802
Federal Register / Vol. 83, No. 5 / Monday, January 8, 2018 / Notices
pursuant to section 7(b) of the Natural
Gas Act (NGA) and Part 157 of the
Commission’s Regulations, requesting
authorization to abandon approximately
1.3 miles of its 18-inch-diameter
mainline pipeline facilities and
associated appurtenances located in
Miami-Dade County, Florida, all as
more fully set forth in the application
which is on file with the Commission
and open to public inspection.
The filing may also be viewed on the
web at https://www.ferc.gov using the
eLibrary link. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application may be directed to Marg
Camardello, Regulatory Analyst, Lead,
(713) 215–3380, P.O. Box 1396,
Houston, Texas 77251; and Ben
Carranza, Manager, Rates & Regulatory,
(713) 420–5535, 1001 Louisiana Street,
Suite 1000, Houston Texas 77002.
Specifically, Florida Gas states that
the mainline segment proposed for
abandonment spans from Mile Post
(MP) 923.6 to the mainline terminus at
MP 924.9 and is in direct conflict with
Miami-Dade County road construction
project including a bridge replacement.
Florida Gas also states that there are no
firm contracts associated with the
facilities to be abandoned and that there
were no deliveries of gas through this
segment of its mainline in more than
three years. The project cost is estimated
at $450,000.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
There are two ways to become
involved in the Commission’s review of
VerDate Sep<11>2014
16:29 Jan 05, 2018
Jkt 244001
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
five copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
Persons unable to file electronically
should submit original and five copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
Comment Date: 5:00 p.m. Eastern
Time on January 23, 2018.
Dated: January 2, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–00090 Filed 1–5–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1763–003;
ER10–1765–003; ER10–1766–003;
ER10–1769–003; ER10–1767–003;
ER10–1532–003; ER10–1541–004;
ER10–1642–005; ER13–2349–002;
ER13–2350–002.
Applicants: Entergy Arkansas, Inc.,
Entergy Louisiana, LLC, Entergy
Mississippi, Inc., Entergy New Orleans,
LLC, Entergy Texas, Inc., Entergy
Nuclear Palisades, LLC, Entergy Power,
LLC, EWO Marketing, LLC, EAM Nelson
Holding, LLC, RS Cogen, LLC, Entergy
Services, Inc.
Description: Triennial Market Power
Update for the Central Region of the
Entergy MBR Utilities.
Filed Date: 12/28/17.
Accession Number: 20171228–5275.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10–1819–017;
ER10–1820–020.
Applicants: Northern States Power
Company, a Minnesota corporation,
Northern States Power Company, a
Wisconsin corporation
Description: Triennial Market Power
Analysis of Northern States Power
Company, a Minnesota corporation, and
Northern States Power Company, a
Wisconsin corporation.
Filed Date: 12/28/17.
Accession Number: 20171228–5269.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10–2042–025;
ER10–1945–006; ER10–1942–017;
ER17–696–005; ER10–1938–020; ER10–
1934–019; ER10–1893–019; ER10–2985–
023; ER10–3049–024; ER10–3051–024;
ER10–1871–006; ER11–4369–004;
ER16–2218–004; ER10–1862–019.
Applicants: Calpine Energy Services,
L.P., Auburndale Peaker Energy Center,
E:\FR\FM\08JAN1.SGM
08JAN1
sradovich on DSK3GMQ082PROD with NOTICES
Federal Register / Vol. 83, No. 5 / Monday, January 8, 2018 / Notices
LLC, Calpine Construction Finance
Company, LP, Calpine Energy Solutions,
LLC, Calpine PowerAmerica—CA, LLC,
CES Marketing IX, LLC, CES Marketing
X, LLC, Champion Energy Marketing
LLC, Champion Energy Services, LLC,
Champion Energy, LLC, Morgan Energy
Center, LLC, North American Power and
Gas, LLC, North American Power
Business, LLC, Power Contract
Financing, L.L.C.
Description: Updated Market Power
Analysis for the Calpine Southeast MBR
Sellers.
Filed Date: 12/29/17.
Accession Number: 20171229–5161.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10–2063–002.
Applicants: Otter Tail Power
Company.
Description: Triennial MBR Report for
Central Region of Otter Tail Power
Company.
Filed Date: 12/28/17.
