2015). I have ordered that Public Notice
of these determinations be published in
the Federal Register.
Alyson Grunder,
Deputy Assistant Secretary for Policy, Bureau
of Educational and Cultural Affairs,
Department of State.
[FR Doc. 2017–18821 Filed 9–5–17; 8:45 am]
BILLING CODE 4710–05–P
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
Notice of Modification to Previously
Published Notice of Intent To Prepare
an Environmental Assessment
Federal Aviation
Administration (FAA), DOT.
ACTION: Notice.
AGENCY:
The FAA is publishing this
notice to advise the public of a
modification to the Notice of Intent to
Prepare an Environmental Assessment
(EA) and notice of opportunity for
public comment published in the
Federal Register on April 21, 2014.
Specifically, FAA is withdrawing a
Terminal Area Apron Expansion Project
from the scope of the EA, and the
project will be subject instead to a
discrete environmental review.
FOR FURTHER INFORMATION CONTACT:
Parks Preston, Assistant Manager,
Atlanta Airports District Office, 1701
Columbia Avenue, Room 220, College
Park, Georgia 30337–2747, (404) 305–
6799.
SUMMARY:
Paulding
Northwest Atlanta Airport (PUJ) is
located outside Atlanta, Georgia, in the
town of Dallas, Georgia. Paulding
County and the Paulding County
Airport Authority (PCAA) own the
airport. PUJ opened in 2008 and is
designated as a general aviation airport.
An EA for the construction of PUJ was
completed in 2005. The 2005 EA
evaluated the future Terminal Area
Apron Expansion. In 2011, PUJ owners
redesigned the Terminal Area Apron
Expansion and conducted a
supplemental environmental assessment
(SEA) to consider potential
environmental impacts associated with
the revised project. The Georgia
Department of Transportation (GDOT),
as authorized by the FAA’s State Block
Grant Program, issued a Finding of No
Significant Impact (FONSI), and the
FAA issued a Record of Decision on the
SEA in March 2011.
In September 2013, the PCAA
submitted an application to the FAA
requesting an Airport Operating
asabaliauskas on DSKBBXCHB2PROD with NOTICES
SUPPLEMENTARY INFORMATION:
VerDate Sep<11>2014
17:37 Sep 05, 2017
Jkt 241001
Certificate under title 14 Code of
Regulations, Part 139. A Part 139
Airport Operating Certificate allows the
airport to accommodate scheduled
passenger-carrying operations,
commonly referred to as ‘‘commercial
service.’’ In November 2013, several
Paulding County residents filed a
Petition for Review in the United States
Court of Appeals for the District of
Columbia of two categorical exclusions
issued by GDOT for airfield
improvement projects. The petitioners
argued that the two projects were
connected to the proposed introduction
of commercial service at PUJ. On
December 23, 2013, the petitioners and
the FAA entered into a settlement
agreement under which the FAA agreed
to prepare, at a minimum, an EA for the
proposed Part 139 Airport Operating
Certificate and all connected actions.
The FAA is currently in the process of
preparing that EA (current EA). While
the settlement agreement contemplated
that the current EA would include all
actions connected with the proposed
issuance of the Part 139 Airport
Operating Certificate, the FAA opted to
include in the current EA all reasonably
foreseeable airport improvement
projects, whether or not connected with
the proposed introduction of
commercial service.
On April 21, 2014, the FAA published
a ‘‘Notice of Intent to Prepare an
Environmental Assessment and Notice
of Opportunity for Public Comment’’ in
the Federal Register, 79 FR 22177. The
Notice of Intent identified all of the
projects intended to be reviewed in the
EA, including ‘‘construct[ion of] a
terminal area expansion to provide
hangars and apron area’’ which is the
Terminal Area Apron Expansion
Project. FAA Order 1050.1F,
Environmental Impacts: Policies and
Procedures, requires that where major
steps toward implementation of the
proposed action have not commenced
within 3 years from the date of the
issuance of an environmental finding,
further environmental review is
required. The current EA was to include
the Terminal Area Apron Expansion
Project because major steps toward
implementation of the project had not
been undertaken since the issuance of
the FONSI in March 2011.
