Combined Notice of Filings #2, 42341-42342 [2017-18941]
Download as PDF
mstockstill on DSK30JT082PROD with NOTICES
Federal Register / Vol. 82, No. 172 / Thursday, September 7, 2017 / Notices
Columbia proposes to install one (1)
Cat 3520/Ariel high-speed reciprocating
compressor unit, rated at 1,480
horsepower. Additionally, Columbia
proposes to designate as standby units
two (2) existing Waukesha reciprocating
compressor units, rated at 250 hp each
(Units 2 and 3), which are currently
utilized for counterstorage compression.
The project will also involve the
construction of a new compressor
building, new dehydration system, new
gas cooler, new separators and
scrubbers, new control room building,
and new station piping. The project will
result in an increase in counterstorage
compression of 980 hp. The certificated
physical parameters of the Crawford
Storage Field will remain unchanged by
the proposed modifications. The
estimated cost of the project is
approximately $20 million.
Any questions regarding this
application should be directed to Robert
D. Jackson, Manager, Certificates &
Regulatory Administration, Columbia
Gas Transmission, LLC, 700 Louisiana
Street, Suite 700, Houston, Texas
77002–2700, at (832) 320–5487 or FAX
(832) 320–6487, or robert_jackson@
transcanada.com.
Any person may, within 60 days after
the issuance of the instant notice by the
Commission, file pursuant to Rule 214
of the Commission’s Procedural Rules
(18 CFR 385.214) a motion to intervene
or notice of intervention. Any person
filing to intervene or the Commission’s
staff may, pursuant to section 157.205 of
the Commission’s Regulations under the
Natural Gas Act (NGA) (18 CFR 157.205)
file a protest to the request. If no protest
is filed within the time allowed
therefore, the proposed activity shall be
deemed to be authorized effective the
day after the time allowed for protest. If
a protest is filed and not withdrawn
within 30 days after the time allowed
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
VerDate Sep<11>2014
17:42 Sep 06, 2017
Jkt 241001
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (www.ferc.gov)
under the e-Filing link. Persons unable
to file electronically should submit
original and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time October 31, 2017.
Dated: August 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–18996 Filed 9–6–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER17–2391–000.
Applicants: Avista Corporation.
Description: § 205(d) Rate Filing:
Avista Corp OATT—Misc Revisions to
be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5082.
PO 00000
Frm 00073
Fmt 4703
Sfmt 4703
42341
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2392–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing:
Pacificorp EIM MBR Application_
August 31 2017 to be effective 11/1/
2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5096.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2393–000.
Applicants: California Independent
System Operator Corporation.
Description: § 205(d) Rate Filing:
2017–08–31 Transferred Frequency
Response Agreement Grant County to be
effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5113.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2394–000.
Applicants: Nevada Power Company.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff NPC 08.31.17
to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5118.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2395–000.
Applicants: Sierra Pacific Power
Company.
Description: § 205(d) Rate Filing:
Market-Based Rate Tariff Volume No. 7
SPPC 08.31.17 to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5122.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2396–000.
Applicants: Mid-Atlantic Interstate
Transmission, LLC, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
MAIT submits Settlement Payment
Agreement No. 4767 to be effective 8/8/
2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5134.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2397–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) Rate Filing:
PSCo–PSCoES–LGIA–464–0.0.0 Filing
to be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5137.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2398–000.
Applicants: California Independent
System Operator Corporation.
Description: § 205(d) Rate Filing:
2017–08–31 Transferred Frequency
Response Agreement Chelan County to
be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5141.
Comments Due: 5 p.m. ET 9/21/17.
E:\FR\FM\07SEN1.SGM
07SEN1
mstockstill on DSK30JT082PROD with NOTICES
42342
Federal Register / Vol. 82, No. 172 / Thursday, September 7, 2017 / Notices
Docket Numbers: ER17–2399–000.
Applicants: Entergy Arkansas, Inc.
Description: § 205(d) Rate Filing:
Revised EAI-Benton WDS Agreement to
be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5146.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2400–000.
Applicants: SP Butler Solar, LLC.
Description: Baseline eTariff Filing:
Application for MBR Authority and
Initial Baseline Tariff Filing to be
effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5153.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2401–000.
