Download as PDF Federal Register / Vol. 82, No. 166 / Tuesday, August 29, 2017 / Notices Decontamination and Decommissioning Fund established at the Department of Treasury pursuant to section 1801 of the Atomic Energy Act of 1954 (42 U.S.C. 2297g). Payment or obligation of funds shall be subject to the requirements of the Anti-Deficiency Act (31 U.S.C. 1341). Authority: Section 1001–1004 of Public Law 102–486, 106 Stat. 2776 (42 U.S.C. 2296a et seq.). link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on September 11, 2017. Issued in Washington, DC on May 11, 2017. Theresa Kliczewski, Office of Waste Disposal, Office of Environmental Management. Dated: August 22, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–18270 Filed 8–28–17; 8:45 am] [FR Doc. 2017–18240 Filed 8–28–17; 8:45 am] BILLING CODE 6450–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY [Docket No. OR17–21–000] Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Project No. 10805–057] sradovich on DSK3GMQ082PROD with NOTICES Grieve Pipeline, LLC; Notice of Petition for Declaratory Order Take notice that on August 11, 2017, pursuant to Rule 207(a)(2) of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207(a)(2) (2016), Grieve Pipeline, LLC, a subsidiary of Elk Petroleum, Inc., filed a petition for a declaratory order seeking approval of open season procedures, rate structure, key contract and tariff terms, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the eLibrary VerDate Sep<11>2014 18:45 Aug 28, 2017 Jkt 241001 Midwest Hydraulic Company, LLC; Notice of Emergency Drawdown and Temporary Variance and Soliciting Comments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Types of Application: Temporary Emergency Drawdown and Variance from License Article 401. b. Project No.: P–10805–057. c. Date Filed: August 18, 2017. d. Applicants: Midwest Hydraulic Company, LLC. e. Name of Projects: Hatfield Hydroelectric Project. f. Location: The project is located on the Black River, in the Township of Hatfield, in Jackson and Clarke counties, Wisconsin. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Dwight Bowler, Midwest Hydraulic Company, LLC, c/o Black River Partners, 813 Jefferson Hill Road, Nassau, New York (518) 766–2753. i. FERC Contact: Ms. Rebecca Martin, (202) 502–6012, Rebecca.Martin@ ferc.gov. j. Deadline for filing comments, is 30 days from the issuance date of this notice by the Commission. All documents may be filed electronically via the Internet. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https:// www.ferc.gov/docs-filing/efiling.asp. If unable to be filed electronically, documents may be paper-filed. To PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 41011 paper-file, an original and seven copies should be mailed to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. Please include the project number (P–10805–057) on any comments, motions, or recommendations filed. k. Description of Request: The licensee must lower the reservoir as a risk reduction measure to prevent additional scouring below the project spillways during high flow events. The drawdown is also necessary to safely construct repairs below the spillway. The drawdown would begin on September 5, 2017 at a rate of 0.50 feet per day for a total drawdown of 5.5 feet to elevation 877 National Geodetic Vertical Datum (NGVD). Article 401 of the project license requires the licensee to maintain a target reservoir surface elevation of Lake Arbutus of 882.5 ± 0.25 feet NGVD at least 50 percent of the time and ± 0.5 feet at all times. Article 401 allows the reservoir elevation to be modified temporarily for operating emergencies. The refill of the reservoir is estimated to occur in spring of 2019. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments: Anyone may submit comments in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. Any comments must be received on or before the specified comment date for the particular application. E:\FR\FM\29AUN1.SGM 29AUN1 41012 Federal Register / Vol. 82, No. 166 / Tuesday, August 29, 2017 / Notices o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title COMMENTS, as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; and (3) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments should relate to project works which are the subject of this application. Agencies may obtain copies of the application directly from the applicant. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: August 22, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–18236 Filed 8–28–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. RD16–10–000, RD17–5–000, and IC17–6–000 (FERC–725E)] sradovich on DSK3GMQ082PROD with NOTICES Errata Notice On August 15, 2017, the Commission issued a Notice of revised information collection and request for comments on FERC–725E (Mandatory Reliability Standards for the Western Electric Coordinating Council), in Docket Nos. RD16–10–000, RD17–5–000, and IC17– 6–000. This Errata Notice corrects multiple figures on page 13, in the table labeled FERC–725E, Mandatory Reliability Standards for the Western Electric Coordinating Council, Changes in Docket No. RD17–5–000. All of the changes described here occur in two separate rows under the column labeled Total Annual Burden Hours & Total Annual Cost ($) (3)*(4)=(5).: The entry in the row labeled Net Burden Change in Year 1 (Due to Docket RD17–5) should be changed from +252 hrs. (increase) to +252 hrs.; $2,993.40 (increase). The entry in the row labeled Net Burden Change in Year 2 and ongoing (Due to Docket RD17–5) should be changed from the ¥621 hrs. (decrease) to +873 hrs.; $53,884.47 (increase). VerDate Sep<11>2014 18:45 Aug 28, 2017 Jkt 241001 Dated: August 22, 2017. Kimberly D. Bose, Secretary. Dated: August 23, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–18237 Filed 8–28–17; 8:45 am] [FR Doc. 2017–18239 Filed 8–28–17; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission [Project No. 2100–180—California] Combined Notice of Filings #1 California Department of Water Resources; Notice of Availability of Environmental Assessment Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC17–158–000. Applicants: CPV Towantic, LLC, Towantic Energy Holdings, LLC, Aircraft Services Corporation. Description: Correction to August 15, 2017 Application for Authorization under Section 203 of the Federal Power Act and Request for Waivers, Confidential Treatment, Expedited Action and Shortened Comment Period of CPV Towantic, LLC, et al. Filed Date: 8/21/17. Accession Number: 20170821–5157. Comments Due: 5 p.m. ET 9/5/17. Docket Numbers: EC17–163–000. Applicants: MDU Resources Group, Inc. Description: Application of MDU Resources Group, Inc. for Authorization Under FPA Section 203(a)(1)(B) and Request for Expedited Consideration and Confidential Treatment. Filed Date: 8/22/17. Accession Number: 20170822–5159. Comments Due: 5 p.m. ET 9/12/17. Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG17–144–000. Applicants: St. Joseph Energy Center, LLC. Description: St. Joseph Energy Center, LLC Submits Self-Certification of EWG Status. Filed Date: 8/23/17. Accession Number: 20170823–5015. Comments Due: 5 p.m. ET 9/13/17. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER17–2342–000. Applicants: Bladen Solar, LLC. Description: Baseline eTariff Filing: Baseline new to be effective 10/10/2017. Filed Date: 8/22/17. Accession Number: 20170822–5135. Comments Due: 5 p.m. ET 9/12/17. Docket Numbers: ER17–2343–000. Applicants: Bullock Solar, LLC. Description: Baseline eTariff Filing: Baseline new to be effective 10/4/2017. In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission or FERC’s) regulations, 18 Code of Federal Regulations Part 380, the Office of Energy Projects has reviewed an application filed by the California Department of Water Resources on May 17, 2017, and supplemented June 16 and June 20, 2017, to permanently reroute three existing primary transmission lines at the Feather River Project No. 2100 between the Hyatt Pumping-Generating Plant and the Table Mountain Substation. The proposal would allow California Department of Water Resources to continuously deliver electricity along a different route away from repair activities at the project’s damaged main spillway and emergency spillway area. The Feather River Project is located on the Feather River in Butte County, California. Staff prepared an environmental assessment (EA) for the application which analyzes the potential environmental effects of approving the requested transmission line modification. In the EA, staff concludes that such an approval, with specified environmental protection measures, would not constitute a major federal action that would significantly affect the quality of the human environment. A copy of the EA is available for review at the Commission’s Public Reference Room or it may be viewed on the Commission’s Web site at www.ferc.gov using the eLibrary link. Enter the docket number P–2100–180 in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY, 202–502–8659. For further information, contact Mr. John Aedo at (415) 369–3335 or by email at john.aedo@ferc.gov. PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 E:\FR\FM\29AUN1.SGM 29AUN1

