Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization, 42340-42341 [2017-18996]

Download as PDF 42340 Federal Register / Vol. 82, No. 172 / Thursday, September 7, 2017 / Notices Dated: September 1, 2017. Kim R. Ford, Deputy Assistant Secretary, Delegated the Duties of Assistant Secretary for Career, Technical, and Adult Education. [FR Doc. 2017–19004 Filed 9–6–17; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission mstockstill on DSK30JT082PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC17–167–000. Applicants: Shoreham Solar Commons LLC, Duke Energy Renewables Solar, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act and Request for Waivers and Expedited Action of Shoreham Solar Commons LLC, et al. Filed Date: 8/30/17. Accession Number: 20170830–5159. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: EC17–168–000. Applicants: Florida Power & Light Company. Description: Application for Approval of Acquisition of Transmission Assets Pursuant to Section 203 of the Federal Power Act and Request for Expedited Action of Florida Power & Light Company. Filed Date: 8/30/17. Accession Number: 20170830–5161. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: EC17–169–000. Applicants: Duke Energy Indiana, LLC. Description: Application for Authorization Under Section 203 for Duke Energy Indiana, LLC. Filed Date: 8/30/17. Accession Number: 20170830–5163. Comments Due: 5 p.m. ET 9/20/17. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2950–011. Applicants: Spruance Genco, LLC. Description: Notice of Non-Material Change in Status by Spruance Genco, LLC. Filed Date: 8/29/17. Accession Number: 20170829–5135. Comments Due: 5 p.m. ET 9/19/17. Docket Numbers: ER17–1756–000. Applicants: Midcontinent Independent System Operator, Inc., Ameren Illinois Company. Description: Ameren Services Company, on behalf of Ameren Illinois VerDate Sep<11>2014 17:42 Sep 06, 2017 Jkt 241001 Company submits tariff filing per 35.19a(b): Refund Report to be effective N/A. Filed Date: 8/30/17. Accession Number: 20170830–5174. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: ER17–2385–000. Applicants: Great Valley Solar 3, LLC. Description: Baseline eTariff Filing: Great Valley Solar 3, LLC Petition for Order Accepting Market-Based Rate Tariff to be effective 10/1/2017. Filed Date: 8/30/17. Accession Number: 20170830–5143. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: ER17–2386–000. Applicants: Great Bay Solar I, LLC. Description: Initial rate filing: Reactive Service to be effective 11/1/2017. Filed Date: 8/30/17. Accession Number: 20170830–5148. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: ER17–2387–000. Applicants: California Independent System Operator Corporation. Description: Sec. 205(d) Rate Filing: 2017–08–31 Transferred Frequency Response Agreement Bonneville Power Admin. to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5000. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2388–000. Applicants: Southwest Power Pool, Inc., Southwestern Public Service Company. Description: Joint Request for Limited Tariff Waiver of Southwestern Public Service Company, et al. Filed Date: 8/30/17. Accession Number: 20170830–5157. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: ER17–2389–000. Applicants: Midcontinent Independent System Operator, Inc. Description: Notice of Cancellation of Service Agreement No. 636 of Midcontinent Independent System Operator, Inc. Filed Date: 8/30/17. Accession Number: 20170830–5158. Comments Due: 5 p.m. ET 9/20/17. Docket Numbers: ER17–2390–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of WMPA No. 4749; Queue No. AC1–037 to be effective 10/30/2017. Filed Date: 8/31/17. Accession Number: 20170831–5034. Comments Due: 5 p.m. ET 9/21/17. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. PO 00000 Frm 00072 Fmt 4703 Sfmt 4703 Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 31, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–18940 Filed 9–6–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–487–000] Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization Take notice that on August 22, 2017, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, filed in Docket No. CP17–487–000 and pursuant to sections 157.205 and 157.208 of the Commission’s regulations, a prior notice under its blanket certificate issued in Docket No. CP83–76–000 requesting authorization to install facilities and appurtenances and to make other modifications (Crawford Counterstorage Project) at its existing Crawford Compressor Station, located in Fairfield County, Ohio. The project will increase the compression available for counterstorage at its existing Crawford Storage Field, located in Hocking and Fairfield Counties, Ohio, all as more fully set forth in the application, which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. E:\FR\FM\07SEN1.SGM 07SEN1 mstockstill on DSK30JT082PROD with NOTICES Federal Register / Vol. 82, No. 172 / Thursday, September 7, 2017 / Notices Columbia proposes to install one (1) Cat 3520/Ariel high-speed reciprocating compressor unit, rated at 1,480 horsepower. Additionally, Columbia proposes to designate as standby units two (2) existing Waukesha reciprocating compressor units, rated at 250 hp each (Units 2 and 3), which are currently utilized for counterstorage compression. The project will also involve the construction of a new compressor building, new dehydration system, new gas cooler, new separators and scrubbers, new control room building, and new station piping. The project will result in an increase in counterstorage compression of 980 hp. The certificated physical parameters of the Crawford Storage Field will remain unchanged by the proposed modifications. The estimated cost of the project is approximately $20 million. Any questions regarding this application should be directed to Robert D. Jackson, Manager, Certificates & Regulatory Administration, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, at (832) 320–5487 or FAX (832) 320–6487, or robert_jackson@ transcanada.com. Any person may, within 60 days after the issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention. Any person filing to intervene or the Commission’s staff may, pursuant to section 157.205 of the Commission’s Regulations under the Natural Gas Act (NGA) (18 CFR 157.205) file a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a VerDate Sep<11>2014 17:42 Sep 06, 2017 Jkt 241001 Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenter’s will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenter’s will not be required to serve copies of filed documents on all other parties. However, the non-party commentary, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (www.ferc.gov) under the e-Filing link. Persons unable to file electronically should submit original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time October 31, 2017. Dated: August 31, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–18996 Filed 9–6–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER17–2391–000. Applicants: Avista Corporation. Description: § 205(d) Rate Filing: Avista Corp OATT—Misc Revisions to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5082. PO 00000 Frm 00073 Fmt 4703 Sfmt 4703 42341 Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2392–000. Applicants: PacifiCorp. Description: § 205(d) Rate Filing: Pacificorp EIM MBR Application_ August 31 2017 to be effective 11/1/ 2017. Filed Date: 8/31/17. Accession Number: 20170831–5096. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2393–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2017–08–31 Transferred Frequency Response Agreement Grant County to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5113. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2394–000. Applicants: Nevada Power Company. Description: § 205(d) Rate Filing: Market-Based Rate Tariff NPC 08.31.17 to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5118. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2395–000. Applicants: Sierra Pacific Power Company. Description: § 205(d) Rate Filing: Market-Based Rate Tariff Volume No. 7 SPPC 08.31.17 to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5122. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2396–000. Applicants: Mid-Atlantic Interstate Transmission, LLC, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: MAIT submits Settlement Payment Agreement No. 4767 to be effective 8/8/ 2017. Filed Date: 8/31/17. Accession Number: 20170831–5134. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2397–000. Applicants: Public Service Company of Colorado. Description: § 205(d) Rate Filing: PSCo–PSCoES–LGIA–464–0.0.0 Filing to be effective 9/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5137. Comments Due: 5 p.m. ET 9/21/17. Docket Numbers: ER17–2398–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2017–08–31 Transferred Frequency Response Agreement Chelan County to be effective 11/1/2017. Filed Date: 8/31/17. Accession Number: 20170831–5141. Comments Due: 5 p.m. ET 9/21/17. E:\FR\FM\07SEN1.SGM 07SEN1

