In the Matter of All Operating Reactor Licensees, 60773-60774 [2017-27583]
Download as PDF
sradovich on DSK3GMQ082PROD with NOTICES
Federal Register / Vol. 82, No. 245 / Friday, December 22, 2017 / Notices
of a radiological emergency, to establish
plume exposure and ingestion pathway
emergency planning zones for nuclear power
plants, and to ensure that licensees maintain
effective offsite and onsite radiological
emergency plans. The standards and
requirements in these regulations were
developed by considering the risks associated
with operation of a power reactor at its
licensed full-power level. These risks include
the potential for a reactor accident with
offsite radiological dose consequences.
As discussed previously in Section III,
because FCS is permanently shut down and
defueled, there is no longer a risk of a
significant offsite radiological release from a
design-basis accident exceeding EPA early
phase PAG at the exclusion area boundary
and the risk of a significant offsite
radiological release from a beyond-designbasis accident is greatly reduced when
compared to an operating power reactor. The
NRC staff has confirmed the reduced risks at
FCS by comparing the generic risk
assumptions in the analyses in NUREG–1738
to site-specific conditions at FCS and
determined that the risk values in NUREG–
1738 bound the risks presented by FCS. As
indicated by the results of the research
conducted for NUREG–1738 and more
recently, for NUREG–2161, ‘‘Consequence
Study of a Beyond-Design-Basis Earthquake
Affecting the Spent Fuel Pool for a U.S. Mark
I Boiling Water Reactor’’ (ADAMS Accession
No. ML14255A365), while other
consequences can be extensive, accidents
from SFPs with significant decay time have
little potential to cause offsite early fatalities,
even if the formal offsite radiological EP
requirements were relaxed. The licensee’s
analysis of a beyond-design-basis accident
involving a complete loss of SFP water
inventory, based on an adiabatic heatup
analysis of the limiting fuel assembly for
decay heat, shows that within 530 days (1
year, 165 days) after shutdown, the time for
the limiting fuel assembly to reach 900 °C is
10 hours after the assemblies have been
uncovered assuming a loss of air cooling.
The only analyzed beyond-design-basis
accident scenario that progresses to a
condition where a significant offsite release
might occur, involves the very unlikely event
where the SFP drains in such a way that all
modes of cooling or heat transfer are assumed
to be unavailable, which is referred to as an
adiabatic heatup of the spent fuel. The
licensee’s analysis of this beyond-designbasis accident shows that within 530 days (1
year, 165 days) after shutdown, more than 10
hours would be available between the time
the fuel is initially uncovered (at which time
adiabatic heatup is conservatively assumed
to begin), until the fuel cladding reaches a
temperature of 1652 degrees Fahrenheit (900
°C), which is the temperature associated with
rapid cladding oxidation and the potential
for a significant radiological release. This
analysis conservatively does not include the
period of time from the initiating event
causing a loss of SFP water inventory until
all cooling means are lost.
The NRC staff has verified OPPD’s analyses
and its calculations. The analyses provide
reasonable assurance that in granting the
requested exemptions to OPPD, there is no
VerDate Sep<11>2014
16:59 Dec 21, 2017
Jkt 244001
design-basis accident that will result in an
offsite radiological release exceeding the EPA
early phase PAGs at the exclusion area
boundary. In the unlikely event of a beyonddesign-basis accident affecting the SFP that
results in a complete loss of heat removal via
all modes of heat transfer, there will be well
over 10 hours available before an offsite
release might occur and, therefore, at least 10
hours to initiate appropriate mitigating
actions to restore a means of heat removal to
the spent fuel. If a radiological release were
projected to occur under this unlikely
scenario, a minimum of 10 hours is
considered sufficient time for offsite
authorities to implement protective actions
using a CEMP approach to protect the health
and safety of the public.
Exemptions from the offsite EP
requirements in 10 CFR part 50 have
previously been approved by the NRC when
the site-specific analyses show that at least
10 hours is available following a loss of SFP
coolant inventory accident with no air
cooling (or other methods of removing decay
heat) until cladding of the hottest fuel
assembly reaches the zirconium rapid
oxidation temperature. The NRC staff
concluded in its previously granted
exemptions, as it does with the OPPD
requested EP exemptions, that if a minimum
of 10 hours is available to initiate mitigative
actions consistent with plant conditions, or
if needed, for offsite authorities to implement
protective actions using a CEMP approach,
then formal offsite radiological emergency
plans, required under 10 CFR part 50, are not
necessary at permanently shutdown and
defueled facilities.
