Clean River Power MR-2, LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene and Protest, 43348-43349 [2017-19567]

Download as PDF 43348 Federal Register / Vol. 82, No. 178 / Friday, September 15, 2017 / Notices link. Click on the eLibrary link, click on General Search and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP17– 481). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. NYISO Operating Committee Meeting DEPARTMENT OF ENERGY September 15, 2017, 10:00 a.m.–4:00 p.m. (EST) Federal Energy Regulatory Commission Dated: September 6, 2017. Kimberly D. Bose, Secretary. September 27, 2017, 10:00 a.m.–4:00 p.m. (EST) [FR Doc. 2017–19561 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Commission Staff Attendance The Federal Energy Regulatory Commission (Commission) hereby gives notice that members of the Commission’s staff may attend the following meetings related to the transmission planning activities of the New York Independent System Operator, Inc. (NYISO): NYISO Business Issues Committee Meeting mstockstill on DSK30JT082PROD with NOTICES September 12, 2017, 10:00 a.m.–4:00 p.m. (EST) The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents .jsp?com=bic&directory=2017-09-12. VerDate Sep<11>2014 17:07 Sep 14, 2017 Jkt 241001 The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents. jsp?com=oc&directory=2017-09-15. NYISO Electric System Planning Working Group Meeting September 26, 2017, 10:00 a.m.–4:00 p.m. (EST) The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents.jsp?com=bic_ espwg&directory=2017-09-26. NYISO Management Committee Meeting The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/ documents.jsp?com=mc&directory =2017-09-27. The discussions at the meetings described above may address matters at issue in the following proceedings: New York Independent System Operator, Inc., Docket No. ER13–102. New York Independent System Operator, Inc., Docket No. ER15–2059. New York Transco, LLC, Docket No. ER15–572. For more information, contact James Eason, Office of Energy Market Regulation, Federal Energy Regulatory Commission at (202) 502–8622 or James.Eason@ferc.gov. Dated: September 5, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–19562 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 [Project No. P–13407–004] Clean River Power MR–2, LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene and Protest Take notice that the following hydroelectric applications have been filed with the Commission and are available for public inspection. a. Type of Applications: Amendment of License. b. Project No.: 13407–004. c. Date filed: May 23, 2017. d. Applicant: Clean River Power MR– 2, LLC, a subsidiary of Free Flow Power Corporation. e. Name of Project: Lowell Lock and Dam Water Power Project. f. Location: The proposed project would be located at the existing Lowell Lock and Dam on the Muskingum River in Washington County, West of the City of Lowell, Ohio. The lock and dam was formally owned and operated by the U.S. Army Corps of Engineers, but is currently owned and operated by the Ohio Department of Natural Resources, Division of Parks and Recreation. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contacts: Ramya Swaminathan, Chief Operating Officer, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; (978) 283–2822, or by email at: Ramya@ryedevelopment.com. i. FERC Contact: M. Joseph Fayyad (202) 502–8759, or by email at mo.fayyad@ferc.gov. j. Deadline for filing comments, motions to intervene and protests is 30 days from the issuance of this notice by the Commission. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/doc-sfiling/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. E:\FR\FM\15SEN1.SGM 15SEN1 mstockstill on DSK30JT082PROD with NOTICES Federal Register / Vol. 82, No. 178 / Friday, September 15, 2017 / Notices The first page of any filing should include docket number P–13407–004. k. Description of currently authorized project: The authorized but unconstructed project works consist of: (a) An existing 840-foot-long, 18-foothigh timber crib and concrete dam that contains a full-length, uncontrolled spillway having a crest elevation of 607.06 feet North American Vertical Datum of 1988; (b) an existing 628-acre impoundment with a volume of 4,492 acre-feet at the crest elevation of the dam; (c) a new 215-foot-long by 165foot-wide by 23-foot-deep intake channel to be excavated upstream of the dam to convey flows to be used