Douglas Leen; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 61559 [2017-28094]
Download as PDF
sradovich on DSK3GMQ082PROD with NOTICES
Federal Register / Vol. 82, No. 248 / Thursday, December 28, 2017 / Notices
increase of 9.2 million cubic feet per
day in the minimum required
deliverability (MRD) without increasing
the overall storage capacity of the field.
Dominion Energy states that the project
will not affect the contracted firm
capacity and MRD rights held by
existing firm storage customers at Clay
Basin. Dominion Energy estimates that
the cost of the proposed project is
approximately $3.6 million.
Any questions regarding this
application should be directed L.
Bradley Burton, Director-Regulatory,
Rates, Certificates and Tariffs Dominion
Energy Questar Corporation, 333 South
State Street, P.O. Box 45360, Salt Lake
City, Utah 84145–0360, by telephone at
(801) 324–2459, by fax at (801) 324–
2905, or by email at brad.burton@
dominionenergy.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
VerDate Sep<11>2014
18:14 Dec 27, 2017
Jkt 244001
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenter will
not receive copies of all documents filed
by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
Dated: December 21, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–28087 Filed 12–27–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. P–14862–000]
Douglas Leen; Notice of Intent To File
License Application, Filing of PreApplication Document, and Approving
Use of the Traditional Licensing
Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: P–14862–000.
c. Date Filed: November 14, 2017.
d. Submitted By: Douglas Leen.
e. Name of Project: Kupeanof
Microhydro Project.
f. Location: On an unnamed stream, in
Petersburg Borough, Alaska. The project
occupies 0.1 acres of United States
lands administered by U.S. Forest
Service.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact:
Douglas Leen, P.O. Box 341, Petersburg,
AK 99833; (907) 518–0335; mail@
dougleen.com.
PO 00000
Frm 00027
Fmt 4703
Sfmt 9990
61559
i. FERC Contact: Ryan Hansen at (202)
502–8074; or email at ryan.hansen@
ferc.gov.
j. Mr. Leen filed his request to use the
Traditional Licensing Process on
November 14, 2017. Mr. Leen provided
public notice of his request on
November 16, 2017. In a letter dated
December 20, 2017, the Director of the
Division of Hydropower Licensing
approved Mr. Leen’s request to use the
Traditional Licensing Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
Alaska State Historic Preservation
Officer, as required by section 106,
National Historic Preservation Act, and
the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. Mr. Leen filed a Pre-Application
Document (PAD; including a proposed
process plan and schedule) with the
Commission, pursuant to 18 CFR 5.6 of
the Commission’s regulations.
m. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website (https://
www.ferc.gov), using the eLibrary link.
Enter the docket number, excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at ferconlinesupport@ferc.gov,
(866) 208–3676 (toll free), or (202) 502–
8659 (TTY). A copy is also available for
inspection and reproduction at the
address in paragraph h.
n. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: December 21, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–28094 Filed 12–27–17; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\28DEN1.SGM
28DEN1
Agencies
[Federal Register Volume 82, Number 248 (Thursday, December 28, 2017)]
[Notices]
[Page 61559]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-28094]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. P-14862-000]
Douglas Leen; Notice of Intent To File License Application,
Filing of Pre-Application Document, and Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project No.: P-14862-000.
c. Date Filed: November 14, 2017.
d. Submitted By: Douglas Leen.
e. Name of Project: Kupeanof Microhydro Project.
f. Location: On an unnamed stream, in Petersburg Borough, Alaska.
The project occupies 0.1 acres of United States lands administered by
U.S. Forest Service.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Douglas Leen, P.O. Box 341,
Petersburg, AK 99833; (907) 518-0335; [email protected].
i. FERC Contact: Ryan Hansen at (202) 502-8074; or email at
[email protected].
j. Mr. Leen filed his request to use the Traditional Licensing
Process on November 14, 2017. Mr. Leen provided public notice of his
request on November 16, 2017. In a letter dated December 20, 2017, the
Director of the Division of Hydropower Licensing approved Mr. Leen's
request to use the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section
7 of the Endangered Species Act and the joint agency regulations
thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b)
of the Magnuson-Stevens Fishery Conservation and Management Act and
implementing regulations at 50 CFR 600.920. We are also initiating
consultation with the Alaska State Historic Preservation Officer, as
required by section 106, National Historic Preservation Act, and the
implementing regulations of the Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. Mr. Leen filed a Pre-Application Document (PAD; including a
proposed process plan and schedule) with the Commission, pursuant to 18
CFR 5.6 of the Commission's regulations.
m. A copy of the PAD is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's website
(https://www.ferc.gov), using the eLibrary link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at
the address in paragraph h.
n. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: December 21, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-28094 Filed 12-27-17; 8:45 am]