Executive Order 13807 of August 15, 2017
The President
Establishing Discipline and Accountability in the Environmental Review and Permitting Process for Infrastructure
Projects
By the authority vested in me as President by the Constitution and the
laws of the United States of America, and in order to ensure that the
Federal environmental review and permitting process for infrastructure
projects is coordinated, predictable, and transparent, it is hereby ordered
as follows:
Section 1. Purpose. America needs increased infrastructure investment to
strengthen our economy, enhance our competitiveness in world trade, create
jobs and increase wages for our workers, and reduce the costs of goods
and services for our families. The poor condition of America’s infrastructure
has been estimated to cost a typical American household thousands of
dollars each year. Inefficiencies in current infrastructure project decisions,
including management of environmental reviews and permit decisions or
authorizations, have delayed infrastructure investments, increased project
costs, and blocked the American people from enjoying improved infrastructure that would benefit our economy, society, and environment. More efficient and effective Federal infrastructure decisions can transform our economy, so the Federal Government, as a whole, must change the way it
processes environmental reviews and authorization decisions.
Sec. 2. Policy. It is the policy of the Federal Government to:
(a) safeguard our communities and maintain a healthy environment;
(b) ensure that Federal authorities make informed decisions concerning
the environmental impacts of infrastructure projects;
(c) develop infrastructure in an environmentally sensitive manner;
(d) provide transparency and accountability to the public regarding environmental review and authorization decisions;
(e) be good stewards of public funds, including those used to develop
infrastructure projects, and avoid duplicative and wasteful processes;
(f) conduct environmental reviews and authorization processes in a coordinated, consistent, predictable, and timely manner in order to give public
and private investors the confidence necessary to make funding decisions
for new infrastructure projects;
mstockstill on DSK30JT082PROD with E0
(g) speak with a coordinated voice when conducting environmental reviews
and making authorization decisions; and
(h) make timely decisions with the goal of completing all Federal environmental reviews and authorization decisions for major infrastructure projects
within 2 years.
Sec. 3. Definitions. The terms of this order shall be applied consistently
with those defined under 42 U.S.C. 4370m and implementing guidance
to the maximum extent possible. The following definitions shall specifically
apply:
(a) ‘‘Authorization’’ means any license, permit, approval, finding, determination, or other administrative decision issued by a Federal department
or agency (agency) that is required or authorized under Federal law in
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00003
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
40464
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
order to site, construct, reconstruct, or commence operations of an infrastructure project, including any authorization under 42 U.S.C. 4370m(3).
(b) ‘‘CAP Goals’’ means Federal Government Priority Goals established
by the Government Performance and Results Act (GPRA) Modernization
Act of 2010, Public Law 111–352, 124 Stat. 3866, and commonly referred
to as Cross-Agency Priority (CAP) Goals.
(c) ‘‘Federal Permitting Improvement Steering Council’’ or ‘‘FPISC’’ means
the entity established under 42 U.S.C. 4370m–1.
(d) ‘‘Infrastructure project’’ means a project to develop the public and
private physical assets that are designed to provide or support services
to the general public in the following sectors: surface transportation, including roadways, bridges, railroads, and transit; aviation; ports, including navigational channels; water resources projects; energy production and generation,
including from fossil, renewable, nuclear, and hydro sources; electricity
transmission; broadband Internet; pipelines; stormwater and sewer infrastructure; drinking water infrastructure; and other sectors as may be determined
by the FPISC.
(e) ‘‘Major infrastructure project’’ means an infrastructure project for which
multiple authorizations by Federal agencies will be required to proceed
with construction, the lead Federal agency has determined that it will prepare
an environmental impact statement (EIS) under the National Environmental
Policy Act (NEPA), 42 U.S.C. 4321 et seq., and the project sponsor has
identified the reasonable availability of funds sufficient to complete the
project.
(f) ‘‘Permitting timetable’’ means an environmental review and authorization schedule, or other equivalent schedule, for a project or group of projects
that identifies milestones—including intermediate and final completion dates
for action by each agency on any Federal environmental review or authorization required for a project or group of projects—that is prepared by the
lead Federal agency in consultation with all cooperating and participating
agencies.
Sec. 4. Agency Performance Accountability. Federal agencies should follow
transparent and coordinated processes for conducting environmental reviews
and making authorization decisions. These processes must include early
and open coordination among Federal, State, tribal, and local agencies and
early engagement with the public. Holding Federal agencies accountable
for their progress on implementing the policy set forth in section 2 of
this order should, among other things, produce measurably better environmental outcomes with respect to infrastructure development.
(a) Performance Priority Goals.
(i) CAP Goal. A CAP Goal is a Federal tool for accelerating progress
in priority areas that require active collaboration among multiple agencies
to overcome organizational barriers and to achieve better performance
than one agency could achieve on its own. Within 180 days of the date
of this order, the Director of the Office of Management and Budget (OMB),
in consultation with the FPISC, shall establish a CAP Goal on Infrastructure
Permitting Modernization so that, where permitted by law:
mstockstill on DSK30JT082PROD with E0
(A) Federal environmental reviews and authorization processes for infrastructure projects are consistent, coordinated, and predictable; and
(B) the time for the Federal Government’s processing of environmental
reviews and authorization decisions for new major infrastructure projects
should be reduced to not more than an average of approximately 2 years,
measured from the date of the publication of a notice of intent to prepare
an environmental impact statement or other benchmark deemed appropriate by the Director of OMB.