for generation into the powerhouse; (d) a new 37-foot-long by 80-foot-wide by 52foot-high intake structure equipped with trashracks containing 2-inch clear bar spacing; (e) a new 160-foot-long by 75foot-wide by 66-foot-high concrete powerhouse located immediately downstream of the dam on the north river bank containing two 2.5-megawatt horizontal Kaplan turbine/generator units; (f) a new 143.5-foot-long dam abutment located adjacent to the powerhouse to serve as an overflow weir to maintain the existing overflow capacity of the dam; (g) a new 100-footlong by 125-foot-wide by 24-foot-deep tailrace channel located immediately downstream of the powerhouse to return flows exiting the powerhouse to the Muskingum River; (h) a new 40-footlong by 40-foot-wide substation located adjacent to the north end of the dam; (i) a new 135-foot-long, 4.16-kilovolt (kV) transmission cable that connects the powerhouse to the substation; (j) a new 1,200-foot-long, 69-kV overhead transmission line that connects the substation to a local utility distribution line; (k) a new 150-foot-long access road and a new 1,800-square-foot parking lot located at the south end of the dam; and (l) appurtenant facilities. l. Description of Amendment: The licensee proposes certain design changes to the project’s works as follows: (1) Change the location of the project works form the north side to the south side of the dam; (2) the tailrace channel will be 255-foot-long by 170foot-wide by 28-foot-deep; and (3) the transmission line will be a 150-footlong, 4.16-kV transmission line that connects the powerhouse to the substation and a 2,375-foot-long, 69-kV transmission line that connects the substation to the local utility distribution line. Most of the 69-kV transmission line will be submerged behind the dam. m. Location of the Application: A copy of the application is available for inspection and reproduction at the VerDate Sep<11>2014 17:07 Sep 14, 2017 Jkt 241001 Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. The filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. n. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. o. Comments, Motions to Intervene, or Protests: Anyone may submit comments, a motion to intervene, or a protest in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, motions to intervene, or protests must be received on or before the specified comment date for the particular application. p. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘MOTION TO INTERVENE’’, or ‘‘PROTEST’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervener must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 43349 Dated: September 7, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–19567 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. RM01–5–000] Electronic Tariff Filings; Notice Regarding Footnotes, Headers, or Footers in Tariff Text in the Commission’s E-Tariff System Take notice that the Commission’s electronic tariff system (eTariff) does not reproduce footnotes, headers, or footers in the Real-Text-Format (RTF) tariff text posted on the Commission’s Web site (https://etariff.ferc.gov/TariffList.aspx).1 To the extent footnotes, headers or footers are needed in tariff text, filers should enter them separately in the body of the document on each page where needed rather than by using automatic features of the word processing program. Dated: September 6, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–19563 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–491–000] Perryville Gas Storage LLC; Notice of Application Take notice that on June 23, 2017, Perryville Gas Storage LLC (Perryville), having its principal place of business at Three Riverway, Suite 1350, Houston, Texas 77056, filed in the above referenced docket an application pursuant to section 7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission’s regulations for an order amending the certificate of public convenience and necessity issued in Docket No. CP09–418–000, and amended in Docket Nos. CP11–159–000, CP12–460–000 and CP13–23–000, to authorize Perryville to make certain 1 This applies to footnotes created programmatically by the word processing software, such as the Insert Footnote Tool in Microsoft Word, and text added to the header or footer areas of a document, such as using the Insert Header or Footer Tool in Microsoft Word or clicking in the header or footer areas of the document. E:\FR\FM\15SEN1.SGM 15SEN1