PUJ owners now desire to move
forward with the Terminal Area Apron
Expansion Project more expeditiously
than will be possible if the project
remains within the scope of the current
EA. The primary need for expediting
this project is the approaching
expiration of a permit for the project
issued by the U.S. Army Corps of
PO 00000
Frm 00166
Fmt 4703
Sfmt 4703
42221
Engineers under section 404 of the
Clean Water Act.
In accordance with FAA Order
1050.1F, where major steps toward
implementation of a proposed action
have not commenced within 3 years
from the date of the issuance of a
FONSI, a written reevaluation may be
prepared. In this case, the general
aviation apron has independent utility,
is not connected to the Part 139 Airport
Operating Certificate, and is therefore
not required by the National
Environmental Policy Act or the terms
of the 2013 settlement agreement to be
included in the EA. Accordingly, the
current EA will no longer consider
direct impacts of the Terminal Area
Apron Expansion Project, but will
address potential cumulative impacts
associated with the project.
To satisfy the requirements of FAA
Order 1050.1F, GDOT has prepared a
written reevaluation of the project, and
FAA concurred. The written
reevaluation is available for review at
PUJ and online at https://
www.paulding.gov/DocumentCenter/
View/5935.
Issued in Atlanta, Georgia, on August 28,
2017.
Larry F. Clark,
Manager, Atlanta Airports District Office,
Southern Region.
[FR Doc. 2017–18920 Filed 9–5–17; 8:45 am]
BILLING CODE 4910–13–P
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
Public Notice for Waiver of
Aeronautical Land-Use Assurance
Federal Aviation
Administration (FAA), DOT.
ACTION: Notice of intent of waiver with
respect to land; Indianapolis
International Airport, Indianapolis,
Indiana.
AGENCY:
The FAA is considering a
proposal to change 22.111 acres of
airport land from aeronautical use to
non-aeronautical use and to authorize
the sale of airport property located at
Indianapolis International Airport,
Indianapolis, Indiana. The
aforementioned land is not needed for
aeronautical use. The future use of the
property is for commercial and
industrial development. The land is
located on the northwest corner of
Ronald Reagan Parkway and Stafford
Road.
There are no impacts to the airport by
allowing the Indianapolis Airport
Authority to dispose of the property.
SUMMARY:
E:\FR\FM\06SEN1.SGM
06SEN1
42222
Federal Register / Vol. 82, No. 171 / Wednesday, September 6, 2017 / Notices
Comments must be received on
or before October 6, 2017.
DATES:
Documents are available for
review by appointment at the FAA
Chicago Airports District Office,
Melanie Myers, Program Manager, 2300
East Devon Avenue, Des Plaines, IL
60018 Telephone: (847) 294–7525/Fax:
(847) 294–7046 and Eric Anderson,
Director of Properties, Indianapolis
Airport Authority, 7800 Col. H. Weir
Cook Memorial Drive, Indianapolis,
Indiana 46241 (317) 487–5135
Written comments on the Sponsor’s
request must be delivered or mailed to:
Melanie Myers, Program Manager,
Federal Aviation Administration,
Chicago Airports District Office, 2300
East Devon Avenue, Des Plaines, Illinois
60018 Telephone Number: (847) 294–
7525/FAX Number: (847) 294–7046.
ADDRESSES:
FOR FURTHER INFORMATION CONTACT:
Melanie Myers, Program Manager,
Federal Aviation Administration,
Chicago Airports District Office, 2300
East Devon Avenue, Des Plaines, IL
60018 Telephone: (847) 294–7525/Fax:
(847) 294–7046.
In
accordance with section 47107(h) of
Title 49, United States Code, this notice
is required to be published in the
Federal Register 30 days before
modifying the land-use assurance that
requires the property to be used for an
aeronautical purpose.
The vacant land consists of fifteen
(15) original airport acquired parcels.
These parcels were acquired under
grants 3–18–0038–17, 3–18–0038–18, 3–
18–0038–23, 3–18–0038–24, 3–18–
0038–25, 3–18–0038–45, or without
federal participation. The future use of
the property is for commercial and
industrial development.
The disposition of proceeds from the
sale of the airport property will be in
accordance with FAA’s Policy and
Procedures Concerning the Use of
Airport Revenue, published in the
Federal Register on February 16, 1999
(64 FR 7696).