(ii) Agency Goals. All Federal agencies with environmental review, authorization, or consultation responsibilities for infrastructure projects shall
modify their Strategic Plans and Annual Performance Plans under the
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00004
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
40465
GPRA Modernization Act of 2010 to include agency performance goals
related to the completion of environmental reviews and authorizations
for infrastructure projects consistent with the new CAP Goal on Infrastructure Permitting Modernization. The agencies shall integrate the achievement of these performance goals into appropriate agency personnel performance plans, such as those of the agency Chief Environmental Review
and Permitting Officers (CERPOs) or other appropriate officials, consistent
with guidance to be provided by OMB, in consultation with the Office
of Personnel Management. Progress on these goals shall be reviewed and
analyzed by agency leadership, pursuant to the GPRA Modernization Act
of 2010.
(b) Accountability. Within 180 days of the establishment of the CAP Goal
on Infrastructure Permitting Modernization, as described in subsection (a)
of this section, or such longer period of time as determined by the Director
of OMB, OMB, in consultation with the FPISC, shall issue guidance for
establishing a performance accountability system to facilitate achievement
of the CAP Goal.
(i) Tracking of Major Infrastructure Projects. The performance accountability system shall track each major infrastructure project. The performance accountability system shall include, at a minimum, assessments of
the agency’s performance with respect to each of the following areas,
as applicable:
(A) whether major infrastructure projects are processed using the ‘‘One
Federal Decision’’ mechanism, as described in subsection 5(b) of this
order;
(B) whether major infrastructure projects have a permitting timetable;
(C) whether major infrastructure projects follow an effective process
that automatically elevates instances in which permitting timetable milestones are missed or extended, or are anticipated to be missed or extended,
to appropriate senior agency officials;
(D) whether agencies are meeting the established milestones in the permitting timetable;
(E) the time it takes to complete the processing of environmental reviews
and authorizations for each major infrastructure project; and
(F) the costs of the environmental reviews and authorizations for each
major infrastructure project.
(ii) Scoring. The accountability system shall include a scoring mechanism
that shall follow, at a minimum, the following procedures:
(A) agencies will submit information to OMB, consistent with existing
reporting mechanisms to the maximum extent possible, on the assessment
areas described in subsection (b)(i) of this section;
(B) at least once per quarter, OMB will produce a scorecard of agency
performance and overall progress toward achieving CAP Goal targets;
mstockstill on DSK30JT082PROD with E0
(C) where an agency’s inability to meet a permitting timetable milestone
results in a significant delay of the project timeline, after consulting with
the project sponsor and relevant agencies, agencies will submit (based
on OMB guidance) an estimate of the delay’s costs to the project; and
(D) the Director of OMB will consider each agency’s performance during
budget formulation and determine whether appropriate penalties, including
those authorized at 23 U.S.C. 139(h)(7) and 33 U.S.C. 2348(h)(5), must
or should be imposed, to the extent required or permitted by law, for
those that significantly fail to meet a permitting timetable milestone or
in other situations deemed appropriate by the Director of OMB after considering the causes of any poor performance.
(iii) Best Practices. Agencies shall implement the techniques and strategies
the FPISC annually identifies as best practices pursuant to 42 U.S.C.
4370m–1(c)(2)(B), as appropriate. The performance accountability system
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00005
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
40466
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
shall track and score agencies on the incorporation and implementation
of appropriate best practices for all infrastructure projects, including the
implementation of such best practices at an agency’s field level.
Sec. 5. Process Enhancements. In furtherance of the policy described in
section 2 of this order, Federal agencies shall follow a more unified environmental review and authorization process.
(a) Processing of Major Infrastructure Projects. In processing environmental
reviews and authorizations for major infrastructure projects, Federal agencies
shall:
(i) use ‘‘One Federal Decision’’ described in subsection (b) of this section;
(ii) develop and follow a permitting timetable, which shall be reviewed
and updated at least quarterly by the lead Federal agency in consultation
with Federal cooperating and participating agencies; and
(iii) follow an effective process that automatically elevates instances where
a permitting timetable milestone is missed or extended, or is anticipated
to be missed or extended, to appropriate senior agency officials of the
lead Federal agency and the cooperating and participating Federal agency
or agencies to which the milestone applies.
(b) One Federal Decision.
(i) Each major infrastructure project shall have a lead Federal agency,
which shall be responsible for navigating the project through the Federal
environmental review and authorization process, including the identification of a primary Federal point of contact at each Federal agency. All
Federal cooperating and participating agencies shall identify points of
contact for each project, cooperate with the lead Federal agency point
of contact, and respond to all reasonable requests for information from
the lead Federal agency in a timely manner.
