Steel Reef Pipelines US LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Saskatchewan Pipeline Project and Request for Comments on Environmental Issues, 2628-2629 [2018-00745]
Download as PDF
2628
Federal Register / Vol. 83, No. 12 / Thursday, January 18, 2018 / Notices
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the projects are not subject to
section 15 of the FPA, notice is hereby
given that the licensee, Algonquin
Power (Beaver Falls), LLC, is authorized
to continue operation of the Upper
Beaver Falls and Lower Beaver Falls
Hydroelectric Projects, until such time
as the Commission acts on its license
application.
Dated: January 11, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–00751 Filed 1–17–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–24–000]
sradovich on DSK3GMQ082PROD with NOTICES
Steel Reef Pipelines US LLC; Notice of
Intent To Prepare an Environmental
Assessment for the Proposed
Saskatchewan Pipeline Project and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the South Saskatchewan Pipeline
Project involving construction and
operation of facilities by Steel Reef
Pipelines US LLC (Steel Reef) in Burke
County, North Dakota. The Commission
will use this EA in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
You can make a difference by providing
us with your specific comments or
concerns about the project. Your
comments should focus on the potential
environmental effects, reasonable
alternatives, and measures to avoid or
lessen environmental impacts. Your
input will help the Commission staff
determine what issues they need to
evaluate in the EA. To ensure that your
comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before February
10, 2018.
VerDate Sep<11>2014
18:27 Jan 17, 2018
Jkt 244001
If you sent comments on this project
to the Commission before the opening of
this docket on December 8, 2017, you
will need to file those comments in
Docket No. CP18–24–000 to ensure they
are considered as part of this
proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
Steel Reef provided landowners with
a fact sheet prepared by the FERC
entitled An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know? This fact sheet addresses a
number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings. It is also
available for viewing on the FERC
website (www.ferc.gov).
Public Participation
For your convenience, there are three
methods you can use to submit your
comments to the Commission. The
Commission encourages electronic filing
of comments and has expert staff
available to assist you at (202) 502–8258
or FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for submitting brief, text-only
comments on a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on eRegister. If you are filing a
comment on a particular project, please
select Comment on a Filing as the filing
type; or
(3) You can file a paper copy of your
comments by mailing them to the
following address. Be sure to reference
the project docket number (C18–24–000)
with your submission: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Steel Reef’s proposed Saskatchewan
Pipeline Project, referred to as the
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
Border Crossing Facilities in its
application, includes a 250-foot-long
10.75-inch-outside-diameter pipeline
along with aboveground facilities
including a metering facility, a remote
telemetry unit, and a pig trap launcher.
The facilities are part of the southern
end of Steel Reef’s planned 2.2-milelong 10.75-inch-outside-diameter South
Saskatchewan Access Pipeline (SSA
Pipeline) it plans to build connecting
gathering facilities owned by Petro
Harvester Oil & Gas, LLC near Portal,
North Dakota to an interconnection with
an existing natural gas processing plant
owned by Steel Reef Infrastructure
Corporation near North Portal in
Saskatchewan, Canada. Steel Reef states
that the Saskatchewan Pipeline Project’s
facilities would, as part of the SSA
Pipeline, permit the transport of up to
30 million standard cubic feet per day
of sour natural gas gathered from
existing oil wells owned and operated
by Petro Harvester Oil & Gas, LLC (Petro
Harvester) within the Burke County
region of North Dakota.
Steel Reef requests certification by
July 2, 2018, and expects to perform its
construction activities in a 30-day
period.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Steel Reef would limit its
construction activities to 0.75 acres of
agricultural land, comprised of 0.35
acres of new permanent pipeline rightof-way and 0.40 acres of temporary
workspace. The new permanent
pipeline right-of-way width would be 65
feet. Steel Reef would restore the
temporary right-of-way to preabandonment conditions. An 0.14 acre
portion of the permanent right-of-way
would overlap the Petro Harvester lease
where Steel Reef would have a shared
land use agreement. None of the route
would be co-located with other existing
utilities, roads or other infrastructure.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371. For instructions on connecting to eLibrary,
refer to the last page of this notice.
E:\FR\FM\18JAN1.SGM
18JAN1
Federal Register / Vol. 83, No. 12 / Thursday, January 18, 2018 / Notices
Necessity. NEPA also requires us 2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
sradovich on DSK3GMQ082PROD with NOTICES
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
• public safety; and
• cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section,
beginning on page 2.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
2 We,
us, and our refer to the environmental staff
of the Commission’s Office of Energy Projects.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
VerDate Sep<11>2014
18:27 Jan 17, 2018
Jkt 244001
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with the
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies of the EA will be sent to the
environmental mailing list for public
review and comment. If you would
prefer to receive a paper copy of the
document instead of the CD version or
would like to remove your name from
the mailing list, please return the
attached Information Request (appendix
2).