This notice announces that the FAA
is considering the release of the subject
airport property at the Indianapolis
International Airport from federal land
covenants, subject to a reservation for
continuing right of flight as well as
restrictions on the released property as
required in FAA Order 5190.6B section
22.16. Approval does not constitute a
commitment by the FAA to financially
assist in the disposal of the subject
airport property nor a determination of
eligibility for grant-in-aid funding from
the FAA.
asabaliauskas on DSKBBXCHB2PROD with NOTICES
SUPPLEMENTARY INFORMATION:
VerDate Sep<11>2014
17:37 Sep 05, 2017
Jkt 241001
Legal Description
Part of the Northwest Quarter of
Section 32, Township 15 North, Range
2 East in Hendricks County, Indiana,
more particularly described as follows:
Commencing at a mag nail with
washer stamped ‘‘Cripe Firm No. 0055’’
(hereinafter referred to as ‘‘a mag nail’’)
at the Southeast corner of the Northwest
Quarter of said Section 32; thence North
00 degrees 23 minutes 29 seconds East
(assumed bearing) along the East line of
said Northwest Quarter 117.10 feet;
thence North 89 degrees 36 minutes 38
seconds West 16.50 feet to a 5⁄8 inch
diameter rebar with a yellow plastic cap
stamped ‘‘Cripe Firm No. 0055’’
(hereinafter referred to as ‘‘a rebar’’) on
the West right of way line of Ronald
Reagan Parkway and the POINT OF
BEGINNING; thence North 00 degrees
23 minutes 29 seconds East along the
said West right of way line and parallel
to the said East line 1250.78 feet to the
North line of land described in Deed
Record 301, page 852, recorded in the
Office of the Recorder of Hendricks
County, Indiana; thence North 89
degrees 59 minutes 55 seconds West
parallel with the South line of said
Northwest Quarter 755.60 feet to the
Northwest corner of land described in
Deed Record 301, page 406, recorded in
said Recorder’s Office and ‘‘a rebar’’;
thence South 00 degrees 23 minutes 29
seconds West parallel with the East line
of said Northwest Quarter 723.00 feet to
the Southwest corner of land described
in Deed Record 303, page 419, recorded
in said Recorder’s Office; thence South
89 degrees 59 minutes 55 seconds East
along the South line of said described
land and parallel with the South line of
said Northwest Quarter 191.30 feet to
the Northwest corner of land described
in Deed Record 312, page 3, recorded in
said Recorder’s Office and ‘‘a rebar’’;
thence South 00 degrees 23 minutes 29
seconds West along the West line of said
described land and parallel with the
East line of said Northwest Quarter
150.00 feet to the North line of land
described in Deed Record 299, page 605,
recorded in said Recorder’s Office;
thence North 89 degrees 59 minutes 55
seconds West along said North line and
parallel with the South line of said
Northwest Quarter 191.30 feet to the
Northwest corner thereof; thence South
00 degrees 23 minutes 29 seconds West
along the West line of said described
land and parallel with the East line of
said Northwest Quarter 146.52 feet to
the Northeast corner of land described
in Instrument No. 199800012353,
recorded in said Recorder’s Office and
‘‘a rebar’’; thence North 89 degrees 59
minutes 55 seconds West along the
PO 00000
Frm 00167
Fmt 4703
Sfmt 4703
North line of said described land and
parallel with the South line of said
Northwest Quarter 125.00 feet to the
Northwest corner thereof; thence South
00 degrees 23 minutes 29 seconds West
along the West line of said described
land and parallel with the East line of
said Northwest Quarter 236.93 feet to ‘‘a
rebar’’ on the North right of way line of
Stafford Road (the next four courses are
along said North right of way line); (1)
thence South 89 degrees 59 minutes 55
seconds East parallel with the said
South line 132.72 feet to ‘‘a rebar’’; (2)
thence South 81 degrees 28 minutes 04
seconds East 132.70 feet to ‘‘a rebar’’; (3)
thence South 89 degrees 59 minutes 55
seconds East parallel with the said
South line 574.15 feet to ‘‘a rebar’’; (4)
thence North 59 degrees 12 minutes 36
seconds East 49.52 feet to the POINT OF
BEGINNING, containing 22.111 acres,
more or less
Issued in Des Plaines, Illinois on August
29, 2017.