(ii) With respect to the applicability of NEPA to a major infrastructure
project, the Federal lead, cooperating, and participating agencies for each
major infrastructure project shall all record any individual agency decision
in one Record of Decision (ROD), which shall be coordinated by the
lead Federal agency unless the project sponsor requests that agencies
issue separate NEPA documents, the NEPA obligations of a cooperating
or participating agency have already been satisfied, or the lead Federal
agency determines that a single ROD would not best promote completion
of the project’s environmental review and authorization process. The Federal lead, cooperating, and participating agencies shall all agree to a permitting timetable that includes the completion dates for the ROD and the
federally required authorizations for the project.
mstockstill on DSK30JT082PROD with E0
(iii) All Federal authorization decisions for the construction of a major
infrastructure project shall be completed within 90 days of the issuance
of a ROD by the lead Federal agency, provided that the final EIS includes
an adequate level of detail to inform agency decisions pursuant to their
specific statutory authority and requirements. The lead Federal agency
may extend the 90-day deadline if the lead Federal agency determines
that Federal law prohibits the agency from issuing its approval or permit
within the 90-day period, the project sponsor requests that the permit
or approval follow a different timeline, or the lead Federal agency determines that an extension would better promote completion of the project’s
environmental review and authorization process.
(iv) The Council on Environmental Quality (CEQ) and OMB shall develop
the framework for implementing One Federal Decision, in consultation
with the FPISC.
(A) The framework should be consistent with the model processes established under 42 U.S.C. 4370m–2, 23 U.S.C. 139, 33 U.S.C. 2348, the
2015 ‘‘Red Book’’ (officially entitled ‘‘Synchronizing Environmental Reviews for Transportation and Other Infrastructure Projects’’), and CEQ
guidance on efficient and timely environmental reviews under NEPA.
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00006
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
40467
(B) The framework shall also include guidance on the development
of permitting timetables by the lead Federal agencies, in collaboration
with Federal cooperating and participating agencies. Permitting timetables
shall identify estimated intermediate and final completion dates for all
environmental reviews and authorizations that are reasonably anticipated
as being needed for a project, including the process for granting extensions
of any established dates. The guidance shall specify that lead Federal
agencies need not include the estimated intermediate and final completion
dates of any such reviews or authorizations until the design of a project
has sufficiently advanced so that they can be developed. In such cases,
the guidance shall instruct lead Federal agencies to estimate when the
project’s design will be advanced enough to determine such dates. The
timelines shall account for any federally required decisions or permits
that are assumed by, or delegated to, State, tribal, or local agencies and
the extent to which any approval or permit to be issued by a Federal
agency is dependent upon the issuance of such a decision or permit.
(C) CEQ and OMB shall also develop guidance for applying One Federal
Decision whenever the lead agency is a State, tribal, or local agency
exercising an assignment or delegation of an agency’s NEPA responsibilities.
(c) Dashboard. All projects subject to 23 U.S.C. 139 and ‘‘covered projects’’
under 42 U.S.C. 4370m shall be tracked on the Dashboard established under
42 U.S.C. 4370m–2(b). Other projects or classes of projects subject to special
environmental review and authorization streamlining processes similar to
those referenced in this subsection may also be tracked on the Dashboard
at the discretion of the FPISC Executive Director. The dates for milestones
of all projects tracked on the Dashboard shall be updated monthly, or on
another appropriate timeline as may be determined by the FPISC Executive
Director.
(d) Executive Order 13766. For purposes of implementing Executive Order
13766 of January 24, 2017 (Expediting Environmental Reviews and Approvals
for High Priority Infrastructure Projects), all infrastructure projects that meet
the criteria for, and are subject to, 23 U.S.C. 139, 33 U.S.C. 2348, or 42
U.S.C. 4370m–4370m–12 shall qualify as high priority projects under Executive Order 13766. Other projects or classes of projects subject to special
environmental review and authorization streamlining processes, similar to
those referenced in this subsection as may be determined by the FPISC
Executive Director in consultation with OMB and CEQ, shall also qualify
as high priority infrastructure projects under Executive Order 13766. The
CEQ Chairman’s responsibilities under sections 2 and 3 of Executive Order
13766 shall be satisfied by referring the project to the FPISC Executive
Director, the Secretary of Transportation, or the Assistant Secretary of the
Army for Civil Works, as appropriate.
(e) Council on Environmental Quality.
(i) Directives. Within 30 days of the date of this order, the CEQ shall
develop an initial list of actions it will take to enhance and modernize
the Federal environmental review and authorization process. Such actions
should include issuing such regulations, guidance, and directives as CEQ
may deem necessary to:
mstockstill on DSK30JT082PROD with E0
(A) ensure optimal interagency coordination of environmental review
and authorization decisions, including by providing for an expanded role
and authorities for lead agencies, more clearly defined responsibilities
for cooperating and participating agencies, and Government-wide applicability of NEPA decisions and analyses;
(B) ensure that environmental reviews and authorization decisions involving multiple agencies are conducted in a manner that is concurrent,
synchronized, timely, and efficient;
(C) provide for agency use, to the maximum extent permitted by law,
of environmental studies, analysis, and decisions conducted in support
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00007
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
40468
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
of earlier Federal, State, tribal, or local environmental reviews or authorization decisions; and
(D) ensure that agencies apply NEPA in a manner that reduces unnecessary burdens and delays as much as possible, including by using CEQ’s
authority to interpret NEPA to simplify and accelerate the NEPA review
process.