Agencies

[Federal Register Volume 82, Number 172 (Thursday, September 7, 2017)]
[Notices]
[Pages 42340-42341]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-18996]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-487-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization

    Take notice that on August 22, 2017, Columbia Gas Transmission, LLC 
(Columbia), 700 Louisiana Street, Suite 700, Houston, Texas 77002-2700, 
filed in Docket No. CP17-487-000 and pursuant to sections 157.205 and 
157.208 of the Commission's regulations, a prior notice under its 
blanket certificate issued in Docket No. CP83-76-000 requesting 
authorization to install facilities and appurtenances and to make other 
modifications (Crawford Counterstorage Project) at its existing 
Crawford Compressor Station, located in Fairfield County, Ohio. The 
project will increase the compression available for counterstorage at 
its existing Crawford Storage Field, located in Hocking and Fairfield 
Counties, Ohio, all as more fully set forth in the application, which 
is on file with the Commission and open to public inspection. The 
filing may also be viewed on the web at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.

[[Page 42341]]

    Columbia proposes to install one (1) Cat 3520/Ariel high-speed 
reciprocating compressor unit, rated at 1,480 horsepower. Additionally, 
Columbia proposes to designate as standby units two (2) existing 
Waukesha reciprocating compressor units, rated at 250 hp each (Units 2 
and 3), which are currently utilized for counterstorage compression. 
The project will also involve the construction of a new compressor 
building, new dehydration system, new gas cooler, new separators and 
scrubbers, new control room building, and new station piping. The 
project will result in an increase in counterstorage compression of 980 
hp. The certificated physical parameters of the Crawford Storage Field 
will remain unchanged by the proposed modifications. The estimated cost 
of the project is approximately $20 million.
    Any questions regarding this application should be directed to 
Robert D. Jackson, Manager, Certificates & Regulatory Administration, 
Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, 
Houston, Texas 77002-2700, at (832) 320-5487 or FAX (832) 320-6487, or 
robert_jackson@transcanada.com.
    Any person may, within 60 days after the issuance of the instant 
notice by the Commission, file pursuant to Rule 214 of the Commission's 
Procedural Rules (18 CFR 385.214) a motion to intervene or notice of 
intervention. Any person filing to intervene or the Commission's staff 
may, pursuant to section 157.205 of the Commission's Regulations under 
the Natural Gas Act (NGA) (18 CFR 157.205) file a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for protest. If a protest is filed and not 
withdrawn within 30 days after the time allowed for filing a protest, 
the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenter's will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenter's will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentary, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site (www.ferc.gov) under the e-Filing link. Persons unable to file 
electronically should submit original and 5 copies of the protest or 
intervention to the Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426.
    Comment Date: 5:00 p.m. Eastern Time October 31, 2017.

    Dated: August 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-18996 Filed 9-6-17; 8:45 am]
 BILLING CODE 6717-01-P