Carlton Lambiasi,
Acting Manager, Chicago Airports District
Office, FAA, Great Lakes Region.
[FR Doc. 2017–18845 Filed 9–5–17; 8:45 am]
BILLING CODE 4910–13–P
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Notice of Final Federal Agency Actions
on Proposed Highway in Alaska
Federal Highway
Administration (FHWA), DOT.
ACTION: Notice of Limitations on Claims
for Judicial Review of Actions by the
FHWA and other Federal agencies.
AGENCY:
This notice announces actions
taken by the FHWA and other federal
agencies that are final. The actions
relate to a proposed highway project,
Seward Highway Milepost 75 to 90
Road and Bridge Rehabilitation, in the
Kenai Peninsula Borough and the
Municipality of Anchorage, Alaska.
Those actions grant licenses, permits,
and approvals for the project.
DATES: By this notice, the FHWA is
advising the public of final agency
action subject to 23 U.S.C. 139(l)(1). A
claim seeking judicial review of the
Federal agency actions on the listed
highway project will be barred unless
the claim is filed on or before February
5, 2018. If the Federal law that
authorizes judicial review of a claim
provides a time period of less than 150
days for filing such claim, then that
shorter time period still applies.
FOR FURTHER INFORMATION CONTACT: Mr.
Henry Rettinger, Central Region Area
SUMMARY:
E:\FR\FM\06SEN1.SGM
06SEN1
Agencies
[Federal Register Volume 82, Number 171 (Wednesday, September 6, 2017)]
[Notices]
[Pages 42221-42222]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-18845]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
Public Notice for Waiver of Aeronautical Land-Use Assurance
AGENCY: Federal Aviation Administration (FAA), DOT.
ACTION: Notice of intent of waiver with respect to land; Indianapolis
International Airport, Indianapolis, Indiana.
-----------------------------------------------------------------------
SUMMARY: The FAA is considering a proposal to change 22.111 acres of
airport land from aeronautical use to non-aeronautical use and to
authorize the sale of airport property located at Indianapolis
International Airport, Indianapolis, Indiana. The aforementioned land
is not needed for aeronautical use. The future use of the property is
for commercial and industrial development. The land is located on the
northwest corner of Ronald Reagan Parkway and Stafford Road.
There are no impacts to the airport by allowing the Indianapolis
Airport Authority to dispose of the property.
[[Page 42222]]
DATES: Comments must be received on or before October 6, 2017.
ADDRESSES: Documents are available for review by appointment at the FAA
Chicago Airports District Office, Melanie Myers, Program Manager, 2300
East Devon Avenue, Des Plaines, IL 60018 Telephone: (847) 294-7525/Fax:
(847) 294-7046 and Eric Anderson, Director of Properties, Indianapolis
Airport Authority, 7800 Col. H. Weir Cook Memorial Drive, Indianapolis,
Indiana 46241 (317) 487-5135
Written comments on the Sponsor's request must be delivered or
mailed to: Melanie Myers, Program Manager, Federal Aviation
Administration, Chicago Airports District Office, 2300 East Devon
Avenue, Des Plaines, Illinois 60018 Telephone Number: (847) 294-7525/
FAX Number: (847) 294-7046.
FOR FURTHER INFORMATION CONTACT: Melanie Myers, Program Manager,
Federal Aviation Administration, Chicago Airports District Office, 2300
East Devon Avenue, Des Plaines, IL 60018 Telephone: (847) 294-7525/Fax:
(847) 294-7046.
SUPPLEMENTARY INFORMATION: In accordance with section 47107(h) of Title
49, United States Code, this notice is required to be published in the
Federal Register 30 days before modifying the land-use assurance that
requires the property to be used for an aeronautical purpose.
The vacant land consists of fifteen (15) original airport acquired
parcels. These parcels were acquired under grants 3-18-0038-17, 3-18-
0038-18, 3-18-0038-23, 3-18-0038-24, 3-18-0038-25, 3-18-0038-45, or
without federal participation. The future use of the property is for
commercial and industrial development.