(ii) Dispute Resolution. Except where dispute resolution processes are
otherwise provided for in law, including under 42 U.S.C. 4370m–2, or
by Executive Order or other Presidential directive, upon request of a
lead Federal agency, cooperating agency, or participating agency, CEQ
may mediate interagency disputes arising between Federal agencies concerning Federal environmental review or authorization decisions for any
infrastructure project pertaining to any environmental law, regulation, order
or policy, and shall facilitate resolution of any conflicting positions of
the relevant agencies.
mstockstill on DSK30JT082PROD with E0
(iii) Agency Procedures. CEQ shall form and lead an interagency working
group, consisting of the Director of OMB, agency CERPOs, and such other
representatives of agencies as CEQ deems appropriate. The working group
shall review the NEPA implementing regulations and other environmental
review and authorization processing policies of agencies that are members
of the FPISC to identify impediments to efficient and effective environmental reviews and authorizations for infrastructure projects. The working
group shall also identify those agencies that require an action plan to
address identified impediments. Based on this review, agencies shall develop action plans that set forth the actions they will take and timelines
for completing those actions, and they shall submit those action plans
to CEQ and OMB for comment. Each agency’s action plan shall, at a
minimum, establish procedures for a regular review and update of categorical exclusions, where appropriate.
(f) Federal Permitting Improvement Steering Council.
(i) Organizational Support. Unless otherwise determined by the Director
of OMB, the General Services Administration (GSA) shall provide necessary
administrative and organizational support to the FPISC, including personnel, procurement, and budget support. The GSA Administrator, or
the head of another agency designated by the Director of OMB, may
delegate any authority to the FPISC Executive Director necessary for the
operation and administration of the FPISC and the Office of the Executive
Director, and the Executive Director may redelegate these authorities, as
appropriate.
(ii) Additional Duties. In addition to the duties and responsibilities charged
to the FPISC Executive Director under 42 U.S.C. 4370m–4370m–12 and
this order, the FPISC Executive Director may, upon request of a FPISC
member agency or a project sponsor, work with the lead agency or any
cooperating and participating agencies to facilitate the environmental review and authorization process for any infrastructure project regardless
of whether the project is a ‘‘covered project’’ under 42 U.S.C. 4370m,
including by resolving disputes and promoting early coordination. The
FPISC Executive Director, the Director of OMB, or the Chairman of CEQ
may establish any appropriate policies or procedures concerning the FPISC
Executive Director’s facilitation of the environmental review and authorization process under this subsection. Agencies must cooperate with the
FPISC Executive Director with respect to the implementation of these
additional duties.
(g) Energy Corridors. The Departments of the Interior and Agriculture,
as appropriate, shall be the lead agencies for facilitating the identification
and designation of energy right-of-way corridors on Federal lands for Government-wide expedited environmental review for the development of energy
infrastructure projects.
(h) The Department of the Interior shall provide to OMB a strategy and
recommendations for a multi-agency reorganization effort that would further
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00008
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
Federal Register / Vol. 82, No. 163 / Thursday, August 24, 2017 / Presidential Documents
40469
the aims of this order. OMB, in consultation with the Department of the
Interior, shall coordinate with the heads of other agencies affected to incorporate the strategy, as appropriate, into the comprehensive reorganization
plan developed under Executive Order 13781 of March 13, 2017 (Comprehensive Plan for Reorganizing the Executive Branch).
Sec. 6. Executive Order 13690 of January 30, 2015 (Establishing a Federal
Flood Risk Management Standard and a Process for Further Soliciting and
Considering Stakeholder Input), is revoked.
Sec. 7. General Provisions. (a) Nothing in this order shall be construed
to impair or otherwise affect:
(i) the authority granted by law to an executive department, agency, or
the head thereof; or
(ii) the functions of the Director of the Office of Management and Budget
relating to budgetary, administrative, or legislative proposals.
(b) This order shall be implemented consistent with applicable law and
subject to the availability of appropriations.
(c) This order is not intended to, and does not, create any right or benefit,
substantive or procedural, enforceable at law or in equity by any party
against the United States, its departments, agencies, or entities, its officers,
employees, or agents, or any other person.
THE WHITE HOUSE,
August 15, 2017.
