Notice of Schedule for Environmental Review of the Proposed Marshall County Mine Panel 18w Project; Texas Eastern Transmission, LP, 47504 [2017-22002]

Download as PDF 47504 Federal Register / Vol. 82, No. 196 / Thursday, October 12, 2017 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–468–000] Notice of Schedule for Environmental Review of the Proposed Marshall County Mine Panel 18w Project; Texas Eastern Transmission, LP On June 30, 2017, Texas Eastern Transmission, LP filed an application in Docket No. CP17–468–000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project is known as the as Marshall County Mine Panel 18W Project (Project), and would excavate and elevate sections of four existing mainline pipelines to minimize and monitor potential strains on the pipelines due to anticipated longwall mining activities. On July 13, 2017, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s Environmental Assessment (EA) for the Project. This instant notice identifies the FERC staff’s planned schedule for the completion of the EA for the Project. asabaliauskas on DSKBBXCHB2PROD with NOTICES Schedule for Environmental Review Issuance of EA—December 21, 2017 90-day Federal Authorization Decision Deadline—March 21, 2018 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Project Description Texas Eastern proposes to excavate and elevate 1.6-mile-long sections each of its Line 10, Line 15, Line 30, and a 1.5-mile-long section of its Line 25 to minimize and monitor potential strains on the pipelines due to anticipated longwall mining activities of Marshall Coal. Concurrent with pipeline elevation, portions of two of the lines, Lines 10 and 15, would be replaced with new pipe. Texas Eastern will also perform maintenance activities on sections of Lines 25 and 30. The four mainline sections will be returned to natural gas service while remaining elevated using sandbags and skids VerDate Sep<11>2014 22:35 Oct 11, 2017 Jkt 244001 during the longwall mining activities and potential ground subsidence. Once the mining-induced subsidence and the 2017–2018 heating season have both ended, the two sections of pipeline located within wetlands will be removed and the four elevated pipeline sections will be re-installed belowground, hydrostatically tested, and placed back into service. Background On July 24, 2017, the Commission issued a Notice of Intent to Prepare an Environmental Assessment for the Proposed Marshall County Mine Panel 18W Project and Request for Comments on Environmental Issues (NOI). The NOI was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. The Commission did not received any comments in response to the NOI. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC Web site (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–468), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ ferc.gov. The eLibrary link on the FERC Web site also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: October 5, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–22002 Filed 10–11–17; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00059 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG18–2–000. Applicants: NTE Carolinas II, LLC. Description: Self-Certification of Exempt Wholesale Generator Status of NTE Carolinas II, LLC. Filed Date: 10/4/17. Accession Number: 20171004–5155. Comments Due: 5 p.m. ET 10/25/17. Docket Numbers: EG18–3–000. Applicants: Bladen Solar, LLC. Description: Self-Certification of Exempt Wholesale Generator Status of Bladen Solar, LLC. Filed Date: 10/5/17. Accession Number: 20171005–5005. Comments Due: 5 p.m. ET 10/26/17. Docket Numbers: EG18–4–000. Applicants: Bullock Solar, LLC. Description: Self-Certification of Exempt Wholesale Generator Status of Bullock Solar, LLC. Filed Date: 10/5/17. Accession Number: 20171005–5006. Comments Due: 5 p.m. ET 10/26/17. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER18–26–000. Applicants: Southwestern Electric Power Company. Description: § 205(d) Rate Filing: SWEPCO–NTEC Hallsville S. Tap to Gum Springs DPA to be effective 9/11/ 2017. Filed Date: 10/4/17. Accession Number: 20171004–5139. Comments Due: 5 p.m. ET 10/25/17. Docket Numbers: ER18–27–000. Applicants: Thunder Ranch Wind Project, LLC. Description: Baseline eTariff Filing: Thunder Ranch Wind Project, LLC MBR Tariff to be effective 11/1/2017. Filed Date: 10/4/17. Accession Number: 20171004–5154. Comments Due: 5 p.m. ET 10/25/17. Docket Numbers: ER18–28–000. Applicants: Duke Energy Florida, LLC. Description: § 205(d) Rate Filing: DEF Bartow NITSA Update to be effective 1/ 1/2018. Filed Date: 10/5/17. Accession Number: 20171005–5003. Comments Due: 5 p.m. ET 10/26/17. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. E:\FR\FM\12OCN1.SGM 12OCN1

Agencies

[Federal Register Volume 82, Number 196 (Thursday, October 12, 2017)]
[Notices]
[Page 47504]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-22002]



[[Page 47504]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-468-000]


Notice of Schedule for Environmental Review of the Proposed 
Marshall County Mine Panel 18w Project; Texas Eastern Transmission, LP

    On June 30, 2017, Texas Eastern Transmission, LP filed an 
application in Docket No. CP17-468-000 requesting a Certificate of 
Public Convenience and Necessity pursuant to Section 7(c) of the 
Natural Gas Act to construct and operate certain natural gas pipeline 
facilities. The proposed project is known as the as Marshall County 
Mine Panel 18W Project (Project), and would excavate and elevate 
sections of four existing mainline pipelines to minimize and monitor 
potential strains on the pipelines due to anticipated longwall mining 
activities.
    On July 13, 2017, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA--December 21, 2017
90-day Federal Authorization Decision Deadline--March 21, 2018

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Texas Eastern proposes to excavate and elevate 1.6-mile-long 
sections each of its Line 10, Line 15, Line 30, and a 1.5-mile-long 
section of its Line 25 to minimize and monitor potential strains on the 
pipelines due to anticipated longwall mining activities of Marshall 
Coal. Concurrent with pipeline elevation, portions of two of the lines, 
Lines 10 and 15, would be replaced with new pipe. Texas Eastern will 
also perform maintenance activities on sections of Lines 25 and 30. The 
four mainline sections will be returned to natural gas service while 
remaining elevated using sandbags and skids during the longwall mining 
activities and potential ground subsidence. Once the mining-induced 
subsidence and the 2017-2018 heating season have both ended, the two 
sections of pipeline located within wetlands will be removed and the 
four elevated pipeline sections will be re-installed belowground, 
hydrostatically tested, and placed back into service.

Background

    On July 24, 2017, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Marshall County 
Mine Panel 18W Project and Request for Comments on Environmental Issues 
(NOI). The NOI was sent to affected landowners; federal, state, and 
local government agencies; elected officials; environmental and public 
interest groups; Native American tribes; other interested parties; and 
local libraries and newspapers. The Commission did not received any 
comments in response to the NOI.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-468), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC Web site also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: October 5, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-22002 Filed 10-11-17; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.