Federal Register / Vol. 82, No. 154 / Friday, August 11, 2017 / Notices
FERC–717, OPEN ACCESS SAME-TIME INFORMATION SYSTEM AND STANDARDS FOR BUSINESS PRACTICES &
COMMUNICATION PROTOCOLS
Number of
respondents
Total number
of
responses
Average
burden hours
and cost per
response 2
Total annual
burden hours
and
total annual
cost
(1)
Information collection requirements
Annual
number of
responses
per
respondent
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
FERC–717 ...........................................................................
Comments: Comments are invited on:
(1) Whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: August 7, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–16959 Filed 8–10–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
asabaliauskas on DSKBBXCHB2PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER13–1966–001.
Applicants: NRG Wholesale
Generation LP.
Description: Compliance filing:
Informational Filing Regarding Planned
Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807–5112.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER15–2572–004.
Applicants: GenOn Energy
Management, LLC.
Description: Compliance filing:
Informational Filing Regarding Planned
Transfer to be effective N/A.
2 The Commission staff thinks that the average
respondent for this collection is similarly situated
to the Commission, in terms of salary plus benefits.
Based upon FERC’s 2017 annual average of
$158,754 (for salary plus benefits), the average
hourly cost is $76.50/hour.
VerDate Sep<11>2014
17:18 Aug 10, 2017
Jkt 241001
170
1
Filed Date: 8/7/17.
Accession Number: 20170807–5108.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER15–2573–004.
Applicants: GenOn Energy
Management, LLC.
Description: Compliance filing:
Informational Filing Regarding Planned
Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807–5109.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16–209–004.
Applicants: Southwest Power Pool,
Inc.
Description: Compliance filing:
Central Power Electric Cooperative
Formula Rate Compliance Filing to be
effective 1/1/2016.
Filed Date: 8/7/17.
Accession Number: 20170807–5144.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16–1774–003.
Applicants: Southwest Power Pool,
Inc.
Description: Compliance filing:
Western Farmers Electric Cooperative
Formula Rate Compliance Filing to be
effective 7/1/2016.
Filed Date: 8/7/17.
Accession Number: 20170807–5152.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16–2665–003.
Applicants: NRG Power Midwest LP.
Description: Compliance filing:
Informational Filing Regarding Planned
Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807–5111.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–274–002.
Applicants: GenOn Energy
Management, LLC.
Description: Compliance filing:
Informational Filing Regarding Planned
Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807–5110.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–1342–001.
Applicants: Duke Energy Florida,
LLC, Duke Energy Carolinas, LLC.
Description: Compliance filing:
Correct Loss Factor Tariff Records to be
effective 5/1/2017.
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
170
30
$2,295
5,100
$390,150
Filed Date: 8/7/17.
Accession Number: 20170807–5077.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2250–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2017–08–07_SA 2523 ITC-Pheasant Run
4th Revised GIA (J075 J466) to be
effective 7/24/2017.
Filed Date: 8/7/17.
Accession Number: 20170807–5078.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2251–000.
Applicants: GenOn Energy
Management, LLC.
Description: § 205(d) Rate Filing: Rate
Schedule FERC No. 1 to be effective
9/1/2017.
Filed Date: 8/7/17.
Accession Number: 20170807–5093.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2252–000.
Applicants: NRG Power Marketing
LLC.
Description: § 205(d) Rate Filing: Rate
Schedule FERC No. 1 to be effective
9/1/2017.
Filed Date: 8/7/17.
Accession Number: 20170807–5094.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2253–000.
Applicants: NorthWestern
Corporation.
Description: NorthWestern
Corporation submits Average System
Cost Filing for Sales of Electric Power to
the Bonneville Power Administration,
FY 2018–2019.
Filed Date: 8/7/17.
Accession Number: 20170807–5121.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2254–000.
Applicants: Southern California
Edison Company.
Description: Tariff Cancellation:
Notices of Cancellation IFA & DSA Mid
Valley Landfill Project SA Nos. 73 & 74
to be effective 12/3/2017.