[FR Doc. 2017–18134
Filed 8–23–17; 11:15 am]
VerDate Sep<11>2014
18:46 Aug 23, 2017
Jkt 241001
PO 00000
Frm 00009
Fmt 4705
Sfmt 4790
E:\FR\FM\24AUE0.SGM
24AUE0
Trump.EPS
mstockstill on DSK30JT082PROD with E0
Billing code 3295–F7–P
Agencies
[Federal Register Volume 82, Number 163 (Thursday, August 24, 2017)]
[Presidential Documents]
[Pages 40463-40469]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-18134]
[[Page 40461]]
Vol. 82
Thursday,
No. 163
August 24, 2017
Part XXX
The President
-----------------------------------------------------------------------
Executive Order 13807--Establishing Discipline and Accountability in
the Environmental Review and Permitting Process for Infrastructure
Projects
Proclamation 9630--National Employer Support of the Guard and Reserve
Week, 2017
Presidential Documents
Federal Register / Vol. 82 , No. 163 / Thursday, August 24, 2017 /
Presidential Documents
___________________________________________________________________
Title 3--
The President
[[Page 40463]]
Executive Order 13807 of August 15, 2017
Establishing Discipline and Accountability in the
Environmental Review and Permitting Process for
Infrastructure Projects
By the authority vested in me as President by the
Constitution and the laws of the United States of
America, and in order to ensure that the Federal
environmental review and permitting process for
infrastructure projects is coordinated, predictable,
and transparent, it is hereby ordered as follows:
Section 1. Purpose. America needs increased
infrastructure investment to strengthen our economy,
enhance our competitiveness in world trade, create jobs
and increase wages for our workers, and reduce the
costs of goods and services for our families. The poor
condition of America's infrastructure has been
estimated to cost a typical American household
thousands of dollars each year. Inefficiencies in
current infrastructure project decisions, including
management of environmental reviews and permit
decisions or authorizations, have delayed
infrastructure investments, increased project costs,
and blocked the American people from enjoying improved
infrastructure that would benefit our economy, society,
and environment. More efficient and effective Federal
infrastructure decisions can transform our economy, so
the Federal Government, as a whole, must change the way
it processes environmental reviews and authorization
decisions.
Sec. 2. Policy. It is the policy of the Federal
Government to:
(a) safeguard our communities and maintain a
healthy environment;
(b) ensure that Federal authorities make informed
decisions concerning the environmental impacts of
infrastructure projects;
(c) develop infrastructure in an environmentally
sensitive manner;
(d) provide transparency and accountability to the
public regarding environmental review and authorization
decisions;
(e) be good stewards of public funds, including
those used to develop infrastructure projects, and
avoid duplicative and wasteful processes;
(f) conduct environmental reviews and authorization
processes in a coordinated, consistent, predictable,
and timely manner in order to give public and private
investors the confidence necessary to make funding
decisions for new infrastructure projects;
(g) speak with a coordinated voice when conducting
environmental reviews and making authorization
decisions; and
(h) make timely decisions with the goal of
completing all Federal environmental reviews and
authorization decisions for major infrastructure
projects within 2 years.
Sec. 3. Definitions. The terms of this order shall be
applied consistently with those defined under 42 U.S.C.
4370m and implementing guidance to the maximum extent
possible. The following definitions shall specifically
apply:
(a) ``Authorization'' means any license, permit,
approval, finding, determination, or other
administrative decision issued by a Federal department
or agency (agency) that is required or authorized under
Federal law in
[[Page 40464]]
order to site, construct, reconstruct, or commence
operations of an infrastructure project, including any
authorization under 42 U.S.C. 4370m(3).
(b) ``CAP Goals'' means Federal Government Priority
Goals established by the Government Performance and
Results Act (GPRA) Modernization Act of 2010, Public
Law 111-352, 124 Stat. 3866, and commonly referred to
as Cross-Agency Priority (CAP) Goals.
(c) ``Federal Permitting Improvement Steering
Council'' or ``FPISC'' means the entity established
under 42 U.S.C. 4370m-1.
(d) ``Infrastructure project'' means a project to
develop the public and private physical assets that are
designed to provide or support services to the general
public in the following sectors: surface
transportation, including roadways, bridges, railroads,
and transit; aviation; ports, including navigational
channels; water resources projects; energy production
and generation, including from fossil, renewable,
nuclear, and hydro sources; electricity transmission;
broadband Internet; pipelines; stormwater and sewer
infrastructure; drinking water infrastructure; and
other sectors as may be determined by the FPISC.
(e) ``Major infrastructure project'' means an
infrastructure project for which multiple
authorizations by Federal agencies will be required to
proceed with construction, the lead Federal agency has
determined that it will prepare an environmental impact
statement (EIS) under the National Environmental Policy
Act (NEPA), 42 U.S.C. 4321 et seq., and the project
sponsor has identified the reasonable availability of
funds sufficient to complete the project.
(f) ``Permitting timetable'' means an environmental
review and authorization schedule, or other equivalent
schedule, for a project or group of projects that
identifies milestones--including intermediate and final
completion dates for action by each agency on any
Federal environmental review or authorization required
for a project or group of projects--that is prepared by
the lead Federal agency in consultation with all
cooperating and participating agencies.
Sec. 4. Agency Performance Accountability. Federal
agencies should follow transparent and coordinated
processes for conducting environmental reviews and
making authorization decisions. These processes must
include early and open coordination among Federal,
State, tribal, and local agencies and early engagement
with the public. Holding Federal agencies accountable
for their progress on implementing the policy set forth
in section 2 of this order should, among other things,
produce measurably better environmental outcomes with
respect to infrastructure development.