Agencies

[Federal Register Volume 82, Number 166 (Tuesday, August 29, 2017)]
[Notices]
[Pages 41011-41012]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-18236]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10805-057]


Midwest Hydraulic Company, LLC; Notice of Emergency Drawdown and 
Temporary Variance and Soliciting Comments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Types of Application: Temporary Emergency Drawdown and Variance 
from License Article 401.
    b. Project No.: P-10805-057.
    c. Date Filed: August 18, 2017.
    d. Applicants: Midwest Hydraulic Company, LLC.
    e. Name of Projects: Hatfield Hydroelectric Project.
    f. Location: The project is located on the Black River, in the 
Township of Hatfield, in Jackson and Clarke counties, Wisconsin.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Dwight Bowler, Midwest Hydraulic Company, 
LLC, c/o Black River Partners, 813 Jefferson Hill Road, Nassau, New 
York (518) 766-2753.
    i. FERC Contact: Ms. Rebecca Martin, (202) 502-6012, 
Rebecca.Martin@ferc.gov.
    j. Deadline for filing comments, is 30 days from the issuance date 
of this notice by the Commission. All documents may be filed 
electronically via the Internet. See, 18 CFR 385.2001(a)(1)(iii) and 
the instructions on the Commission's Web site at https://www.ferc.gov/docs-filing/efiling.asp. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original and seven 
copies should be mailed to: Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. Please include the project number (P-
10805-057) on any comments, motions, or recommendations filed.
    k. Description of Request: The licensee must lower the reservoir as 
a risk reduction measure to prevent additional scouring below the 
project spillways during high flow events. The drawdown is also 
necessary to safely construct repairs below the spillway. The drawdown 
would begin on September 5, 2017 at a rate of 0.50 feet per day for a 
total drawdown of 5.5 feet to elevation 877 National Geodetic Vertical 
Datum (NGVD). Article 401 of the project license requires the licensee 
to maintain a target reservoir surface elevation of Lake Arbutus of 
882.5  0.25 feet NGVD at least 50 percent of the time and 
 0.5 feet at all times. Article 401 allows the reservoir 
elevation to be modified temporarily for operating emergencies. The 
refill of the reservoir is estimated to occur in spring of 2019.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits 
in the docket number field to access the document. You may also 
register online at https://www.ferc.gov/docs-filing/esubscription.asp to 
be notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item 
(h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments: Anyone may submit comments in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. Any comments must be received on or before the specified comment 
date for the particular application.

[[Page 41012]]

    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title COMMENTS, as applicable; (2) set 
forth in the heading the name of the applicant and the project number 
of the application to which the filing responds; and (3) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments must set forth their evidentiary basis and otherwise comply 
with the requirements of 18 CFR 4.34(b). All comments should relate to 
project works which are the subject of this application. Agencies may 
obtain copies of the application directly from the applicant. A copy of 
all other filings in reference to this application must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) 
and 385.2010.

    Dated: August 22, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-18236 Filed 8-28-17; 8:45 am]
 BILLING CODE 6717-01-P