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
PO 00000
Frm 00015
Fmt 4703
Sfmt 9990
2629
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an intervenor which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the Document-less
Intervention Guide under the e-filing
link on the Commission’s website.
Motions to intervene are more fully
described at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP18–24–000). Be sure you
have selected an appropriate date range.
For assistance, please contact FERC
Online Support at FercOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
for TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Finally, public sessions or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Dated: January 11, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–00745 Filed 1–17–18; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\18JAN1.SGM
18JAN1
Agencies
[Federal Register Volume 83, Number 12 (Thursday, January 18, 2018)]
[Notices]
[Pages 2628-2629]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-00745]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-24-000]
Steel Reef Pipelines US LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Saskatchewan Pipeline Project
and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the South Saskatchewan Pipeline
Project involving construction and operation of facilities by Steel
Reef Pipelines US LLC (Steel Reef) in Burke County, North Dakota. The
Commission will use this EA in its decision-making process to determine
whether the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. You can make a difference by providing us with
your specific comments or concerns about the project. Your comments
should focus on the potential environmental effects, reasonable
alternatives, and measures to avoid or lessen environmental impacts.
Your input will help the Commission staff determine what issues they
need to evaluate in the EA. To ensure that your comments are timely and
properly recorded, please send your comments so that the Commission
receives them in Washington, DC on or before February 10, 2018.
If you sent comments on this project to the Commission before the
opening of this docket on December 8, 2017, you will need to file those
comments in Docket No. CP18-24-000 to ensure they are considered as
part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
Steel Reef provided landowners with a fact sheet prepared by the
FERC entitled An Interstate Natural Gas Facility On My Land? What Do I
Need To Know? This fact sheet addresses a number of typically asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC website (www.ferc.gov).
Public Participation
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has expert staff available to assist you at
(202) 502-8258 or [email protected]. Please carefully follow
these instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's website (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
eRegister. If you are filing a comment on a particular project, please
select Comment on a Filing as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address. Be sure to reference the project docket number
(C18-24-000) with your submission: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington,
DC 20426.
Summary of the Proposed Project
Steel Reef's proposed Saskatchewan Pipeline Project, referred to as
the Border Crossing Facilities in its application, includes a 250-foot-
long 10.75-inch-outside-diameter pipeline along with aboveground
facilities including a metering facility, a remote telemetry unit, and
a pig trap launcher. The facilities are part of the southern end of
Steel Reef's planned 2.2-mile-long 10.75-inch-outside-diameter South
Saskatchewan Access Pipeline (SSA Pipeline) it plans to build
connecting gathering facilities owned by Petro Harvester Oil & Gas, LLC
near Portal, North Dakota to an interconnection with an existing
natural gas processing plant owned by Steel Reef Infrastructure
Corporation near North Portal in Saskatchewan, Canada. Steel Reef
states that the Saskatchewan Pipeline Project's facilities would, as
part of the SSA Pipeline, permit the transport of up to 30 million
standard cubic feet per day of sour natural gas gathered from existing
oil wells owned and operated by Petro Harvester Oil & Gas, LLC (Petro
Harvester) within the Burke County region of North Dakota.
Steel Reef requests certification by July 2, 2018, and expects to
perform its construction activities in a 30-day period.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE, Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Steel Reef would limit its construction activities to 0.75 acres of
agricultural land, comprised of 0.35 acres of new permanent pipeline
right-of-way and 0.40 acres of temporary workspace. The new permanent
pipeline right-of-way width would be 65 feet. Steel Reef would restore
the temporary right-of-way to pre-abandonment conditions. An 0.14 acre
portion of the permanent right-of-way would overlap the Petro Harvester
lease where Steel Reef would have a shared land use agreement. None of
the route would be co-located with other existing utilities, roads or
other infrastructure.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and
[[Page 2629]]
Necessity. NEPA also requires us \2\ to discover and address concerns
the public may have about proposals. This process is referred to as
``scoping.'' The main goal of the scoping process is to focus the
analysis in the EA on the important environmental issues. By this
notice, the Commission requests public comments on the scope of the
issues to address in the EA. We will consider all filed comments during
the preparation of the EA.
---------------------------------------------------------------------------
\2\ We, us, and our refer to the environmental staff of the
Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section, beginning on page 2.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies of the EA will be sent
to the environmental mailing list for public review and comment. If you
would prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an intervenor which is an official party to the Commission's
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene. Instructions for becoming an intervenor are in the Document-
less Intervention Guide under the e-filing link on the Commission's
website. Motions to intervene are more fully described at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP18-
24-000). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public sessions or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: January 11, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-00745 Filed 1-17-18; 8:45 am]