Additionally, FCS committed to
maintaining SFP makeup strategies in its
letter to the NRC dated December 16, 2016
(ADAMS Accession No. ML16356A578). The
multiple strategies for providing makeup to
the SFP include: using existing plant systems
for inventory makeup; an internal strategy
that relies on the fire protection system with
redundant pumps (one diesel-driven and
electric motor-driven); and onsite diesel fire
truck that can take suction from the Missouri
River. These strategies will continue to be
required as license condition 3.G,
‘‘Mitigation Strategy License Condition.’’
Considering the very low probability of
beyond-design-basis accidents affecting the
SFP, these diverse strategies provide multiple
methods to obtain additional makeup or
spray to the SFP before the onset of any
postulated offsite radiological release.
For all the reasons stated above, the NRC
staff finds that the licensee’s requested
exemptions to meet the underlying purpose
of all of the standards in 10 CFR 50.47(b),
and requirements in 10 CFR 50.47(c)(2) and
10 CFR part 50, Appendix E, acceptably
satisfy the special circumstances in 10 CFR
50.12(a)(2)(ii) in view of the greatly reduced
risk of offsite radiological consequences
associated with the permanently shutdown
and defueled state of the FCS facility.
The NRC staff has concluded that the
exemptions being granted by this action will
maintain an acceptable level of emergency
preparedness at FCS and, if needed, that
there is reasonable assurance that adequate
offsite protective measures can and will be
PO 00000
Frm 00078
Fmt 4703
Sfmt 4703
60773
taken by State and local government agencies
using a CEMP approach in the unlikely event
of a radiological emergency at the FCS
facility. Since the underlying purposes of the
rules, as exempted, would continue to be
achieved, even with the elimination of the
requirements under 10 CFR part 50 to
maintain formal offsite radiological
emergency plans and reduction in the scope
of the onsite emergency planning activities at
FCS, the special circumstances required by
10 CFR 50.12(a)(2)(ii) exist.
E. Environmental Considerations
In accordance with 10 CFR 51.31(a), the
Commission has determined that the granting
of this exemption will not have a significant
effect on the quality of the human
environment as discussed in the NRC staff’s
Finding of No Significant Impact and
associated Environmental Assessment
published November 27, 2017 (82 FR 56060).
IV. Conclusions
Accordingly, the Commission has
determined, pursuant to 10 CFR 50.12(a), that
OPPD’s request for exemptions from certain
EP requirements in 10 CFR 50.47(b), 10 CFR
50.47(c)(2), and 10 CFR part 50, Appendix E,
Section IV, and as summarized in Table 1 of
the exemption dated December 11, 2017, are
authorized by law, will not present an undue
risk to the public health and safety, and are
consistent with the common defense and
security. Also, special circumstances are
present. Therefore, the Commission hereby
grants OPPD’s exemptions from certain EP
requirements of 10 CFR 50.47(b), 10 CFR
50.47(c)(2), and 10 CFR part 50, Appendix E,
Section IV, as discussed and evaluated in
detail in the staff’s safety evaluation dated
December 11, 2017. The exemptions are
effective as of April 7, 2018.
Dated at Rockville, Maryland, this 11th day
of December, 2017.
For the Nuclear Regulatory Commission.
Kathryn M. Brock,
Acting Director, Division of Operating
Reactor Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2017–27590 Filed 12–21–17; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2016–0061]
In the Matter of All Operating Reactor
Licensees
Nuclear Regulatory
Commission.
ACTION: Director’s decision under 10
CFR 2.206; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued a
director’s decision in response to a
petition dated February 19, 2016, filed
by Roy Mathew, Sheila Ray, Swagata
Som, Gurcharan Singh Matharu, Tania
Martinez Navedo, Thomas Koshy, and
SUMMARY:
E:\FR\FM\22DEN1.SGM
22DEN1
sradovich on DSK3GMQ082PROD with NOTICES
60774
Federal Register / Vol. 82, No. 245 / Friday, December 22, 2017 / Notices
Kenneth Miller (Petitioners), requesting
that the NRC take enforcement-related
action with regard to all operating
nuclear power plants. The petitioner’s
requests and the director’s decision are
included in the SUPPLEMENTARY
INFORMATION section of this document.
DATES: The director’s decision was
issued on December 12, 2017.
ADDRESSES: Please refer to Docket ID
NRC–2016–0061 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2016–0061. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual(s) listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Tanya Mensah, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
3610, email: Tanya.Mensah@nrc.gov.
SUPPLEMENTARY INFORMATION: Notice is
hereby given that the Director, Office of
Nuclear Reactor Regulation, has issued
a director’s decision (ADAMS Accession
No. ML17304A893) under Title 10 of
the Code of Federal Regulations (10
CFR) section 2.206 on a petition filed by
the Petitioners on February 19, 2016
(ADAMS Accession No. ML16050A223).