Agencies

[Federal Register Volume 82, Number 178 (Friday, September 15, 2017)]
[Notices]
[Pages 43348-43349]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-19567]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. P-13407-004]


Clean River Power MR-2, LLC; Notice of Application Accepted for 
Filing and Soliciting Comments, Motions To Intervene and Protest

    Take notice that the following hydroelectric applications have been 
filed with the Commission and are available for public inspection.
    a. Type of Applications: Amendment of License.
    b. Project No.: 13407-004.
    c. Date filed: May 23, 2017.
    d. Applicant: Clean River Power MR-2, LLC, a subsidiary of Free 
Flow Power Corporation.
    e. Name of Project: Lowell Lock and Dam Water Power Project.
    f. Location: The proposed project would be located at the existing 
Lowell Lock and Dam on the Muskingum River in Washington County, West 
of the City of Lowell, Ohio. The lock and dam was formally owned and 
operated by the U.S. Army Corps of Engineers, but is currently owned 
and operated by the Ohio Department of Natural Resources, Division of 
Parks and Recreation.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
    h. Applicant Contacts: Ramya Swaminathan, Chief Operating Officer, 
Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 
02114; (978) 283-2822, or by email at: Ramya@ryedevelopment.com.
    i. FERC Contact: M. Joseph Fayyad (202) 502-8759, or by email at 
mo.fayyad@ferc.gov.
    j. Deadline for filing comments, motions to intervene and protests 
is 30 days from the issuance of this notice by the Commission. The 
Commission strongly encourages electronic filing. Please file comments, 
motions to intervene, and protests using the Commission's eFiling 
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/doc-sfiling/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please 
send a paper copy to: Secretary, Federal Energy Regulatory Commission, 
888 First Street NE., Washington, DC 20426.

[[Page 43349]]

The first page of any filing should include docket number P-13407-004.
    k. Description of currently authorized project: The authorized but 
unconstructed project works consist of: (a) An existing 840-foot-long, 
18-foot-high timber crib and concrete dam that contains a full-length, 
uncontrolled spillway having a crest elevation of 607.06 feet North 
American Vertical Datum of 1988; (b) an existing 628-acre impoundment 
with a volume of 4,492 acre-feet at the crest elevation of the dam; (c) 
a new 215-foot-long by 165-foot-wide by 23-foot-deep intake channel to 
be excavated upstream of the dam to convey flows to be used for 
generation into the powerhouse; (d) a new 37-foot-long by 80-foot-wide 
by 52-foot-high intake structure equipped with trashracks containing 2-
inch clear bar spacing; (e) a new 160-foot-long by 75-foot-wide by 66-
foot-high concrete powerhouse located immediately downstream of the dam 
on the north river bank containing two 2.5-megawatt horizontal Kaplan 
turbine/generator units; (f) a new 143.5-foot-long dam abutment located 
adjacent to the powerhouse to serve as an overflow weir to maintain the 
existing overflow capacity of the dam; (g) a new 100-foot-long by 125-
foot-wide by 24-foot-deep tailrace channel located immediately 
downstream of the powerhouse to return flows exiting the powerhouse to 
the Muskingum River; (h) a new 40-foot-long by 40-foot-wide substation 
located adjacent to the north end of the dam; (i) a new 135-foot-long, 
4.16-kilovolt (kV) transmission cable that connects the powerhouse to 
the substation; (j) a new 1,200-foot-long, 69-kV overhead transmission 
line that connects the substation to a local utility distribution line; 
(k) a new 150-foot-long access road and a new 1,800-square-foot parking 
lot located at the south end of the dam; and (l) appurtenant 
facilities.
    l. Description of Amendment: The licensee proposes certain design 
changes to the project's works as follows: (1) Change the location of 
the project works form the north side to the south side of the dam; (2) 
the tailrace channel will be 255-foot-long by 170-foot-wide by 28-foot-
deep; and (3) the transmission line will be a 150-foot-long, 4.16-kV 
transmission line that connects the powerhouse to the substation and a 
2,375-foot-long, 69-kV transmission line that connects the substation 
to the local utility distribution line. Most of the 69-kV transmission 
line will be submerged behind the dam.
    m. Location of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. The filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above. Agencies may obtain copies of the application directly from 
the applicant.
    n. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    o. Comments, Motions to Intervene, or Protests: Anyone may submit 
comments, a motion to intervene, or a protest in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
and .214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, motions to 
intervene, or protests must be received on or before the specified 
comment date for the particular application.
    p. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``MOTION TO 
INTERVENE'', or ``PROTEST'' as applicable; (2) set forth in the heading 
the name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervener must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: September 7, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-19567 Filed 9-14-17; 8:45 am]