(a) Performance Priority Goals.
(i) CAP Goal. A CAP Goal is a Federal tool for accelerating progress in
priority areas that require active collaboration among multiple agencies to
overcome organizational barriers and to achieve better performance than one
agency could achieve on its own. Within 180 days of the date of this order,
the Director of the Office of Management and Budget (OMB), in consultation
with the FPISC, shall establish a CAP Goal on Infrastructure Permitting
Modernization so that, where permitted by law:
(A) Federal environmental reviews and authorization processes for
infrastructure projects are consistent, coordinated, and predictable; and
(B) the time for the Federal Government's processing of environmental
reviews and authorization decisions for new major infrastructure projects
should be reduced to not more than an average of approximately 2 years,
measured from the date of the publication of a notice of intent to prepare
an environmental impact statement or other benchmark deemed appropriate by
the Director of OMB.
(ii) Agency Goals. All Federal agencies with environmental review,
authorization, or consultation responsibilities for infrastructure projects
shall modify their Strategic Plans and Annual Performance Plans under the
[[Page 40465]]
GPRA Modernization Act of 2010 to include agency performance goals related
to the completion of environmental reviews and authorizations for
infrastructure projects consistent with the new CAP Goal on Infrastructure
Permitting Modernization. The agencies shall integrate the achievement of
these performance goals into appropriate agency personnel performance
plans, such as those of the agency Chief Environmental Review and
Permitting Officers (CERPOs) or other appropriate officials, consistent
with guidance to be provided by OMB, in consultation with the Office of
Personnel Management. Progress on these goals shall be reviewed and
analyzed by agency leadership, pursuant to the GPRA Modernization Act of
2010.
(b) Accountability. Within 180 days of the
establishment of the CAP Goal on Infrastructure
Permitting Modernization, as described in subsection
(a) of this section, or such longer period of time as
determined by the Director of OMB, OMB, in consultation
with the FPISC, shall issue guidance for establishing a
performance accountability system to facilitate
achievement of the CAP Goal.
(i) Tracking of Major Infrastructure Projects. The performance
accountability system shall track each major infrastructure project. The
performance accountability system shall include, at a minimum, assessments
of the agency's performance with respect to each of the following areas, as
applicable:
(A) whether major infrastructure projects are processed using the ``One
Federal Decision'' mechanism, as described in subsection 5(b) of this
order;
(B) whether major infrastructure projects have a permitting timetable;
(C) whether major infrastructure projects follow an effective process
that automatically elevates instances in which permitting timetable
milestones are missed or extended, or are anticipated to be missed or
extended, to appropriate senior agency officials;
(D) whether agencies are meeting the established milestones in the
permitting timetable;
(E) the time it takes to complete the processing of environmental reviews
and authorizations for each major infrastructure project; and
(F) the costs of the environmental reviews and authorizations for each
major infrastructure project.
(ii) Scoring. The accountability system shall include a scoring mechanism
that shall follow, at a minimum, the following procedures:
(A) agencies will submit information to OMB, consistent with existing
reporting mechanisms to the maximum extent possible, on the assessment
areas described in subsection (b)(i) of this section;
(B) at least once per quarter, OMB will produce a scorecard of agency
performance and overall progress toward achieving CAP Goal targets;
(C) where an agency's inability to meet a permitting timetable milestone
results in a significant delay of the project timeline, after consulting
with the project sponsor and relevant agencies, agencies will submit (based
on OMB guidance) an estimate of the delay's costs to the project; and
(D) the Director of OMB will consider each agency's performance during
budget formulation and determine whether appropriate penalties, including
those authorized at 23 U.S.C. 139(h)(7) and 33 U.S.C. 2348(h)(5), must or
should be imposed, to the extent required or permitted by law, for those
that significantly fail to meet a permitting timetable milestone or in
other situations deemed appropriate by the Director of OMB after
considering the causes of any poor performance.
(iii) Best Practices. Agencies shall implement the techniques and
strategies the FPISC annually identifies as best practices pursuant to 42
U.S.C. 4370m-1(c)(2)(B), as appropriate. The performance accountability
system
[[Page 40466]]
shall track and score agencies on the incorporation and implementation of
appropriate best practices for all infrastructure projects, including the
implementation of such best practices at an agency's field level.
Sec. 5. Process Enhancements. In furtherance of the
policy described in section 2 of this order, Federal
agencies shall follow a more unified environmental
review and authorization process.
(a) Processing of Major Infrastructure Projects. In
processing environmental reviews and authorizations for
major infrastructure projects, Federal agencies shall:
(i) use ``One Federal Decision'' described in subsection (b) of this
section;
(ii) develop and follow a permitting timetable, which shall be reviewed and
updated at least quarterly by the lead Federal agency in consultation with
Federal cooperating and participating agencies; and
(iii) follow an effective process that automatically elevates instances
where a permitting timetable milestone is missed or extended, or is
anticipated to be missed or extended, to appropriate senior agency
officials of the lead Federal agency and the cooperating and participating
Federal agency or agencies to which the milestone applies.