The Petitioners requested that the
NRC take enforcement action against all
operating nuclear power plants.
Specifically, the Petitioners requested
VerDate Sep<11>2014
16:59 Dec 21, 2017
Jkt 244001
that the NRC either: (1) Issue orders to
require immediate corrective actions
including compensatory measures to
address the operability of electric power
systems in accordance with their plant
technical specifications, and to
implement plant modifications in
accordance with current NRC regulatory
requirements and staff guidance
provided in the references within the
2.206 petition; or (2) issue orders to
immediately shut down the nuclear
power plants that are operating without
addressing the significant design
deficiency identified in NRC Bulletin
2012–01, ‘‘Design Vulnerability in
Electric Power System,’’ dated July 27,
2012, (ADAMS Accession No.
ML12074A115) since the licensees are
not in compliance with their technical
specifications (typically Section 3.8.1)
related to onsite and offsite power
systems.
On February 24, 2016, the NRC’s
petition manager acknowledged receipt
of the petition and offered the
Petitioners an opportunity to address
the Petition Review Board (PRB). The
Petitioners declined an opportunity to
address the PRB on the basis that the
petition already contained all of the
relevant facts to support the PRB’s
review.
The NRC sent a copy of the proposed
director’s decision to the Petitioners and
to the licensees for comment by letters
dated September 18, 2017 (ADAMS
Accession Nos. ML17156A197 and
ML17156A214). The Petitioners and the
licensees were provided the opportunity
to provide comments on any part of the
proposed director’s decision that was
considered to be erroneous or any issues
in the petition that were not addressed.
The Petitioners provided comments by
letter dated October 11, 2017 (ADAMS
Accession No. ML17291A040), and the
Nuclear Energy Institute (NEI) provided
comments, on behalf of licensees, by
letter dated October 16, 2017 (ADAMS
Accession No. ML17291A846). No new
information was provided. To enhance
the clarity of the director’s decision, the
NRC staff revised the description of the
NRC’s accident sequence precursor
(ASP) program provided in Section D of
the director’s decision, to differentiate
between condition and event
assessments. The comments from the
Petitioners and NEI, along with the NRC
staff’s responses to the comments, are
included as an attachment to the
director’s decision. The attachment
identifies any updates to the director’s
decision, as a result of comments
received from the Petitioners and NEI.
The Director, Office of Nuclear
Reactor Regulation, has determined that
the request(s) to issue orders to
PO 00000
Frm 00079
Fmt 4703
Sfmt 4703
operating reactor licensees regarding an
open phase condition be denied. The
reasons for this decision are explained
in the Director’s Decision DD–17–04,
pursuant to 10 CFR 2.206.
The NRC will file a copy of the
director’s decision with the Secretary of
the Commission for the Commission’s
review in accordance with 10 CFR
2.206. As provided by this regulation,
the director’s decision will constitute
the final action of the Commission 25
days after the date of the decision unless
the Commission, on its own motion,
institutes a review of the director’s
decision in that time.
Dated at Rockville, Maryland, this 19th day
of December 2017.
For the Nuclear Regulatory Commission.
Tanya M. Mensah,
Senior Project Manager, ROP Oversight and
Generic Communications Branch, Division of
Inspection and Regional Support, Office of
Nuclear Reactor Regulation.
[FR Doc. 2017–27583 Filed 12–21–17; 8:45 am]
BILLING CODE 7590–01–P
POSTAL REGULATORY COMMISSION
[Docket Nos. MC2018–58 and CP2018–95;
CP2018–96; CP2018–97; MC2018–59 and
CP2018–98; CP2018–99]
New Postal Products
Postal Regulatory Commission.
Notice.
AGENCY:
ACTION:
The Commission is noticing
recent Postal Service filings for the
Commission’s consideration concerning
negotiated service agreements. This
notice informs the public of the filing,
invites public comment, and takes other
administrative steps.
DATES: Comments are due: December
26, 2017 (Comment due date applies to
MC2018–58 and CP2018–95; CP2018–
96; CP2018–97); December 27, 2017
(Comment due date applies to MC2018–
59 and CP2018–98; CP2018–99).
ADDRESSES: Submit comments
electronically via the Commission’s
Filing Online system at https://
www.prc.gov. Those who cannot submit
comments electronically should contact
the person identified in the FOR FURTHER
INFORMATION CONTACT section by
telephone for advice on filing
alternatives.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
David A. Trissell, General Counsel, at
202–789–6820.
