Town of West Stockbridge; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 47498 [2017-22010]

Download as PDF 47498 Federal Register / Vol. 82, No. 196 / Thursday, October 12, 2017 / Notices Commission will issue a notice requesting comments, protests, and motions to intervene in that proceeding. Dated: October 5, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–22005 Filed 10–11–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13371–002] asabaliauskas on DSKBBXCHB2PROD with NOTICES Town of West Stockbridge; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Exemption from Licensing. b. Project No.: 13371–002. c. Date Filed: September 21, 2017. d. Applicant: Town of West Stockbridge (West Stockbridge). e. Name of Project: Shaker Mill Dam Hydroelectric Project. f. Location: On the Williams River, in the Town of West Stockbridge, Berkshire County, Massachusetts. No federal or tribal lands would be occupied by project works or located within the project boundary. g. Filed Pursuant to: Public Utility Regulatory Policies Act of 1978, 16 U.S.C. 2705, 2708 (2012), amended by the Hydropower Regulatory Efficiency Act of 2013, Public Law 113–23, 127 Stat. 493 (2013). h. Applicant Contact: Town of West Stockbridge, c/o Earl B. Moffatt, Chairman, Board of Selectmen, 21 State Line Rd., P.O. Box 525, West Stockbridge, MA 01266; (413) 232–0300, extension 319. i. FERC Contact: Michael Watts, (202) 502–6123 or michael.watts@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC 61,076 (2001). k. Pursuant to section 4.32(b)(7) of the Commission’s regulations, if any VerDate Sep<11>2014 22:35 Oct 11, 2017 Jkt 244001 resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: November 20, 2017. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at http:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13371–002. m. This application is not ready for environmental analysis at this time. n. The proposed Shaker Mill Dam Hydroelectric Project would consists of: (1) An existing 43-foot-long, 16.3-foothigh concrete gravity dam that includes a 10-foot-wide non-overflow section and a 33-foot-long ogee spillway section with two discharge pipes, and a crest elevation of 895.3 feet mean sea level (msl); (2) existing east and west concrete abutments; (3) existing east and west masonry training walls that extend downstream of the dam; (4) an existing 32.3-acre impoundment with a normal water surface elevation of 895.3 feet msl; (5) an intake structure that includes an existing 12-inch-diameter gate opening and a proposed 24-inchdiameter gate opening; (6) a proposed powerhouse with a 3-kilowatt (kW) Kaplan turbine-generator unit and a 6kW Kaplan turbine-generator unit, for a total installed capacity of 9 kW; (7) two proposed draft tubes to discharge water from the powerhouse; and (8) appurtenant facilities. West Stockbridge proposes to operate the project in a run-of-river mode with an estimated annual energy production of approximately 67.5 megawatt-hours. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at http://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the PO 00000 Frm 00053 Fmt 4703 Sfmt 4703 document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at http:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate (e.g., if there are no deficiencies and/or scoping is waived, the schedule would be shortened). Issue Deficiency Letter—November 2017. Issue Notice of Acceptance—March 2018. Issue Scoping Document—April 2018. Issue Notice of Ready for Environmental Analysis—June 2018. Issue Notice of the Availability of the EA—October 2018. Dated: October 5, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–22010 Filed 10–11–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP17–56–000, CP17–57–000] Texas Eastern Transmission, L.P.; Brazoria Interconnector Gas Pipeline, LLC; Notice of Availability of the Environmental Assessment for the Proposed Stratton Ridge Expansion Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Stratton Ridge Expansion Project (Project), proposed by Texas Eastern Transmission, L.P. and Brazoria Interconnector Gas Pipeline, LLC (together referred to as Applicants) in the above-referenced dockets. The Applicants request authorization to construct certain facilities designed to transport up to 322 million cubic feet per day of natural gas on a firm basis from Texas Eastern Transmission, L.P.’s existing interconnections to a delivery point on the Brazoria Interconnector Gas Pipeline near Stratton Ridge, Texas. The EA assesses the potential environmental effects of the E:\FR\FM\12OCN1.SGM 12OCN1

Agencies

[Federal Register Volume 82, Number 196 (Thursday, October 12, 2017)]
[Notices]
[Page 47498]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-22010]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13371-002]


Town of West Stockbridge; Notice of Application Tendered for 
Filing With the Commission and Soliciting Additional Study Requests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Exemption from Licensing.
    b. Project No.: 13371-002.
    c. Date Filed: September 21, 2017.
    d. Applicant: Town of West Stockbridge (West Stockbridge).
    e. Name of Project: Shaker Mill Dam Hydroelectric Project.
    f. Location: On the Williams River, in the Town of West 
Stockbridge, Berkshire County, Massachusetts. No federal or tribal 
lands would be occupied by project works or located within the project 
boundary.
    g. Filed Pursuant to: Public Utility Regulatory Policies Act of 
1978, 16 U.S.C. 2705, 2708 (2012), amended by the Hydropower Regulatory 
Efficiency Act of 2013, Public Law 113-23, 127 Stat. 493 (2013).
    h. Applicant Contact: Town of West Stockbridge, c/o Earl B. 
Moffatt, Chairman, Board of Selectmen, 21 State Line Rd., P.O. Box 525, 
West Stockbridge, MA 01266; (413) 232-0300, extension 319.
    i. FERC Contact: Michael Watts, (202) 502-6123 or 
michael.watts@ferc.gov.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of the Commission's regulations, 
if any resource agency, Indian Tribe, or person believes that an 
additional scientific study should be conducted in order to form an 
adequate factual basis for a complete analysis of the application on 
its merit, the resource agency, Indian Tribe, or person must file a 
request for a study with the Commission not later than 60 days from the 
date of filing of the application, and serve a copy of the request on 
the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: November 20, 2017.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-13371-002.
    m. This application is not ready for environmental analysis at this 
time.
    n. The proposed Shaker Mill Dam Hydroelectric Project would 
consists of: (1) An existing 43-foot-long, 16.3-foot-high concrete 
gravity dam that includes a 10-foot-wide non-overflow section and a 33-
foot-long ogee spillway section with two discharge pipes, and a crest 
elevation of 895.3 feet mean sea level (msl); (2) existing east and 
west concrete abutments; (3) existing east and west masonry training 
walls that extend downstream of the dam; (4) an existing 32.3-acre 
impoundment with a normal water surface elevation of 895.3 feet msl; 
(5) an intake structure that includes an existing 12-inch-diameter gate 
opening and a proposed 24-inch-diameter gate opening; (6) a proposed 
powerhouse with a 3-kilowatt (kW) Kaplan turbine-generator unit and a 
6-kW Kaplan turbine-generator unit, for a total installed capacity of 9 
kW; (7) two proposed draft tubes to discharge water from the 
powerhouse; and (8) appurtenant facilities.
    West Stockbridge proposes to operate the project in a run-of-river 
mode with an estimated annual energy production of approximately 67.5 
megawatt-hours.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate (e.g., if there are no 
deficiencies and/or scoping is waived, the schedule would be 
shortened).
    Issue Deficiency Letter--November 2017.
    Issue Notice of Acceptance--March 2018.
    Issue Scoping Document--April 2018.
    Issue Notice of Ready for Environmental Analysis--June 2018.
    Issue Notice of the Availability of the EA--October 2018.

    Dated: October 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-22010 Filed 10-11-17; 8:45 am]