Filed Date: 8/7/17.
Accession Number: 20170807–5127.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17–2255–000.
Applicants: PJM Interconnection,
L.L.C.
E:\FR\FM\11AUN1.SGM
11AUN1
37582
Federal Register / Vol. 82, No. 154 / Friday, August 11, 2017 / Notices
Description: § 205(d) Rate Filing:
Original Service Agreement No. 4758,
Queue Position No. AA2–177 to be
effective 7/10/2017.
Filed Date: 8/7/17.
Accession Number: 20170807–5139.
Comments Due: 5 p.m. ET 8/28/17.
Take notice that the Commission
received the following qualifying
facility filings:
Docket Numbers: QF17–1266–000.
Applicants: Escondido Bioenergy
Facilty, LLC.
Description: Form 556 of Escondido
Bioenergy Facilty, LLC.
Filed Date: 8/3/17.
Accession Number: 20170803–5043.
Comments Due: None Applicable.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: August 7, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–16958 Filed 8–10–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14851–000]
asabaliauskas on DSKBBXCHB2PROD with NOTICES
White Pine Waterpower, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On July 13, 2017, White Pine
Waterpower, LLC, filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the White Pine Pumped Storage
Project to be located near the town of
Ely in White Pine, Nevada. The sole
purpose of a preliminary permit, if
VerDate Sep<11>2014
17:18 Aug 10, 2017
Jkt 241001
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The applicant proposes to study two
alternative closed-loop pumped storage
alternatives at the site: One sized to 250
megawatts (MW) and the other to 500
MW. The 500-MW alternative would
consist of the following: (1) A new
upper reservoir with a surface area of 52
acres and a storage capacity of 2,400
acre-feet at a surface elevation of
approximately 8,530 feet above mean
sea level (msl) created through
construction of a new earth or rockfilled dam; (2) a new lower reservoir
with a surface area of 40 acres and a
total storage capacity of 2,400 acre-feet
at a surface elevation of 6,290 feet msl;
(3) 10,600 feet of tunnel and penstock
connecting the upper and lower
reservoirs; (5) a new underground
powerhouse containing three turbinegenerator units; (6) a new 1.5 mile
transmission line connecting the
powerhouse to a nearby electric grid
interconnection, (7) appurtenant
facilities. The 500-MW alternative
would have an annual generation of
502,717 megawatt-hours (MWh).
For the 250-MW alternative, the new
upper and lower reservoirs would be
sized to have half of the storage of the
500-MW alternative (1,200 acre-feet),
reducing the dam size needed to
impound the reservoirs. The alternative
would require 11,700 feet of tunnel and
penstock and have 2 pump-generating
units. The 250-MW alternative would
require the same transmission line and
would have an estimated annual
generation of 547,500 MWh.
Applicant Contact: Matthew Shapiro,
CEO, Gridflex Energy, LLC, 1210 W.
Franklin Street, Suite 2, Boise, ID 83702.
FERC Contact: Jim Fargo; phone: (202)
502–6095.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14851–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the eLibrary
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14851) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: August 7, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–16960 Filed 8–10–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC17–151–000.
Applicants: Waverly Wind Farm LLC.
Description: Application for
Authorization for Disposition of
Jurisdictional Facilities and Request for
Expedited Action of Waverly Wind
Farm LLC.
Filed Date: 8/4/17.
Accession Number: 20170804–5211.
Comments Due: 5 p.m. ET 8/25/17.
Docket Numbers: EC17–152–000.
Applicants: GenOn Energy, Inc.
Description: Application of GenOn
Energy, Inc. and Its Public Utility
Subsidiaries for Approval Under
Section 203 of the Federal Power Act
and Request for Expedited Action.
Filed Date: 8/4/17.
Accession Number: 20170804–5214.