Accession Number: 20171228–5302.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10–2211–006.
Applicants: Vandolah Power
Company, L.L.C.
Description: Triennial MBR Report for
Southeast Region of Vandolah Power
Company, L.L.C.
Filed Date: 12/29/17.
Accession Number: 20171229–5117.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10–2739–018;
ER10–2743–013; ER12–995–005; ER10–
1892–007; ER10–2793–007; ER10–2755–
016; ER16–1652–006; ER10–1872–007;
ER10–2751–013; ER10–1859–007.
Applicants: LS Power Marketing, LLC,
Bluegrass Generation Company, L.L.C.,
Cherokee County Cogeneration Partners,
LLC, Columbia Energy LLC, DeSoto
County Generating Company, LLC, Las
Vegas Power Company, LLC,
LifeEnergy, LLC, Mobile Energy LLC,
Renaissance Power, L.L.C., Santa Rosa
Energy Center, LLC.
Description: Updated Market Power
Analysis of the LS Southeast MBR
Sellers.
Filed Date: 12/29/17.
Accession Number: 20171229–5186.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10–2877–002.
Applicants: Cobb Electric
Membership Corporation.
Description: Triennial Market Power
Update for the Central Region of Cobb
Electric Membership Corporation.
Filed Date: 12/29/17.
Accession Number: 20171229–5158.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10–3125–011;
ER10–3102–011; ER15–1447–003;
ER10–3100–011; ER15–1657–006;
ER10–3107–011; ER10–3109–011.
VerDate Sep<11>2014
16:29 Jan 05, 2018
Jkt 244001
Applicants: AL Sandersville, LLC,
Effingham County Power, LLC, MidGeorgia Cogen L.P., MPC Generating,
LLC, SEPG Energy Marketing Services,
LLC, Walton County Power, LLC,
Washington County Power, LLC.
Description: Updated Market Power
Analysis for the Southeast Region of AL
Sandersville, LLC, et al.
Filed Date: 12/29/17.
Accession Number: 20171229–5156.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER17–2457–002.
Applicants: Rock Creek Wind Project,
LLC.
Description: Notice of Non-Material
Change in Status of Rock Creek Wind
Project, LLC.
Filed Date: 12/29/17.
Accession Number: 20171229–5113.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER17–2577–001.
Applicants: York Haven Power
Company, LLC.
Description: Tariff Amendment:
Response to AIR to be effective
11/29/2017.
Filed Date: 12/28/17.
Accession Number: 20171228–5261.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–560–000.
Applicants: Northern Indiana Public
Service Company.
Description: Market-Based Triennial
Review Filing: NIPSCO Triennial
Market Power Update to be effective
12/29/2017.
Filed Date: 12/28/17.
Accession Number: 20171228–5254.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER18–561–000.
Applicants: Wisconsin Public Service
Corporation.
Description: § 205(d) Rate Filing:
Revision to Ancillary Services Tariff to
be effective 2/26/2018.
Filed Date: 12/28/17.
Accession Number: 20171228–5260.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–562–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing: SA
605 7th Rev—NITSA with Bonneville
Power Administration to be effective
3/1/2018.
Filed Date: 12/28/17.
Accession Number: 20171228–5264.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–563–000.
Applicants: Red Pine Wind Project,
LLC.
Description: § 205(d) Rate Filing:
Filing of Red Pine Rate Schedule FERC
No. 1 re Reactive Power Compensation
to be effective 3/1/2018.
Filed Date: 12/28/17.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
803
Accession Number: 20171228–5265.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–564–000.
Applicants: South Central MCN LLC.
Description: Compliance filing:
SCMCN Limited 205 DX Filing to be
effective N/A.
Filed Date: 12/28/17.
Accession Number: 20171228–5266.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–565–000.
Applicants: California Independent
System Operator Corporation.
Description: Petition for Approval of
Disposition of Proceeds of Penalty
Assessments of California Independent
System Operator Corporation.
Filed Date: 12/28/17.
Accession Number: 20171228–5273.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18–566–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2017–12–29_SA 3077 OTP-East River
T–T (Britton) to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5013.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–567–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Otter Tail Power Company.
Description: § 205(d) Rate Filing:
2017–12–29_SA 3076 OTP-East River
T–T (Load) to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5016.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–568–000.