(b) One Federal Decision.
(i) Each major infrastructure project shall have a lead Federal agency,
which shall be responsible for navigating the project through the Federal
environmental review and authorization process, including the
identification of a primary Federal point of contact at each Federal
agency. All Federal cooperating and participating agencies shall identify
points of contact for each project, cooperate with the lead Federal agency
point of contact, and respond to all reasonable requests for information
from the lead Federal agency in a timely manner.
(ii) With respect to the applicability of NEPA to a major infrastructure
project, the Federal lead, cooperating, and participating agencies for each
major infrastructure project shall all record any individual agency
decision in one Record of Decision (ROD), which shall be coordinated by the
lead Federal agency unless the project sponsor requests that agencies issue
separate NEPA documents, the NEPA obligations of a cooperating or
participating agency have already been satisfied, or the lead Federal
agency determines that a single ROD would not best promote completion of
the project's environmental review and authorization process. The Federal
lead, cooperating, and participating agencies shall all agree to a
permitting timetable that includes the completion dates for the ROD and the
federally required authorizations for the project.
(iii) All Federal authorization decisions for the construction of a major
infrastructure project shall be completed within 90 days of the issuance of
a ROD by the lead Federal agency, provided that the final EIS includes an
adequate level of detail to inform agency decisions pursuant to their
specific statutory authority and requirements. The lead Federal agency may
extend the 90-day deadline if the lead Federal agency determines that
Federal law prohibits the agency from issuing its approval or permit within
the 90-day period, the project sponsor requests that the permit or approval
follow a different timeline, or the lead Federal agency determines that an
extension would better promote completion of the project's environmental
review and authorization process.
(iv) The Council on Environmental Quality (CEQ) and OMB shall develop the
framework for implementing One Federal Decision, in consultation with the
FPISC.
(A) The framework should be consistent with the model processes
established under 42 U.S.C. 4370m-2, 23 U.S.C. 139, 33 U.S.C. 2348, the
2015 ``Red Book'' (officially entitled ``Synchronizing Environmental
Reviews for Transportation and Other Infrastructure Projects''), and CEQ
guidance on efficient and timely environmental reviews under NEPA.
[[Page 40467]]
(B) The framework shall also include guidance on the development of
permitting timetables by the lead Federal agencies, in collaboration with
Federal cooperating and participating agencies. Permitting timetables shall
identify estimated intermediate and final completion dates for all
environmental reviews and authorizations that are reasonably anticipated as
being needed for a project, including the process for granting extensions
of any established dates. The guidance shall specify that lead Federal
agencies need not include the estimated intermediate and final completion
dates of any such reviews or authorizations until the design of a project
has sufficiently advanced so that they can be developed. In such cases, the
guidance shall instruct lead Federal agencies to estimate when the
project's design will be advanced enough to determine such dates. The
timelines shall account for any federally required decisions or permits
that are assumed by, or delegated to, State, tribal, or local agencies and
the extent to which any approval or permit to be issued by a Federal agency
is dependent upon the issuance of such a decision or permit.
(C) CEQ and OMB shall also develop guidance for applying One Federal
Decision whenever the lead agency is a State, tribal, or local agency
exercising an assignment or delegation of an agency's NEPA
responsibilities.
(c) Dashboard. All projects subject to 23 U.S.C.
139 and ``covered projects'' under 42 U.S.C. 4370m
shall be tracked on the Dashboard established under 42
U.S.C. 4370m-2(b). Other projects or classes of
projects subject to special environmental review and
authorization streamlining processes similar to those
referenced in this subsection may also be tracked on
the Dashboard at the discretion of the FPISC Executive
Director. The dates for milestones of all projects
tracked on the Dashboard shall be updated monthly, or
on another appropriate timeline as may be determined by
the FPISC Executive Director.
(d) Executive Order 13766. For purposes of
implementing Executive Order 13766 of January 24, 2017
(Expediting Environmental Reviews and Approvals for
High Priority Infrastructure Projects), all
infrastructure projects that meet the criteria for, and
are subject to, 23 U.S.C. 139, 33 U.S.C. 2348, or 42
U.S.C. 4370m-4370m-12 shall qualify as high priority
projects under Executive Order 13766. Other projects or
classes of projects subject to special environmental
review and authorization streamlining processes,
similar to those referenced in this subsection as may
be determined by the FPISC Executive Director in
consultation with OMB and CEQ, shall also qualify as
high priority infrastructure projects under Executive
Order 13766. The CEQ Chairman's responsibilities under
sections 2 and 3 of Executive Order 13766 shall be
satisfied by referring the project to the FPISC
Executive Director, the Secretary of Transportation, or
the Assistant Secretary of the Army for Civil Works, as
appropriate.
(e) Council on Environmental Quality.
