DCP Operating Company, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Mewbourn 3 Residue East Pipeline, and Request for Comments on Environmental Issues, 43346-43348 [2017-19561]

Download as PDF mstockstill on DSK30JT082PROD with NOTICES 43346 Federal Register / Vol. 82, No. 178 / Friday, September 15, 2017 / Notices to, local policy objectives and local electricity system fundamentals. 4. Fundamental drivers and underlying market conditions—identify key drivers that establish the context for the values and cause differing outcomes among studies of cost/benefit results in a particular category, such as differing levels of excess generation capacity, transmission, or distribution system capacity, projected demand growth, level of penetration and location of distributed generation, retail prices, etc. 5. Are there specific emerging issues related to net metering cost-benefit analyses that are improving or complicating the application of benefitcost analysis? The following items are considered out of scope of the report and information on these items should not be included in the responses: 1. Costs and benefits of distributed solar generation beyond distributed solar’s impact on net metering; 2. Indirect cost/benefits (e.g., societal impacts, network effects) that go beyond what is included in existing analyses; 3. Recommendations on a. How to conduct cost/benefit analysis, b. NEM design options, c. Transitions to alternative forms of compensation. All interested parties are invited to submit in writing by the date specified in the DATES section of this RFI, comments and information on all elements listed in this SUPPLEMENTARY section. Please submit comments only and cite docket number EERE–2017– OT–0056, in all correspondence related to this case. All comments received will be posted without change to https:// www.regulations.gov, including any personal and/or business confidential information provided. Do not submit to the RFI information for which disclosure is restricted by statute, such as trade secrets and commercial or financial information (hereinafter referred to as Confidential Business Information (CBI)). Comments submitted to the RFI email address cannot be claimed as CBI. Comments received through the RFI address will waive any CBI claims for the information submitted. DOE plans to publish all information received in response to this RFI. Issued in Washington, DC, on September 12, 2017. Sean Cunningham, Director, Office of Energy Policy and Systems Analysis, U.S. Department of Energy. [FR Doc. 2017–19647 Filed 9–14–17; 8:45 am] BILLING CODE 6450–01–P VerDate Sep<11>2014 17:07 Sep 14, 2017 Jkt 241001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–481–000] DCP Operating Company, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Mewbourn 3 Residue East Pipeline, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Mewbourn 3 Residue East Pipeline involving construction and operation of facilities by DCP Operating Company, LP (DCP) in Weld County, Colorado. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before October 6, 2017. If you sent comments on this project to the Commission before the opening of this docket on August 2, 2017, you will need to file those comments in Docket No. CP17–481–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. DCP provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Public Participation For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’ as the filing type; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP17–481– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Summary of the Proposed Project DCP proposes to construct and operate 8.4 miles of new 20-inchdiameter pipeline in Weld County, Colorado. The Mewbourn 3 Residue East Pipeline Project would provide about 253,000 dekatherms of natural gas per day to an interconnect with Colorado Interstate Gas Company L.L.C.’s High Plains System. According to DCP, its project would transport E:\FR\FM\15SEN1.SGM 15SEN1 Federal Register / Vol. 82, No. 178 / Friday, September 15, 2017 / Notices natural gas from DCP’s Mewbourne Processing Plant Complex to support further transportation and market needs in Colorado and other states in the region. The Mewbourn 3 Residue East Pipeline Project would consist of the following facilities: • 8.4 miles of new 20-inch-diameter pipeline; and • pig launcher and receiver assembly,1 cathodic protection rectifier unit, three mainline valves, and a metering station. The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the proposed facilities would disturb about 87.4 acres of land for the aboveground facilities and the pipeline. Following construction, DCP would maintain about 32.3 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. The EA Process mstockstill on DSK30JT082PROD with NOTICES The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 3 to discover and address concerns the public may have about proposals. This process is referred to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; 1 A pig is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 3 We, us, and our refer to the environmental staff of the Commission’s Office of Energy Projects. VerDate Sep<11>2014 17:07 Sep 14, 2017 Jkt 241001 • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; • public safety; and • cumulative impacts. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the Colorado State Historic Preservation Office (SHPO), and to solicit its views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 43347 construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies of the EA will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the Document-less Intervention Guide under the e-filing link on the Commission’s Web site. Motions to intervene are more fully described at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the eLibrary E:\FR\FM\15SEN1.SGM 15SEN1 43348 Federal Register / Vol. 82, No. 178 / Friday, September 15, 2017 / Notices link. Click on the eLibrary link, click on General Search and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP17– 481). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Finally, public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. NYISO Operating Committee Meeting DEPARTMENT OF ENERGY September 15, 2017, 10:00 a.m.–4:00 p.m. (EST) Federal Energy Regulatory Commission Dated: September 6, 2017. Kimberly D. Bose, Secretary. September 27, 2017, 10:00 a.m.–4:00 p.m. (EST) [FR Doc. 2017–19561 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Commission Staff Attendance The Federal Energy Regulatory Commission (Commission) hereby gives notice that members of the Commission’s staff may attend the following meetings related to the transmission planning activities of the New York Independent System Operator, Inc. (NYISO): NYISO Business Issues Committee Meeting mstockstill on DSK30JT082PROD with NOTICES September 12, 2017, 10:00 a.m.–4:00 p.m. (EST) The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents .jsp?com=bic&directory=2017-09-12. VerDate Sep<11>2014 17:07 Sep 14, 2017 Jkt 241001 The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents. jsp?com=oc&directory=2017-09-15. NYISO Electric System Planning Working Group Meeting September 26, 2017, 10:00 a.m.–4:00 p.m. (EST) The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/documents.jsp?com=bic_ espwg&directory=2017-09-26. NYISO Management Committee Meeting The above-referenced meeting will be via web conference and teleconference. The above-referenced meeting is open to stakeholders. Further information may be found at: https://www.nyiso.com/public/ committees/ documents.jsp?com=mc&directory =2017-09-27. The discussions at the meetings described above may address matters at issue in the following proceedings: New York Independent System Operator, Inc., Docket No. ER13–102. New York Independent System Operator, Inc., Docket No. ER15–2059. New York Transco, LLC, Docket No. ER15–572. For more information, contact James Eason, Office of Energy Market Regulation, Federal Energy Regulatory Commission at (202) 502–8622 or James.Eason@ferc.gov. Dated: September 5, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–19562 Filed 9–14–17; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 [Project No. P–13407–004] Clean River Power MR–2, LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene and Protest Take notice that the following hydroelectric applications have been filed with the Commission and are available for public inspection. a. Type of Applications: Amendment of License. b. Project No.: 13407–004. c. Date filed: May 23, 2017. d. Applicant: Clean River Power MR– 2, LLC, a subsidiary of Free Flow Power Corporation. e. Name of Project: Lowell Lock and Dam Water Power Project. f. Location: The proposed project would be located at the existing Lowell Lock and Dam on the Muskingum River in Washington County, West of the City of Lowell, Ohio. The lock and dam was formally owned and operated by the U.S. Army Corps of Engineers, but is currently owned and operated by the Ohio Department of Natural Resources, Division of Parks and Recreation. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contacts: Ramya Swaminathan, Chief Operating Officer, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114; (978) 283–2822, or by email at: Ramya@ryedevelopment.com. i. FERC Contact: M. Joseph Fayyad (202) 502–8759, or by email at mo.fayyad@ferc.gov. j. Deadline for filing comments, motions to intervene and protests is 30 days from the issuance of this notice by the Commission. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/doc-sfiling/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. E:\FR\FM\15SEN1.SGM 15SEN1

