Florida Gas Transmission Company, L.L.C.; Notice of Revised Schedule for Environmental Review of the Wekiva Parkway Relocation Project, 37205-37206 [2017-16746]
Download as PDF
Federal Register / Vol. 82, No. 152 / Wednesday, August 9, 2017 / Notices
Dated: August 3, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–16749 Filed 8–8–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2590–061]
sradovich on DSK3GMQ082PROD with NOTICES
Consolidated Water Power Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Amendment of
license to change project boundary.
b. Project No: 2590–061.
c. Date Filed: June 6, 2017.
d. Applicant: Consolidated Water
Power Company.
e. Name of Project: Whiting
Hydroelectric Project.
f. Location: The project is located on
the Wisconsin River in Portage County,
Wisconsin.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Thomas J. Witt,
Consolidated Water Power Company,
610 High St., P.O. Box 8050, Wisconsin
Rapids, WI 54495–8050, (715) 422–
3927.
i. FERC Contact: Hillary Berlin, (202)
502–8915, hillary.berlin@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
August 31, 2017.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–2590–061.
Comments emailed to Commission staff
VerDate Sep<11>2014
17:00 Aug 08, 2017
Jkt 241001
are not considered part of the
Commission record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request:
Consolidated Water Power Company
(licensee) filed for Commission approval
an application to remove 65 acres of
land on the east side of the Wisconsin
River from the project boundary. These
lands were formerly utilized for
industrial purposes, and currently serve
no project purpose. The licensee will
also obtain ownership of 217 acres of
land already within the project
boundary, 25 of which are located along
the eastern shoreline. The licensee will
relocate a portion of the Green Circle
State Trail from the lands removed from
the boundary to a portion of this land
along the shoreline.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above. Agencies may obtain copies of
the application directly from the
applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
37205
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title COMMENTS, PROTEST,
or MOTION TO INTERVENE as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person commenting,
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, motions to intervene, or
protests must set forth their evidentiary
basis. Any filing made by an intervenor
must be accompanied by proof of
service on all persons listed in the
service list prepared by the Commission
in this proceeding, in accordance with
18 CFR 385.2010.
Dated: August 1, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–16750 Filed 8–8–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–79–000]
Florida Gas Transmission Company,
L.L.C.; Notice of Revised Schedule for
Environmental Review of the Wekiva
Parkway Relocation Project
This notice identifies the Federal
Energy Regulatory Commission staff’s
revised schedule for the completion of
the environmental assessment (EA) for
the Florida Gas Transmission Company,
L.L.C. (Florida Gas) Wekiva Parkway
Relocation Project. The first notice of
schedule, issued on June 7, 2017,
identified July 28, 2017 as the EA
issuance date. However, due to
additional environmental information to
be filed by Florida Gas since issuance of
the June 7, 2017 Scheduling Notice, the
Commission staff requires more time to
complete our review. As a result, staff
has revised the schedule for issuance of
the EA, to allow for time to incorporate
supplemental information into the final
document.
E:\FR\FM\09AUN1.SGM
09AUN1
37206
Federal Register / Vol. 82, No. 152 / Wednesday, August 9, 2017 / Notices
Schedule for Environmental Review
Issuance of Notice of Availability of
EA: September 14, 2017.
90-day Federal Authorization
Decision Deadline: December 13, 2017.
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription
(www.ferc.gov/docs-filing/
esubscription.asp).
Dated: July 27, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–16746 Filed 8–8–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14819–000]
sradovich on DSK3GMQ082PROD with NOTICES
Merchant Hydro Developers, LLC;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 18, 2017, Merchant Hydro
Developers, LLC, filed an application for
a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the Allamuchy Pumped Storage
Hydroelectric Project to be located near
the town of Budd Lake, New Jersey in
Morris County, New Jersey. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following: (1) A new upper reservoir
with a surface area of 70 acres and a
storage capacity of 1,050 acre-feet at a
surface elevation of approximately 1,150
feet above mean sea level (msl) created
through construction of a new rollercompacted concrete or rock-filled dam;
(2) excavating a new lower reservoir
with a surface area of 39 acres and a
total storage capacity of 1,260 acre-feet
at a surface elevation of 780 feet msl; (3)
VerDate Sep<11>2014
17:00 Aug 08, 2017
Jkt 241001
a new 1,328-foot-long, 48-inch-diameter
penstock connecting the upper and
lower reservoirs; (4) a new 150-footlong, 50-foot-wide powerhouse
containing two turbine-generator units
with a total rated capacity of 32
megawatts; (5) a new transmission line
connecting the powerhouse to a nearby
electric grid interconnection point with
options to evaluate multiple grid
interconnection locations; and (6)
appurtenant facilities. Possible initial
fill water and make-up water would
come from the Musconetcong River. The
proposed project would have an annual
generation of 116,253 megawatt-hours.
