Lock 13 Hydro Partners, LLC; Notice Soliciting Scoping Comments, 2635-2636 [2018-00754]

Download as PDF Federal Register / Vol. 83, No. 12 / Thursday, January 18, 2018 / Notices 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 9, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–00749 Filed 1–17–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2531–000] sradovich on DSK3GMQ082PROD with NOTICES Brookfield White Pine, LLC; Notice of Authorization for Continued Project Operation On August 10, 2012, Brookfield White Pine LLC, licensee for the West Buxton Hydroelectric Project, filed an Application for a New License pursuant to the Federal Power Act (FPA) and the Commission’s regulations thereunder. The West Buxton Hydroelectric Project facility is located on the Saco River in the towns of Buxton, Hollis, and Standish, within York and Cumberland Counties, Maine. The license for Project No. 2531 was issued for a period ending December 31, 2017. Section 15(a) (1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be VerDate Sep<11>2014 18:27 Jan 17, 2018 Jkt 244001 required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 2531 is issued to the licensee for a period effective January 1, 2018 through December 31, 2018 or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before December 31, 2018, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that the licensee, Brookfield White Pine, LLC is authorized to continue operation of the West Buxton Hydroelectric Project, until such time as the Commission acts on its application for a subsequent license. Dated: January 11, 2018. Kimberly D. Bose, Secretary. 2635 Docket Numbers: RP18–338–000. Applicants: Guardian Pipeline, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate PAL Agreement— MIECO INC to be effective 1/10/2018. Filed Date: 1/9/18. Accession Number: 20180109–5146. Comments Due: 5 p.m. ET 1/22/18. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: January 10, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–00743 Filed 1–17–18; 8:45 am] [FR Doc. 2018–00750 Filed 1–17–18; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Project No. 14799–001] Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP18–272–001. Applicants: Ryckman Creek Resources, LLC. Description: Tariff Amendment: Amended Non Conforming Service Agreement Filing to be effective 12/28/ 2017. Filed Date: 1/9/18. Accession Number: 20180109–5145. Comments Due: 5 p.m. ET 1/22/18. Docket Numbers: RP18–337–000. Applicants: Gulf Crossing Pipeline Company LLC. Description: § 4(d) Rate Filing: Neg Rate Agmt Filing (BP 1936) to be effective 1/9/2018. Filed Date: 1/9/18. Accession Number: 20180109–5022. Comments Due: 5 p.m. ET 1/22/18. PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 Lock 13 Hydro Partners, LLC; Notice Soliciting Scoping Comments a. Type Filing: Notice of Intent to File License Application and PreApplication Document for an Original Major License. b. Project No.: P–14799–001. c. Date Filed: September 7, 2017. d. Applicant: Lock 13 Hydro Partners, LLC. e. Name of Project: Evelyn Hydroelectric Project. f. Location: On the Kentucky River, in Lee and Estill Counties, Kentucky. The project would be located at the Commonwealth of Kentucky’s existing Lock and Dam No. 13. No federal land would be occupied by the project works or located within the project boundary. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: David Brown Kinloch, Lock 13 Hydro Partners, LLC, 414 S. Wenzel Street, Louisville, KY E:\FR\FM\18JAN1.SGM 18JAN1 sradovich on DSK3GMQ082PROD with NOTICES 2636 Federal Register / Vol. 83, No. 12 / Thursday, January 18, 2018 / Notices 40204; (502) 589–0975; email— kyhydropower@gmail.com. i. FERC Contact: Sarah Salazar, (202) 502–6863 or sarah.salazar@ferc.gov. j. Cooperating Agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See 94 FERC 61,076 (2001). k. Deadline for Filing Scoping Comments: February 8, 2018. l. With this notice, we are soliciting comments on Commission staff’s Scoping Document 1 (SD1). All comments on the SD1 should be sent to the address above in paragraph h. In addition, all comments on SD1, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application must be filed with the Commission. Documents may be filed electronically via the internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s website https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. In lieu of electronic filing, please send a paper copy to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. All filings with the Commission must include on the first page, the project name (Evelyn Hydroelectric Project and number (P–14799–001), and bear the appropriate heading: Comments on Scoping Document 1, Request for Cooperating Agency Status, or Communications to and from Commission Staff. Any individual or entity interested in commenting on the SD1 must do so by February 8, 2018. m. A copy of the Pre-Application Document is available for review at the Commission in the Public Reference Room, or may be viewed on the Commission’s website (https:// www.ferc.gov) using the eLibrary link. Enter the docket number, excluding the last three digits in the docket number field, to access the document. For VerDate Sep<11>2014 18:27 Jan 17, 2018 Jkt 244001 assistance, contact FERC Online Support at FERCONlineSupport@ ferc.gov, or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in paragraph h. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Scoping Process: The Commission staff intends to prepare a single Environmental Assessment (EA) for the Evelyn Hydroelectric Project in accordance with the National Environmental Policy Act. The EA will consider both site-specific and cumulative environmental impacts and reasonable alternatives to the proposed action. Commission staff does not propose to conduct any on-site scoping meetings at this time. Instead, we are soliciting comments, recommendations, and information, on the SD1 issued on January 9, 2018. Copies of the SD1 outlining the subject areas to be addressed in the EA were distributed to the parties on the Commission’s mailing list and the applicant’s distribution list. Copies of the SD1 may be viewed on the web at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call 1–866–208–3676 or for TTY, (202) 502–8659. Dated: January 9, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–00754 Filed 1–17–18; 8:45 am] BILLING CODE 6717–01–P FEDERAL COMMUNICATIONS COMMISSION [OMB 3060–0441] Information Collection Being Reviewed by the Federal Communications Commission Under Delegated Authority Federal Communications Commission. ACTION: Notice and request for comments. AGENCY: As part of its continuing effort to reduce paperwork burdens, and as required by the Paperwork Reduction Act of 1995 (PRA), the Federal Communications Commission (FCC or SUMMARY: PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 Commission) invites the general public and other Federal agencies to take this opportunity to comment on the following information collections. Comments are requested concerning: Whether the proposed collection of information is necessary for the proper performance of the functions of the Commission, including whether the information shall have practical utility; the accuracy of the Commission’s burden estimate; ways to enhance the quality, utility, and clarity of the information collected; ways to minimize the burden of the collection of information on the respondents, including the use of automated collection techniques or other forms of information technology; and ways to further reduce the information collection burden on small business concerns with fewer than 25 employees. The FCC may not conduct or sponsor a collection of information unless it displays a currently valid Office of Management and Budget (OMB) control number. No person shall be subject to any penalty for failing to comply with a collection of information subject to the PRA that does not display a valid OMB control number. DATES: Written PRA comments should be submitted on or before March 19, 2018. If you anticipate that you will be submitting comments, but find it difficult to do so within the period of time allowed by this notice, you should advise the contact listed below as soon as possible. ADDRESSES: Direct all PRA comments to Cathy Williams, FCC, via email PRA@ fcc.gov and to Cathy.Williams@fcc.gov. FOR FURTHER INFORMATION CONTACT: For additional information about the information collection, contact Cathy Williams at (202) 418–2918. SUPPLEMENTARY INFORMATION: OMB Control Number: 3060–0441. Title: Section 90.621, Selection and Assignment of Frequencies and Section 90.693, Grandfathering Provisions for Incumbent Licensees. Form Number: N/A. Type of Review: Extension of a currently approved collection. Respondents: Business or other forprofit entities; Not-for-profit institutions; and State, Local, or Tribal Government. Number of Respondents: 50 respondents; 50 responses. Estimated Time per Response: 1.5 hours. Frequency of Response: On occasion reporting requirement. Obligation to Respond: Required to obtain or retain benefits. Statutory authority for this information collection E:\FR\FM\18JAN1.SGM 18JAN1

