Florida Gas Transmission Company, LLC; Notice of Schedule for Environmental Review of the East-West Project, 42670 [2017-19113]

Download as PDF 42670 Federal Register / Vol. 82, No. 174 / Monday, September 11, 2017 / Notices DEPARTMENT OF ENERGY Background DEPARTMENT OF ENERGY Federal Energy Regulatory Commission On December 19, 2016 the Commission issued a Notice of Intent to Prepare an Environmental Assessment for the Proposed East-West Project and Request for Comments on Environmental Issues (NOI). The NOI was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. In response to the NOI, the Commission received comments from one landowner and the Louisiana Department of Fisheries and Wildlife. The primary issues raised by the commentors are potential impacts on soils, wetlands, wildlife refuges, cultural resources, and the aging process/potential corrosion of the pipelines. Federal Energy Regulatory Commission [Docket No. CP17–8–000] Florida Gas Transmission Company, LLC; Notice of Schedule for Environmental Review of the EastWest Project On October 31, 2016 Florida Gas Transmission Company, LLC (FGT) filed an application in Docket No. CP17–8– 000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project is known as the East-West Project (Project), and would provide new capacity of 275 million cubic feet per day on FGT’s pipeline system in the western division to meet the demand for additional transportation and delivery of natural gas to the proposed Port Arthur—Motiva Meter and Regulator (M&R) Station and the Wilson—Coastal Bend M&R Station in Jefferson and Wharton Counties, Texas respectively. On November 9, 2016 the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s Environmental Assessment (EA) for the Project. This instant notice identifies the FERC staff’s planned schedule for the completion of the EA for the Project. Schedule for Environmental Review Issuance of EA, October 20, 2017 90-day Federal Authorization Decision Deadline, January 18, 2018 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. asabaliauskas on DSKBBXCHB2PROD with NOTICES Project Description FGT proposes to construct and operate about 13.3 miles of 12-inchdiameter lateral pipeline, about 12 miles 16-inch-diameter lateral and connection pipeline, and four new meter stations and auxiliary and appurtenant facilities in Wharton, Matagorda, Jefferson, and Orange Counties, Texas, and Calcasieu and Acadia Parishes, Louisiana. VerDate Sep<11>2014 16:34 Sep 08, 2017 Jkt 241001 Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC Web site (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–8), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ ferc.gov. The eLibrary link on the FERC Web site also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: September 1, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–19113 Filed 9–8–17; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 [Docket No. ER17–2377–000] GenOn Holdco 10, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding, of GenOn Holdco 10, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is September 25, 2017. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email E:\FR\FM\11SEN1.SGM 11SEN1

Agencies

[Federal Register Volume 82, Number 174 (Monday, September 11, 2017)]
[Notices]
[Page 42670]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-19113]



[[Page 42670]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-8-000]


Florida Gas Transmission Company, LLC; Notice of Schedule for 
Environmental Review of the East-West Project

    On October 31, 2016 Florida Gas Transmission Company, LLC (FGT) 
filed an application in Docket No. CP17-8-000 requesting a Certificate 
of Public Convenience and Necessity pursuant to Section 7(c) of the 
Natural Gas Act to construct and operate certain natural gas pipeline 
facilities. The proposed project is known as the East-West Project 
(Project), and would provide new capacity of 275 million cubic feet per 
day on FGT's pipeline system in the western division to meet the demand 
for additional transportation and delivery of natural gas to the 
proposed Port Arthur--Motiva Meter and Regulator (M&R) Station and the 
Wilson--Coastal Bend M&R Station in Jefferson and Wharton Counties, 
Texas respectively.
    On November 9, 2016 the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA, October 20, 2017
90-day Federal Authorization Decision Deadline, January 18, 2018
    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    FGT proposes to construct and operate about 13.3 miles of 12-inch-
diameter lateral pipeline, about 12 miles 16-inch-diameter lateral and 
connection pipeline, and four new meter stations and auxiliary and 
appurtenant facilities in Wharton, Matagorda, Jefferson, and Orange 
Counties, Texas, and Calcasieu and Acadia Parishes, Louisiana.

Background

    On December 19, 2016 the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed East-West Project 
and Request for Comments on Environmental Issues (NOI). The NOI was 
sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. In response to the NOI, the Commission received 
comments from one landowner and the Louisiana Department of Fisheries 
and Wildlife. The primary issues raised by the commentors are potential 
impacts on soils, wetlands, wildlife refuges, cultural resources, and 
the aging process/potential corrosion of the pipelines.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-8), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC Web site also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: September 1, 2017.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2017-19113 Filed 9-8-17; 8:45 am]
 BILLING CODE 6717-01-P