(i) Directives. Within 30 days of the date of this order, the CEQ shall
develop an initial list of actions it will take to enhance and modernize
the Federal environmental review and authorization process. Such actions
should include issuing such regulations, guidance, and directives as CEQ
may deem necessary to:
(A) ensure optimal interagency coordination of environmental review and
authorization decisions, including by providing for an expanded role and
authorities for lead agencies, more clearly defined responsibilities for
cooperating and participating agencies, and Government-wide applicability
of NEPA decisions and analyses;
(B) ensure that environmental reviews and authorization decisions
involving multiple agencies are conducted in a manner that is concurrent,
synchronized, timely, and efficient;
(C) provide for agency use, to the maximum extent permitted by law, of
environmental studies, analysis, and decisions conducted in support
[[Page 40468]]
of earlier Federal, State, tribal, or local environmental reviews or
authorization decisions; and
(D) ensure that agencies apply NEPA in a manner that reduces unnecessary
burdens and delays as much as possible, including by using CEQ's authority
to interpret NEPA to simplify and accelerate the NEPA review process.
(ii) Dispute Resolution. Except where dispute resolution processes are
otherwise provided for in law, including under 42 U.S.C. 4370m-2, or by
Executive Order or other Presidential directive, upon request of a lead
Federal agency, cooperating agency, or participating agency, CEQ may
mediate interagency disputes arising between Federal agencies concerning
Federal environmental review or authorization decisions for any
infrastructure project pertaining to any environmental law, regulation,
order or policy, and shall facilitate resolution of any conflicting
positions of the relevant agencies.
(iii) Agency Procedures. CEQ shall form and lead an interagency working
group, consisting of the Director of OMB, agency CERPOs, and such other
representatives of agencies as CEQ deems appropriate. The working group
shall review the NEPA implementing regulations and other environmental
review and authorization processing policies of agencies that are members
of the FPISC to identify impediments to efficient and effective
environmental reviews and authorizations for infrastructure projects. The
working group shall also identify those agencies that require an action
plan to address identified impediments. Based on this review, agencies
shall develop action plans that set forth the actions they will take and
timelines for completing those actions, and they shall submit those action
plans to CEQ and OMB for comment. Each agency's action plan shall, at a
minimum, establish procedures for a regular review and update of
categorical exclusions, where appropriate.
(f) Federal Permitting Improvement Steering
Council.
(i) Organizational Support. Unless otherwise determined by the Director of
OMB, the General Services Administration (GSA) shall provide necessary
administrative and organizational support to the FPISC, including
personnel, procurement, and budget support. The GSA Administrator, or the
head of another agency designated by the Director of OMB, may delegate any
authority to the FPISC Executive Director necessary for the operation and
administration of the FPISC and the Office of the Executive Director, and
the Executive Director may redelegate these authorities, as appropriate.
(ii) Additional Duties. In addition to the duties and responsibilities
charged to the FPISC Executive Director under 42 U.S.C. 4370m-4370m-12 and
this order, the FPISC Executive Director may, upon request of a FPISC
member agency or a project sponsor, work with the lead agency or any
cooperating and participating agencies to facilitate the environmental
review and authorization process for any infrastructure project regardless
of whether the project is a ``covered project'' under 42 U.S.C. 4370m,
including by resolving disputes and promoting early coordination. The FPISC
Executive Director, the Director of OMB, or the Chairman of CEQ may
establish any appropriate policies or procedures concerning the FPISC
Executive Director's facilitation of the environmental review and
authorization process under this subsection. Agencies must cooperate with
the FPISC Executive Director with respect to the implementation of these
additional duties.
(g) Energy Corridors. The Departments of the
Interior and Agriculture, as appropriate, shall be the
lead agencies for facilitating the identification and
designation of energy right-of-way corridors on Federal
lands for Government-wide expedited environmental
review for the development of energy infrastructure
projects.
(h) The Department of the Interior shall provide to
OMB a strategy and recommendations for a multi-agency
reorganization effort that would further
[[Page 40469]]
the aims of this order. OMB, in consultation with the
Department of the Interior, shall coordinate with the
heads of other agencies affected to incorporate the
strategy, as appropriate, into the comprehensive
reorganization plan developed under Executive Order
13781 of March 13, 2017 (Comprehensive Plan for
Reorganizing the Executive Branch).
Sec. 6. Executive Order 13690 of January 30, 2015
(Establishing a Federal Flood Risk Management Standard
and a Process for Further Soliciting and Considering
Stakeholder Input), is revoked.
Sec. 7. General Provisions. (a) Nothing in this order
shall be construed to impair or otherwise affect:
(i) the authority granted by law to an executive department, agency, or the
head thereof; or
(ii) the functions of the Director of the Office of Management and Budget
relating to budgetary, administrative, or legislative proposals.
(b) This order shall be implemented consistent with
applicable law and subject to the availability of
appropriations.
(c) This order is not intended to, and does not,
create any right or benefit, substantive or procedural,
enforceable at law or in equity by any party against
the United States, its departments, agencies, or
entities, its officers, employees, or agents, or any
other person.
(Presidential Sig.)
THE WHITE HOUSE,
August 15, 2017.
[FR Doc. 2017-18134