Agencies

[Federal Register Volume 83, Number 12 (Thursday, January 18, 2018)]
[Notices]
[Pages 2635-2636]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-00754]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14799-001]


Lock 13 Hydro Partners, LLC; Notice Soliciting Scoping Comments

    a. Type Filing: Notice of Intent to File License Application and 
Pre-Application Document for an Original Major License.
    b. Project No.: P-14799-001.
    c. Date Filed: September 7, 2017.
    d. Applicant: Lock 13 Hydro Partners, LLC.
    e. Name of Project: Evelyn Hydroelectric Project.
    f. Location: On the Kentucky River, in Lee and Estill Counties, 
Kentucky. The project would be located at the Commonwealth of 
Kentucky's existing Lock and Dam No. 13. No federal land would be 
occupied by the project works or located within the project boundary.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: David Brown Kinloch, Lock 13 Hydro Partners, 
LLC, 414 S. Wenzel Street, Louisville, KY

[[Page 2636]]

40204; (502) 589-0975; [email protected]
    i. FERC Contact: Sarah Salazar, (202) 502-6863 or 
[email protected].
    j. Cooperating Agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC 61,076 
(2001).
    k. Deadline for Filing Scoping Comments: February 8, 2018.
    l. With this notice, we are soliciting comments on Commission 
staff's Scoping Document 1 (SD1). All comments on the SD1 should be 
sent to the address above in paragraph h. In addition, all comments on 
SD1, requests for cooperating agency status, and all communications to 
and from Commission staff related to the merits of the potential 
application must be filed with the Commission. Documents may be filed 
electronically via the internet. See 18 CFR 385.2001(a)(1)(iii) and the 
instructions on the Commission's website https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support. In lieu of electronic 
filing, please send a paper copy to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    All filings with the Commission must include on the first page, the 
project name (Evelyn Hydroelectric Project and number (P-14799-001), 
and bear the appropriate heading: Comments on Scoping Document 1, 
Request for Cooperating Agency Status, or Communications to and from 
Commission Staff. Any individual or entity interested in commenting on 
the SD1 must do so by February 8, 2018.
    m. A copy of the Pre-Application Document is available for review 
at the Commission in the Public Reference Room, or may be viewed on the 
Commission's website (https://www.ferc.gov) using the eLibrary link. 
Enter the docket number, excluding the last three digits in the docket 
number field, to access the document. For assistance, contact FERC 
Online Support at [email protected], or toll free at 1-866-
208-3676, or for TTY, (202) 502-8659. A copy is also available for 
inspection and reproduction at the address in paragraph h.
    Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Scoping Process: The Commission staff intends to prepare a 
single Environmental Assessment (EA) for the Evelyn Hydroelectric 
Project in accordance with the National Environmental Policy Act. The 
EA will consider both site-specific and cumulative environmental 
impacts and reasonable alternatives to the proposed action.
    Commission staff does not propose to conduct any on-site scoping 
meetings at this time. Instead, we are soliciting comments, 
recommendations, and information, on the SD1 issued on January 9, 2018.
    Copies of the SD1 outlining the subject areas to be addressed in 
the EA were distributed to the parties on the Commission's mailing list 
and the applicant's distribution list. Copies of the SD1 may be viewed 
on the web at https://www.ferc.gov using the eLibrary link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, call 1-866-208-3676 or 
for TTY, (202) 502-8659.

    Dated: January 9, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-00754 Filed 1-17-18; 8:45 am]
 BILLING CODE 6717-01-P