Comments Due: 5 p.m. ET 8/25/17.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER16–328–004;
ER10–2196–004; ER10–2740–012; ER10–
2742–011; ER11–4027–009; ER13–1143–
005; ER13–1144–005; ER14–152–008;
ER15–1657–005; ER17–1849–001.
Applicants: Cogentrix Virginia
Financing Holding Com, Elgin Energy
E:\FR\FM\11AUN1.SGM
11AUN1
Agencies
[Federal Register Volume 82, Number 154 (Friday, August 11, 2017)]
[Notices]
[Pages 37581-37582]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-16958]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #2
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER13-1966-001.
Applicants: NRG Wholesale Generation LP.
Description: Compliance filing: Informational Filing Regarding
Planned Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807-5112.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER15-2572-004.
Applicants: GenOn Energy Management, LLC.
Description: Compliance filing: Informational Filing Regarding
Planned Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807-5108.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER15-2573-004.
Applicants: GenOn Energy Management, LLC.
Description: Compliance filing: Informational Filing Regarding
Planned Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807-5109.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16-209-004.
Applicants: Southwest Power Pool, Inc.
Description: Compliance filing: Central Power Electric Cooperative
Formula Rate Compliance Filing to be effective 1/1/2016.
Filed Date: 8/7/17.
Accession Number: 20170807-5144.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16-1774-003.
Applicants: Southwest Power Pool, Inc.
Description: Compliance filing: Western Farmers Electric
Cooperative Formula Rate Compliance Filing to be effective 7/1/2016.
Filed Date: 8/7/17.
Accession Number: 20170807-5152.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER16-2665-003.
Applicants: NRG Power Midwest LP.
Description: Compliance filing: Informational Filing Regarding
Planned Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807-5111.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-274-002.
Applicants: GenOn Energy Management, LLC.
Description: Compliance filing: Informational Filing Regarding
Planned Transfer to be effective N/A.
Filed Date: 8/7/17.
Accession Number: 20170807-5110.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-1342-001.
Applicants: Duke Energy Florida, LLC, Duke Energy Carolinas, LLC.
Description: Compliance filing: Correct Loss Factor Tariff Records
to be effective 5/1/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5077.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2250-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2017-08-07_SA 2523 ITC-
Pheasant Run 4th Revised GIA (J075 J466) to be effective 7/24/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5078.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2251-000.
Applicants: GenOn Energy Management, LLC.
Description: Sec. 205(d) Rate Filing: Rate Schedule FERC No. 1 to
be effective 9/1/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5093.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2252-000.
Applicants: NRG Power Marketing LLC.
Description: Sec. 205(d) Rate Filing: Rate Schedule FERC No. 1 to
be effective 9/1/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5094.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2253-000.
Applicants: NorthWestern Corporation.
Description: NorthWestern Corporation submits Average System Cost
Filing for Sales of Electric Power to the Bonneville Power
Administration, FY 2018-2019.
Filed Date: 8/7/17.
Accession Number: 20170807-5121.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2254-000.
Applicants: Southern California Edison Company.
Description: Tariff Cancellation: Notices of Cancellation IFA & DSA
Mid Valley Landfill Project SA Nos. 73 & 74 to be effective 12/3/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5127.
Comments Due: 5 p.m. ET 8/28/17.
Docket Numbers: ER17-2255-000.
Applicants: PJM Interconnection, L.L.C.
[[Page 37582]]
Description: Sec. 205(d) Rate Filing: Original Service Agreement
No. 4758, Queue Position No. AA2-177 to be effective 7/10/2017.
Filed Date: 8/7/17.
Accession Number: 20170807-5139.
Comments Due: 5 p.m. ET 8/28/17.
Take notice that the Commission received the following qualifying
facility filings:
Docket Numbers: QF17-1266-000.
Applicants: Escondido Bioenergy Facilty, LLC.
Description: Form 556 of Escondido Bioenergy Facilty, LLC.
Filed Date: 8/3/17.
Accession Number: 20170803-5043.
Comments Due: None Applicable.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: August 7, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-16958 Filed 8-10-17; 8:45 am]