SUPPLEMENTARY INFORMATION:
Table of Contents
I. Introduction
E:\FR\FM\22DEN1.SGM
22DEN1
Agencies
[Federal Register Volume 82, Number 245 (Friday, December 22, 2017)]
[Notices]
[Pages 60773-60774]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-27583]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2016-0061]
In the Matter of All Operating Reactor Licensees
AGENCY: Nuclear Regulatory Commission.
ACTION: Director's decision under 10 CFR 2.206; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued a
director's decision in response to a petition dated February 19, 2016,
filed by Roy Mathew, Sheila Ray, Swagata Som, Gurcharan Singh Matharu,
Tania Martinez Navedo, Thomas Koshy, and
[[Page 60774]]
Kenneth Miller (Petitioners), requesting that the NRC take enforcement-
related action with regard to all operating nuclear power plants. The
petitioner's requests and the director's decision are included in the
SUPPLEMENTARY INFORMATION section of this document.
DATES: The director's decision was issued on December 12, 2017.
ADDRESSES: Please refer to Docket ID NRC-2016-0061 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2016-0061. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact
the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Tanya Mensah, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-3610, email: [email protected].
SUPPLEMENTARY INFORMATION: Notice is hereby given that the Director,
Office of Nuclear Reactor Regulation, has issued a director's decision
(ADAMS Accession No. ML17304A893) under Title 10 of the Code of Federal
Regulations (10 CFR) section 2.206 on a petition filed by the
Petitioners on February 19, 2016 (ADAMS Accession No. ML16050A223).
The Petitioners requested that the NRC take enforcement action
against all operating nuclear power plants. Specifically, the
Petitioners requested that the NRC either: (1) Issue orders to require
immediate corrective actions including compensatory measures to address
the operability of electric power systems in accordance with their
plant technical specifications, and to implement plant modifications in
accordance with current NRC regulatory requirements and staff guidance
provided in the references within the 2.206 petition; or (2) issue
orders to immediately shut down the nuclear power plants that are
operating without addressing the significant design deficiency
identified in NRC Bulletin 2012-01, ``Design Vulnerability in Electric
Power System,'' dated July 27, 2012, (ADAMS Accession No. ML12074A115)
since the licensees are not in compliance with their technical
specifications (typically Section 3.8.1) related to onsite and offsite
power systems.
On February 24, 2016, the NRC's petition manager acknowledged
receipt of the petition and offered the Petitioners an opportunity to
address the Petition Review Board (PRB). The Petitioners declined an
opportunity to address the PRB on the basis that the petition already
contained all of the relevant facts to support the PRB's review.
The NRC sent a copy of the proposed director's decision to the
Petitioners and to the licensees for comment by letters dated September
18, 2017 (ADAMS Accession Nos. ML17156A197 and ML17156A214). The
Petitioners and the licensees were provided the opportunity to provide
comments on any part of the proposed director's decision that was
considered to be erroneous or any issues in the petition that were not
addressed. The Petitioners provided comments by letter dated October
11, 2017 (ADAMS Accession No. ML17291A040), and the Nuclear Energy
Institute (NEI) provided comments, on behalf of licensees, by letter
dated October 16, 2017 (ADAMS Accession No. ML17291A846). No new
information was provided. To enhance the clarity of the director's
decision, the NRC staff revised the description of the NRC's accident
sequence precursor (ASP) program provided in Section D of the
director's decision, to differentiate between condition and event
assessments. The comments from the Petitioners and NEI, along with the
NRC staff's responses to the comments, are included as an attachment to
the director's decision. The attachment identifies any updates to the
director's decision, as a result of comments received from the
Petitioners and NEI.
The Director, Office of Nuclear Reactor Regulation, has determined
that the request(s) to issue orders to operating reactor licensees
regarding an open phase condition be denied. The reasons for this
decision are explained in the Director's Decision DD-17-04, pursuant to
10 CFR 2.206.
The NRC will file a copy of the director's decision with the
Secretary of the Commission for the Commission's review in accordance
with 10 CFR 2.206. As provided by this regulation, the director's
decision will constitute the final action of the Commission 25 days
after the date of the decision unless the Commission, on its own
motion, institutes a review of the director's decision in that time.
Dated at Rockville, Maryland, this 19th day of December 2017.
For the Nuclear Regulatory Commission.
Tanya M. Mensah,
Senior Project Manager, ROP Oversight and Generic Communications
Branch, Division of Inspection and Regional Support, Office of Nuclear
Reactor Regulation.
[FR Doc. 2017-27583 Filed 12-21-17; 8:45 am]
BILLING CODE 7590-01-P