Applicants: Mid-Atlantic Interstate
Transmission, LLC, American
Transmission Systems, Incorporation,
PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
MAIT and ATSI submit Two ECSAs SA
Nos. 4801 and 4860 to be effective
3/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5018.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–569–000.
Applicants: Consolidated Edison
Company of New York, Inc.
Description: § 205(d) Rate Filing: 2017
RY 2 to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5019.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–570–000.
Applicants: Consolidated Edison
Company of New York, Inc.
Description: § 205(d) Rate Filing: 2017
WDS RY 2 to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5020.
E:\FR\FM\08JAN1.SGM
08JAN1
804
Federal Register / Vol. 83, No. 5 / Monday, January 8, 2018 / Notices
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–571–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Attachment AE Revisions to Clarify
ILTCRs to be effective 2/27/2018.
Filed Date: 12/29/17.
Accession Number: 20171229–5026
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18–572–000.
Applicants: South Central MCN LLC.
Description: Limited Revisions to SPP
Transmission Formula Rate Template of
South Central MCN LLC.
Filed Date: 12/28/17.
Accession Number: 20171228–5306.
Comments Due: 5 p.m. ET 1/18/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 29, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–00124 Filed 1–5–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
sradovich on DSK3GMQ082PROD with NOTICES
[Project No. 5124–021]
Notice of Intent To File License
Application, Filing of Pre-Application
Document (Pad), Commencement of
Pre-Filing Process, and Scoping;
Request for Comments on the Pad and
Scoping Document, and Identification
of Issues and Associated Study
Requests; Washington Electric
Cooperative, Inc.
a. Type of Filing: Notice of Intent to
File License Application for a New
License and Commencing Pre-filing
Process.
b. Project No.: 5124–021.
VerDate Sep<11>2014
16:29 Jan 05, 2018
Jkt 244001
c. Dated Filed: October 30, 2017.
d. Submitted By: Washington Electric
Cooperative, Inc.
e. Name of Project: North Branch No.
3 Hydroelectric Project.
f. Location: On the North Branch
Winooski River, in Washington County,
Vermont. The project does not occupy
lands of the United States.
g. Filed Pursuant to: 18 CFR part 5 of
the Commission’s Regulations.
h. Potential Applicant Contact: Ms.
Patricia Richards, General Manager,
Washington Electric Cooperative, Inc.,
P.O. Box 8, 40 Church Street East
Montpelier, Vermont 05651; phone:
(802) 223–5245 or email at
patty.richards@wec.coop.
i. FERC Contact: Michael Tust at (202)
502–6522 or email at michael.tust@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item o below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC 61,076 (2001).
k. With this notice, we are initiating
informal consultation with: (a) The U.S.
Fish and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402 and (b) the State Historic
Preservation Officer, as required by
section 106, National Historic
Preservation Act, and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Washington Electric Cooperative, Inc.
(WEC) as the Commission’s non-federal
representatives for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act and section
106 of the National Historic
Preservation Act.
m. WEC filed a Pre-Application
Document (PAD; including a proposed
process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
n. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). A copy is also available for
inspection and reproduction at the
address in paragraph h.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. With this notice, we are soliciting
comments on the PAD and
Commission’s staff Scoping Document 1
(SD1), as well as study requests. All
comments on the PAD and SD1, and
study requests should be sent to the
address above in paragraph h. In
addition, all comments on the PAD and
SD1, study requests, requests for
cooperating agency status, and all
communications to and from
Commission staff related to the merits of
the potential application must be filed
with the Commission.
The Commission strongly encourages
electronic filing. Please file all
documents using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov. In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–5124–021.
All filings with the Commission must
bear the appropriate heading: Comments
on Pre-Application Document, Study
Requests, Comments on Scoping
Document 1, Request for Cooperating
Agency Status, or Communications to
and from Commission Staff. Any
individual or entity interested in
submitting study requests, commenting
on the PAD or SD1, and any agency
requesting cooperating status must do so
60 days following the date of issuance
of this notice.
p. Although our current intent is to
prepare an environmental assessment
(EA), there is the possibility that an
Environmental Impact Statement (EIS)
will be required. Nevertheless, this
meeting will satisfy the NEPA scoping
requirements, irrespective of whether an
EA or EIS is issued by the Commission.
