Spire STL Pipeline LLC; Supplemental Notice of Availability of the Environmental Assessment and Reopening of Comment Period for the Proposed Spire STL Pipeline Project, 57249 [2017-25998]

Download as PDF Federal Register / Vol. 82, No. 231 / Monday, December 4, 2017 / Notices the Commission issued a Notice of Intent to Prepare an Environmental Impact Statement for the Planned Midcontinent Supply Header Interstate Pipeline Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Sessions. On March 22, 2017, the Commission issued a Supplemental Notice to seek comments on additional facilities identified by Midship Pipeline as part of the MIDSHIP Project. The notices were sent to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; affected property owners; other interested parties; and local libraries and newspapers. Major issues raised include the potential for induced seismicity; possible alternative routes; and potential impacts on agricultural lands, cattle grazing, threatened and endangered species, surface water and groundwater resources, air quality and noise, and safety. The U.S. Environmental Protection Agency is a cooperating agency in the preparation of the EIS. sradovich on DSK3GMQ082PROD with NOTICES Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents via email. Go to www.ferc.gov/docs-filing/ esubscription.asp. Additional information about the MIDSHIP Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC Web site (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–458), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ ferc.gov. The eLibrary link on the FERC Web site also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. [FR Doc. 2017–26031 Filed 12–1–17; 8:45 am] BILLING CODE 6717–01–P 18:22 Dec 01, 2017 Federal Energy Regulatory Commission [Docket Nos. CP17–40–000 and CP17–40– 001] Spire STL Pipeline LLC; Supplemental Notice of Availability of the Environmental Assessment and Reopening of Comment Period for the Proposed Spire STL Pipeline Project On September 29, 2017, the Federal Energy Regulatory Commission (FERC or Commission) issued in Docket Nos. CP17–40–000 and CP17–40–001 a Notice of Availability of the Environmental Assessment for the Proposed Spire STL Pipeline Project. FERC has subsequently learned that delivery of the CD version of the Environmental Assessment (EA) was delayed and as a result some stakeholders did not receive a copy of the EA until after the comment period had closed. In recognition of the delay in receipt, this supplemental notice announces the opening of another comment period. A CD containing an electronic copy of the EA was previously mailed to you. Alternatively, the EA is available for public viewing on the FERC’s Web site (www.ferc.gov) using the eLibrary link and searching for accession number 20170929–3022; the direct link is as follows: https://elibrary.FERC.gov/ idmws/file_list.asp?accession_num= 20170929-3022. The enclosure contains the original notice of availability describing the project and the methods you can use to file your comments to the Commission. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before December 22, 2017. Dated: November 22, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–25998 Filed 12–1–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Dated: November 28, 2017. Kimberly D. Bose, Secretary. VerDate Sep<11>2014 DEPARTMENT OF ENERGY Jkt 244001 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC18–23–000. PO 00000 Frm 00055 Fmt 4703 Sfmt 4703 57249 Applicants: Dynegy Inc., Vistra Energy Corp. Description: Joint Application of Dynegy Inc., et al. for Authorization for Merger of Jurisdictional Assets and Purchase of Securities under Sections 203(a)(1) and 203(a)(2) of the Federal Power Act. Filed Date: 11/22/17. Accession Number: 20171122–5134. Comments Due: 5 p.m. ET 1/22/17. Docket Numbers: EC18–24–000. Applicants: Innergex Renewable Energy Inc. Description: Application of Innergex Renewable Energy Inc. for Authorization of Acquisition under Section 203(a)(2). Filed Date: 11/24/17. Accession Number: 20171124–5031. Comments Due: 5 p.m. ET 12/15/17. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2331–068; ER10–2319–058; ER10–2317–058; ER13–1351–040; ER10–2330–065. Applicants: J.P. Morgan Ventures Energy Corporation, BE CA LLC, BE Alabama LLC, Florida Power Development LLC, Utility Contract Funding, L.L.C. Description: Notice of Non-Material Change in Status of the J.P. Morgan Sellers. Filed Date: 11/27/17. Accession Number: 20171127–5059. Comments Due: 5 p.m. ET 12/18/17. Docket Numbers: ER17–2087–001. Applicants: Hog Creek Wind Project, LLC. Description: Notice of Non-Material Change in Status of Hog Creek Wind Project, LLC. Filed Date: 11/27/17. Accession Number: 20171127–5061. Comments Due: 5 p.m. ET 12/18/17. Docket Numbers: ER18–329–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Six Interconnection Service Agreements re: Dayton Transfer to be effective 10/26/2017. Filed Date: 11/27/17. Accession Number: 20171127–5010. Comments Due: 5 p.m. ET 12/18/17. Docket Numbers: ER18–330–000. Applicants: NSTAR Electric Company. Description: Tariff Cancellation: Notice of Cancellation of Essential Power Newington Design Engineering Agreement to be effective 11/27/2017. Filed Date: 11/27/17. Accession Number: 20171127–5080. Comments Due: 5 p.m. ET 12/18/17. E:\FR\FM\04DEN1.SGM 04DEN1

Agencies

[Federal Register Volume 82, Number 231 (Monday, December 4, 2017)]
[Notices]
[Page 57249]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-25998]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-40-000 and CP17-40-001]


Spire STL Pipeline LLC; Supplemental Notice of Availability of 
the Environmental Assessment and Reopening of Comment Period for the 
Proposed Spire STL Pipeline Project

    On September 29, 2017, the Federal Energy Regulatory Commission 
(FERC or Commission) issued in Docket Nos. CP17-40-000 and CP17-40-001 
a Notice of Availability of the Environmental Assessment for the 
Proposed Spire STL Pipeline Project. FERC has subsequently learned that 
delivery of the CD version of the Environmental Assessment (EA) was 
delayed and as a result some stakeholders did not receive a copy of the 
EA until after the comment period had closed. In recognition of the 
delay in receipt, this supplemental notice announces the opening of 
another comment period.
    A CD containing an electronic copy of the EA was previously mailed 
to you. Alternatively, the EA is available for public viewing on the 
FERC's Web site (www.ferc.gov) using the eLibrary link and searching 
for accession number 20170929-3022; the direct link is as follows: 
https://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20170929-3022.
    The enclosure contains the original notice of availability 
describing the project and the methods you can use to file your 
comments to the Commission. To ensure that the Commission has the 
opportunity to consider your comments prior to making its decision on 
this project, it is important that we receive your comments in 
Washington, DC on or before December 22, 2017.

    Dated: November 22, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-25998 Filed 12-1-17; 8:45 am]
BILLING CODE 6717-01-P