Applicants: SP Decatur Parkway
Solar, LLC.
Description: Baseline eTariff Filing:
Application for MBR Authority and
Initial Baseline Tariff Filing to be
effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5154.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17–2402–000.
Applicants: California Independent
System Operator Corporation.
Description: § 205(d) Rate Filing:
2017–08–31 Westerm O’Neill Generator
Scheduling Agreement to be effective
11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831–5155.
Comments Due: 5 p.m. ET 9/21/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
Dated: August 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Dated: August 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–18941 Filed 9–6–17; 8:45 am]
[FR Doc. 2017–18942 Filed 9–6–17; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:42 Sep 06, 2017
Jkt 241001
[Docket No. ER17–2385–000]
[Docket No. EF17–5–000]
Southeastern Power Administration;
Notice of Filing
Take notice that on August 29, 2017,
Southeastern Power Administration
submitted tariff filing per: GeorgiaAlabama-South Carolina System 2017
Rate Adjustment to be effective 10/1/
2017.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the eLibrary
link and is available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please
email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on September 28, 2017.
PO 00000
Frm 00074
Fmt 4703
Sfmt 4703
Great Valley Solar 3, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Great
Valley Solar 3, LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is September
20, 2017.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
E:\FR\FM\07SEN1.SGM
07SEN1
Agencies
[Federal Register Volume 82, Number 172 (Thursday, September 7, 2017)]
[Notices]
[Pages 42341-42342]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-18941]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #2
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER17-2391-000.
Applicants: Avista Corporation.
Description: Sec. 205(d) Rate Filing: Avista Corp OATT--Misc
Revisions to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5082.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2392-000.
Applicants: PacifiCorp.
Description: Sec. 205(d) Rate Filing: Pacificorp EIM MBR
Application_August 31 2017 to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5096.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2393-000.
Applicants: California Independent System Operator Corporation.
Description: Sec. 205(d) Rate Filing: 2017-08-31 Transferred
Frequency Response Agreement Grant County to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5113.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2394-000.
Applicants: Nevada Power Company.
Description: Sec. 205(d) Rate Filing: Market-Based Rate Tariff NPC
08.31.17 to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5118.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2395-000.
Applicants: Sierra Pacific Power Company.
Description: Sec. 205(d) Rate Filing: Market-Based Rate Tariff
Volume No. 7 SPPC 08.31.17 to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5122.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2396-000.
Applicants: Mid-Atlantic Interstate Transmission, LLC, PJM
Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: MAIT submits Settlement
Payment Agreement No. 4767 to be effective 8/8/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5134.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2397-000.
Applicants: Public Service Company of Colorado.
Description: Sec. 205(d) Rate Filing: PSCo-PSCoES-LGIA-464-0.0.0
Filing to be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5137.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2398-000.
Applicants: California Independent System Operator Corporation.
Description: Sec. 205(d) Rate Filing: 2017-08-31 Transferred
Frequency Response Agreement Chelan County to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5141.
Comments Due: 5 p.m. ET 9/21/17.
[[Page 42342]]
Docket Numbers: ER17-2399-000.
Applicants: Entergy Arkansas, Inc.
Description: Sec. 205(d) Rate Filing: Revised EAI-Benton WDS
Agreement to be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5146.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2400-000.
Applicants: SP Butler Solar, LLC.
Description: Baseline eTariff Filing: Application for MBR Authority
and Initial Baseline Tariff Filing to be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5153.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2401-000.
Applicants: SP Decatur Parkway Solar, LLC.
Description: Baseline eTariff Filing: Application for MBR Authority
and Initial Baseline Tariff Filing to be effective 9/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5154.
Comments Due: 5 p.m. ET 9/21/17.
Docket Numbers: ER17-2402-000.
Applicants: California Independent System Operator Corporation.
Description: Sec. 205(d) Rate Filing: 2017-08-31 Westerm O'Neill
Generator Scheduling Agreement to be effective 11/1/2017.
Filed Date: 8/31/17.
Accession Number: 20170831-5155.
Comments Due: 5 p.m. ET 9/21/17.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: August 31, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-18941 Filed 9-6-17; 8:45 am]