E:\FR\FM\08JAN1.SGM
08JAN1
Agencies
[Federal Register Volume 83, Number 5 (Monday, January 8, 2018)]
[Notices]
[Pages 802-804]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-00124]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-1763-003; ER10-1765-003; ER10-1766-003; ER10-
1769-003; ER10-1767-003; ER10-1532-003; ER10-1541-004; ER10-1642-005;
ER13-2349-002; ER13-2350-002.
Applicants: Entergy Arkansas, Inc., Entergy Louisiana, LLC, Entergy
Mississippi, Inc., Entergy New Orleans, LLC, Entergy Texas, Inc.,
Entergy Nuclear Palisades, LLC, Entergy Power, LLC, EWO Marketing, LLC,
EAM Nelson Holding, LLC, RS Cogen, LLC, Entergy Services, Inc.
Description: Triennial Market Power Update for the Central Region
of the Entergy MBR Utilities.
Filed Date: 12/28/17.
Accession Number: 20171228-5275.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10-1819-017; ER10-1820-020.
Applicants: Northern States Power Company, a Minnesota corporation,
Northern States Power Company, a Wisconsin corporation
Description: Triennial Market Power Analysis of Northern States
Power Company, a Minnesota corporation, and Northern States Power
Company, a Wisconsin corporation.
Filed Date: 12/28/17.
Accession Number: 20171228-5269.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10-2042-025; ER10-1945-006; ER10-1942-017; ER17-
696-005; ER10-1938-020; ER10-1934-019; ER10-1893-019; ER10-2985-023;
ER10-3049-024; ER10-3051-024; ER10-1871-006; ER11-4369-004; ER16-2218-
004; ER10-1862-019.
Applicants: Calpine Energy Services, L.P., Auburndale Peaker Energy
Center,
[[Page 803]]
LLC, Calpine Construction Finance Company, LP, Calpine Energy
Solutions, LLC, Calpine PowerAmerica--CA, LLC, CES Marketing IX, LLC,
CES Marketing X, LLC, Champion Energy Marketing LLC, Champion Energy
Services, LLC, Champion Energy, LLC, Morgan Energy Center, LLC, North
American Power and Gas, LLC, North American Power Business, LLC, Power
Contract Financing, L.L.C.
Description: Updated Market Power Analysis for the Calpine
Southeast MBR Sellers.
Filed Date: 12/29/17.
Accession Number: 20171229-5161.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10-2063-002.
Applicants: Otter Tail Power Company.
Description: Triennial MBR Report for Central Region of Otter Tail
Power Company.
Filed Date: 12/28/17.
Accession Number: 20171228-5302.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER10-2211-006.
Applicants: Vandolah Power Company, L.L.C.
Description: Triennial MBR Report for Southeast Region of Vandolah
Power Company, L.L.C.
Filed Date: 12/29/17.
Accession Number: 20171229-5117.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10-2739-018; ER10-2743-013; ER12-995-005; ER10-
1892-007; ER10-2793-007; ER10-2755-016; ER16-1652-006; ER10-1872-007;
ER10-2751-013; ER10-1859-007.
Applicants: LS Power Marketing, LLC, Bluegrass Generation Company,
L.L.C., Cherokee County Cogeneration Partners, LLC, Columbia Energy
LLC, DeSoto County Generating Company, LLC, Las Vegas Power Company,
LLC, LifeEnergy, LLC, Mobile Energy LLC, Renaissance Power, L.L.C.,
Santa Rosa Energy Center, LLC.
Description: Updated Market Power Analysis of the LS Southeast MBR
Sellers.
Filed Date: 12/29/17.
Accession Number: 20171229-5186.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10-2877-002.
Applicants: Cobb Electric Membership Corporation.
Description: Triennial Market Power Update for the Central Region
of Cobb Electric Membership Corporation.
Filed Date: 12/29/17.
Accession Number: 20171229-5158.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER10-3125-011; ER10-3102-011; ER15-1447-003; ER10-
3100-011; ER15-1657-006; ER10-3107-011; ER10-3109-011.
Applicants: AL Sandersville, LLC, Effingham County Power, LLC, Mid-
Georgia Cogen L.P., MPC Generating, LLC, SEPG Energy Marketing
Services, LLC, Walton County Power, LLC, Washington County Power, LLC.