The disposition of proceeds from the sale of the airport property
will be in accordance with FAA's Policy and Procedures Concerning the
Use of Airport Revenue, published in the Federal Register on February
16, 1999 (64 FR 7696).
This notice announces that the FAA is considering the release of
the subject airport property at the Indianapolis International Airport
from federal land covenants, subject to a reservation for continuing
right of flight as well as restrictions on the released property as
required in FAA Order 5190.6B section 22.16. Approval does not
constitute a commitment by the FAA to financially assist in the
disposal of the subject airport property nor a determination of
eligibility for grant-in-aid funding from the FAA.
Legal Description
Part of the Northwest Quarter of Section 32, Township 15 North,
Range 2 East in Hendricks County, Indiana, more particularly described
as follows:
Commencing at a mag nail with washer stamped ``Cripe Firm No.
0055'' (hereinafter referred to as ``a mag nail'') at the Southeast
corner of the Northwest Quarter of said Section 32; thence North 00
degrees 23 minutes 29 seconds East (assumed bearing) along the East
line of said Northwest Quarter 117.10 feet; thence North 89 degrees 36
minutes 38 seconds West 16.50 feet to a \5/8\ inch diameter rebar with
a yellow plastic cap stamped ``Cripe Firm No. 0055'' (hereinafter
referred to as ``a rebar'') on the West right of way line of Ronald
Reagan Parkway and the POINT OF BEGINNING; thence North 00 degrees 23
minutes 29 seconds East along the said West right of way line and
parallel to the said East line 1250.78 feet to the North line of land
described in Deed Record 301, page 852, recorded in the Office of the
Recorder of Hendricks County, Indiana; thence North 89 degrees 59
minutes 55 seconds West parallel with the South line of said Northwest
Quarter 755.60 feet to the Northwest corner of land described in Deed
Record 301, page 406, recorded in said Recorder's Office and ``a
rebar''; thence South 00 degrees 23 minutes 29 seconds West parallel
with the East line of said Northwest Quarter 723.00 feet to the
Southwest corner of land described in Deed Record 303, page 419,
recorded in said Recorder's Office; thence South 89 degrees 59 minutes
55 seconds East along the South line of said described land and
parallel with the South line of said Northwest Quarter 191.30 feet to
the Northwest corner of land described in Deed Record 312, page 3,
recorded in said Recorder's Office and ``a rebar''; thence South 00
degrees 23 minutes 29 seconds West along the West line of said
described land and parallel with the East line of said Northwest
Quarter 150.00 feet to the North line of land described in Deed Record
299, page 605, recorded in said Recorder's Office; thence North 89
degrees 59 minutes 55 seconds West along said North line and parallel
with the South line of said Northwest Quarter 191.30 feet to the
Northwest corner thereof; thence South 00 degrees 23 minutes 29 seconds
West along the West line of said described land and parallel with the
East line of said Northwest Quarter 146.52 feet to the Northeast corner
of land described in Instrument No. 199800012353, recorded in said
Recorder's Office and ``a rebar''; thence North 89 degrees 59 minutes
55 seconds West along the North line of said described land and
parallel with the South line of said Northwest Quarter 125.00 feet to
the Northwest corner thereof; thence South 00 degrees 23 minutes 29
seconds West along the West line of said described land and parallel
with the East line of said Northwest Quarter 236.93 feet to ``a rebar''
on the North right of way line of Stafford Road (the next four courses
are along said North right of way line); (1) thence South 89 degrees 59
minutes 55 seconds East parallel with the said South line 132.72 feet
to ``a rebar''; (2) thence South 81 degrees 28 minutes 04 seconds East
132.70 feet to ``a rebar''; (3) thence South 89 degrees 59 minutes 55
seconds East parallel with the said South line 574.15 feet to ``a
rebar''; (4) thence North 59 degrees 12 minutes 36 seconds East 49.52
feet to the POINT OF BEGINNING, containing 22.111 acres, more or less
Issued in Des Plaines, Illinois on August 29, 2017.
Carlton Lambiasi,
Acting Manager, Chicago Airports District Office, FAA, Great Lakes
Region.
[FR Doc. 2017-18845 Filed 9-5-17; 8:45 am]
BILLING CODE 4910-13-P