarey@ferc.gov. Dated: January 12, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–01012 Filed 1–19–18; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 19:00 Jan 19, 2018 Jkt 244001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14866–000] Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On December 22, 2017, Merchant Hydro Developers, LLC, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Preckle Pumped Storage Hydro Project to be located near Duryea Borough in Luzerne County, Pennsylvania and Ransom Township in Lackawanna County, Pennsylvania. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) A new upper reservoir with a surface area of 300 acres and a storage capacity of 4,500 acre-feet at a surface elevation of approximately 1,356 feet above mean sea level (msl) created through construction of a new rollercompacted concrete or rock-fill dam; (2) a new lower reservoir with a surface area of 200 acres and a storage capacity of 3,480 acre-feet at a surface elevation of 550 feet msl; (3) two new 5,640-footlong, 16-foot-diameter penstocks connecting the upper and lower reservoirs; (4) a new 150-foot-long, 250foot-wide, 50-foot-high powerhouse containing two turbine-generator units with a total rated capacity of 450 megawatts; (5) a new 13,200-foot-long transmission line connecting the powerhouse to the 230/69-kilovolt Stanton substation owned by PPL Electric Utilities; and (6) appurtenant facilities. The proposed project would have an annual generation of 27,594 megawatt-hours. Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC, 5710 Oak Crest Drive, Doylestown, PA 18902; phone: 267–254–6107. FERC Contact: Woohee Choi; phone: (202) 502–6336. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 2973 intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–14866–000. More information about this project, including a copy of the application, can be viewed or printed on the eLibrary link of the Commission’s website at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14866) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: January 12, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–01018 Filed 1–19–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER18–634–000] Access Energy Solutions, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Access Energy Solutions, LLC‘s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and E:\FR\FM\22JAN1.SGM 22JAN1

Agencies

[Federal Register Volume 83, Number 14 (Monday, January 22, 2018)]
[Notices]
[Page 2973]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-01018]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14866-000]


Merchant Hydro Developers, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On December 22, 2017, Merchant Hydro Developers, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the 
Preckle Pumped Storage Hydro Project to be located near Duryea Borough 
in Luzerne County, Pennsylvania and Ransom Township in Lackawanna 
County, Pennsylvania. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would consist of the following: (1) A new 
upper reservoir with a surface area of 300 acres and a storage capacity 
of 4,500 acre-feet at a surface elevation of approximately 1,356 feet 
above mean sea level (msl) created through construction of a new 
roller-compacted concrete or rock-fill dam; (2) a new lower reservoir 
with a surface area of 200 acres and a storage capacity of 3,480 acre-
feet at a surface elevation of 550 feet msl; (3) two new 5,640-foot-
long, 16-foot-diameter penstocks connecting the upper and lower 
reservoirs; (4) a new 150-foot-long, 250-foot-wide, 50-foot-high 
powerhouse containing two turbine-generator units with a total rated 
capacity of 450 megawatts; (5) a new 13,200-foot-long transmission line 
connecting the powerhouse to the 230/69-kilovolt Stanton substation 
owned by PPL Electric Utilities; and (6) appurtenant facilities. The 
proposed project would have an annual generation of 27,594 megawatt-
hours.
    Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC, 
5710 Oak Crest Drive, Doylestown, PA 18902; phone: 267-254-6107.
    FERC Contact: Woohee Choi; phone: (202) 502-6336.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14866-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the eLibrary link of the 
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14866) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: January 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-01018 Filed 1-19-18; 8:45 am]
 BILLING CODE 6717-01-P