Notice of Request Under Blanket Authorization; Columbia Gas Transmission, LLC, 61560 [2017-28086]

Download as PDF 61560 Federal Register / Vol. 82, No. 248 / Thursday, December 28, 2017 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP18–30–000] sradovich on DSK3GMQ082PROD with NOTICES Notice of Request Under Blanket Authorization; Columbia Gas Transmission, LLC Take notice that on December 15, 2017, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Houston, Texas 77002–2700, filed in Docket No. CP18–30–000 a prior notice request pursuant to sections 157.205 and 157.208 of the Commission’s regulations under the Natural Gas Act (NGA), and Columbia’s blanket certificate issued in Docket No. CP83– 76–000, to perform installations and activities to enable the in-line inspection, or pigging, of approximately 53.6 miles of its 20-inch diameter Line D–600 (D600 Launcher & Receiver Project). The majority of the proposed project installations and activities will be located at nine (9) modification points (Mod Points) along the existing Line D–600 right-of-way in Allen, Paulding, and Putnam Counties, Ohio. Columbia’s project will consist of various modification activities necessary to insure that the line is pigcapable, including the installation of one new 24 x 20 bi-directional launcher/receiver at Mod Point 1 in Columbia’s existing Cecil Panhandle Station in Paulding County, Ohio, one new 24 x 20 bi-directional launcher/ receiver at Mod Point 9 in Columbia’s existing Greeley Chapel Station in Allen County, Ohio, and additional appurtenances, including valves, tees, and stopples, at seven other Mod Points in Paulding, Putnam, and Allen Counties, Ohio, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Linda Farquhar, Manager, Project Determinations & Regulatory Administration, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, by telephone at (832) 320– 5685, by facsimile at (832) 320–6685, or VerDate Sep<11>2014 18:14 Dec 27, 2017 Jkt 244001 by email at linda_farquhar@ transcanada.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and seven copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: December 21, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–28086 Filed 12–27–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14751–002] Alpine Pacific Utilities Hydro, LLC; Notice of Application Accepted for Filing With the Commission, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, Intent To Waive Scoping, Soliciting Comments, Terms and Conditions, Recommendations, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Minor License. b. Project No.: 14751–002. c. Date filed: February 1, 2017. d. Applicant: Alpine Pacific Utilities Hydro, LLC. e. Name of Project: Fresno Dam Site Water Power Project. f. Location: On the Milk River in Hill County, Montana near the town of Kremlin at the existing Bureau of Reclamation Fresno Dam. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Justin Ahmann, Alpine Pacific Utilities Hydro, LLC, 75 Somers Road, Somers, Montana 59932, (406) 755–1333. i. FERC Contact: John Matkowski, (202) 502–8576 or john.matkowski@ ferc.gov. j. Deadline for filing motions to intervene and protests, comments, terms and conditions, recommendations, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file motions to E:\FR\FM\28DEN1.SGM 28DEN1

Agencies

[Federal Register Volume 82, Number 248 (Thursday, December 28, 2017)]
[Notices]
[Page 61560]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-28086]



[[Page 61560]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-30-000]


Notice of Request Under Blanket Authorization; Columbia Gas 
Transmission, LLC

    Take notice that on December 15, 2017, Columbia Gas Transmission, 
LLC (Columbia), 700 Louisiana Street, Houston, Texas 77002-2700, filed 
in Docket No. CP18-30-000 a prior notice request pursuant to sections 
157.205 and 157.208 of the Commission's regulations under the Natural 
Gas Act (NGA), and Columbia's blanket certificate issued in Docket No. 
CP83-76-000, to perform installations and activities to enable the in-
line inspection, or pigging, of approximately 53.6 miles of its 20-inch 
diameter Line D-600 (D600 Launcher & Receiver Project). The majority of 
the proposed project installations and activities will be located at 
nine (9) modification points (Mod Points) along the existing Line D-600 
right-of-way in Allen, Paulding, and Putnam Counties, Ohio.
    Columbia's project will consist of various modification activities 
necessary to insure that the line is pig-capable, including the 
installation of one new 24 x 20 bi-directional launcher/receiver at Mod 
Point 1 in Columbia's existing Cecil Panhandle Station in Paulding 
County, Ohio, one new 24 x 20 bi-directional launcher/receiver at Mod 
Point 9 in Columbia's existing Greeley Chapel Station in Allen County, 
Ohio, and additional appurtenances, including valves, tees, and 
stopples, at seven other Mod Points in Paulding, Putnam, and Allen 
Counties, Ohio, all as more fully set forth in the application which is 
on file with the Commission and open to public inspection. The filing 
may also be viewed on the web at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Any questions concerning this application may be directed to Linda 
Farquhar, Manager, Project Determinations & Regulatory Administration, 
Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, 
Houston, Texas 77002-2700, by telephone at (832) 320-5685, by facsimile 
at (832) 320-6685, or by email at [email protected].
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and seven copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.

    Dated: December 21, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-28086 Filed 12-27-17; 8:45 am]
 BILLING CODE 6717-01-P