Description: Updated Market Power Analysis for the Southeast Region
of AL Sandersville, LLC, et al.
Filed Date: 12/29/17.
Accession Number: 20171229-5156.
Comments Due: 5 p.m. ET 2/27/18.
Docket Numbers: ER17-2457-002.
Applicants: Rock Creek Wind Project, LLC.
Description: Notice of Non-Material Change in Status of Rock Creek
Wind Project, LLC.
Filed Date: 12/29/17.
Accession Number: 20171229-5113.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER17-2577-001.
Applicants: York Haven Power Company, LLC.
Description: Tariff Amendment: Response to AIR to be effective 11/
29/2017.
Filed Date: 12/28/17.
Accession Number: 20171228-5261.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-560-000.
Applicants: Northern Indiana Public Service Company.
Description: Market-Based Triennial Review Filing: NIPSCO Triennial
Market Power Update to be effective 12/29/2017.
Filed Date: 12/28/17.
Accession Number: 20171228-5254.
Comments Due: 5 p.m. ET 2/26/18.
Docket Numbers: ER18-561-000.
Applicants: Wisconsin Public Service Corporation.
Description: Sec. 205(d) Rate Filing: Revision to Ancillary
Services Tariff to be effective 2/26/2018.
Filed Date: 12/28/17.
Accession Number: 20171228-5260.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-562-000.
Applicants: NorthWestern Corporation.
Description: Sec. 205(d) Rate Filing: SA 605 7th Rev--NITSA with
Bonneville Power Administration to be effective 3/1/2018.
Filed Date: 12/28/17.
Accession Number: 20171228-5264.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-563-000.
Applicants: Red Pine Wind Project, LLC.
Description: Sec. 205(d) Rate Filing: Filing of Red Pine Rate
Schedule FERC No. 1 re Reactive Power Compensation to be effective 3/1/
2018.
Filed Date: 12/28/17.
Accession Number: 20171228-5265.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-564-000.
Applicants: South Central MCN LLC.
Description: Compliance filing: SCMCN Limited 205 DX Filing to be
effective N/A.
Filed Date: 12/28/17.
Accession Number: 20171228-5266.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-565-000.
Applicants: California Independent System Operator Corporation.
Description: Petition for Approval of Disposition of Proceeds of
Penalty Assessments of California Independent System Operator
Corporation.
Filed Date: 12/28/17.
Accession Number: 20171228-5273.
Comments Due: 5 p.m. ET 1/18/18.
Docket Numbers: ER18-566-000.
Applicants: Midcontinent Independent System Operator, Inc., Otter
Tail Power Company.
Description: Sec. 205(d) Rate Filing: 2017-12-29_SA 3077 OTP-East
River T-T (Britton) to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5013.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-567-000.
Applicants: Midcontinent Independent System Operator, Inc., Otter
Tail Power Company.
Description: Sec. 205(d) Rate Filing: 2017-12-29_SA 3076 OTP-East
River T-T (Load) to be effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5016.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-568-000.
Applicants: Mid-Atlantic Interstate Transmission, LLC, American
Transmission Systems, Incorporation, PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: MAIT and ATSI submit Two
ECSAs SA Nos. 4801 and 4860 to be effective 3/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5018.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-569-000.
Applicants: Consolidated Edison Company of New York, Inc.
Description: Sec. 205(d) Rate Filing: 2017 RY 2 to be effective 1/
1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5019.
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-570-000.
Applicants: Consolidated Edison Company of New York, Inc.
Description: Sec. 205(d) Rate Filing: 2017 WDS RY 2 to be
effective 1/1/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5020.
[[Page 804]]
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-571-000.
Applicants: Southwest Power Pool, Inc.
Description: Sec. 205(d) Rate Filing: Attachment AE Revisions to
Clarify ILTCRs to be effective 2/27/2018.
Filed Date: 12/29/17.
Accession Number: 20171229-5026
Comments Due: 5 p.m. ET 1/19/18.
Docket Numbers: ER18-572-000.
Applicants: South Central MCN LLC.
Description: Limited Revisions to SPP Transmission Formula Rate
Template of South Central MCN LLC.
Filed Date: 12/28/17.
Accession Number: 20171228-5306.
Comments Due: 5 p.m. ET 1/18/18.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: December 29, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-00124 Filed 1-5-18; 8:45 am]