Agencies

[Federal Register Volume 82, Number 178 (Friday, September 15, 2017)]
[Notices]
[Pages 43346-43348]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-19561]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-481-000]


DCP Operating Company, LP; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Mewbourn 3 Residue East 
Pipeline, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Mewbourn 3 Residue East 
Pipeline involving construction and operation of facilities by DCP 
Operating Company, LP (DCP) in Weld County, Colorado. The Commission 
will use this EA in its decision-making process to determine whether 
the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before October 6, 2017.
    If you sent comments on this project to the Commission before the 
opening of this docket on August 2, 2017, you will need to file those 
comments in Docket No. CP17-481-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    DCP provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or FercOnlineSupport@ferc.gov. Please carefully follow 
these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
eRegister. If you are filing a comment on a particular project, please 
select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP17-481-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    DCP proposes to construct and operate 8.4 miles of new 20-inch-
diameter pipeline in Weld County, Colorado. The Mewbourn 3 Residue East 
Pipeline Project would provide about 253,000 dekatherms of natural gas 
per day to an interconnect with Colorado Interstate Gas Company 
L.L.C.'s High Plains System. According to DCP, its project would 
transport

[[Page 43347]]

natural gas from DCP's Mewbourne Processing Plant Complex to support 
further transportation and market needs in Colorado and other states in 
the region.
    The Mewbourn 3 Residue East Pipeline Project would consist of the 
following facilities:
     8.4 miles of new 20-inch-diameter pipeline; and
     pig launcher and receiver assembly,\1\ cathodic protection 
rectifier unit, three mainline valves, and a metering station.
---------------------------------------------------------------------------

    \1\ A pig is a tool that the pipeline company inserts into and 
pushes through the pipeline for cleaning the pipeline, conducting 
internal inspections, or other purposes.
---------------------------------------------------------------------------

    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 87.4 
acres of land for the aboveground facilities and the pipeline. 
Following construction, DCP would maintain about 32.3 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ We, us, and our refer to the environmental staff of the 
Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:

     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety; and
     cumulative impacts.

    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Colorado State Historic Preservation Office (SHPO), and to 
solicit its views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\5\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the Document-less Intervention Guide under the e-filing link on the 
Commission's Web site. Motions to intervene are more fully described at 
https://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the eLibrary

[[Page 43348]]

link. Click on the eLibrary link, click on General Search and enter the 
docket number, excluding the last three digits in the Docket Number 
field (i.e., CP17-481). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public sessions or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: September 6, 2017.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2017-19561 Filed 9-14-17; 8:45 am]
 BILLING CODE 6717-01-P