Applicant Contact: Adam Rousselle,
Merchant Hydro Developers, LLC, 5710
Oak Crest Drive, Doylestown, PA 18902;
phone: (267) 254–6107.
FERC Contact: Tim Looney; phone:
(202) 502–6096.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.1
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–14819–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the eLibrary
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14819) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
1 The Commission is issuing a second notice for
this project because some municipalities may not
have been notified by the first notice issued on May
25, 2017.
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
Dated: August 3, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–16748 Filed 8–8–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP17–363–002.
Applicants: Eastern Shore Natural Gas
Company.
Description: Eastern Shore Natural
Gas Company submits tariff filing per
154.203: Motion to Place Suspended
Tariff Sheets into Effect to be effective
8/1/2017.
Filed Date: 07/31/2017.
Accession Number: 20170731–5263.
Comment Date: 5:00 p.m. Eastern
Time on Monday, August 14, 2017.
Docket Numbers: RP17–927–000.
Applicants: Gulf South Pipeline
Company, LP.
Description: Gulf South Pipeline
Company, LP submits tariff filing per
154.204: Cap Rel Neg Rate Agmt
(Petrohawk 41455 to Texla 48436) to be
effective 8/1/2017.
Filed Date: 07/31/2017.
Accession Number: 20170731–5101.
Comment Date: 5:00 p.m. Eastern
Time on Monday, August 14, 2017.
Docket Numbers: RP17–928–000.
Applicants: Great Lakes Gas
Transmission Limited Par.
Description: Great Lakes Gas
Transmission Limited Partnership SemiAnnual Transporter’s Use Report.
Filed Date: 07/31/2017.
Accession Number: 20170731–5125.
Comment Date: 5:00 p.m. Eastern
Time on Monday, August 14, 2017.
Docket Numbers: RP17–929–000.
Applicants: Dominion Energy
Overthrust Pipeline, LLC.
Description: Annual Fuel Gas
Reimbursement Report for 2017 of
Dominion Energy Overthrust Pipeline,
LLC.
Filed Date: 07/31/2017.
Accession Number: 20170731–5126.
Comment Date: 5:00 p.m. Eastern
Time on Monday, August 14, 2017.
Docket Numbers: RP17–930–000.
Applicants: Algonquin Gas
Transmission, LLC.
Description: Algonquin Gas
Transmission, LLC submits tariff filing
E:\FR\FM\09AUN1.SGM
09AUN1
Agencies
[Federal Register Volume 82, Number 152 (Wednesday, August 9, 2017)]
[Notices]
[Pages 37205-37206]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-16746]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-79-000]
Florida Gas Transmission Company, L.L.C.; Notice of Revised
Schedule for Environmental Review of the Wekiva Parkway Relocation
Project
This notice identifies the Federal Energy Regulatory Commission
staff's revised schedule for the completion of the environmental
assessment (EA) for the Florida Gas Transmission Company, L.L.C.
(Florida Gas) Wekiva Parkway Relocation Project. The first notice of
schedule, issued on June 7, 2017, identified July 28, 2017 as the EA
issuance date. However, due to additional environmental information to
be filed by Florida Gas since issuance of the June 7, 2017 Scheduling
Notice, the Commission staff requires more time to complete our review.
As a result, staff has revised the schedule for issuance of the EA, to
allow for time to incorporate supplemental information into the final
document.
[[Page 37206]]
Schedule for Environmental Review
Issuance of Notice of Availability of EA: September 14, 2017.
90-day Federal Authorization Decision Deadline: December 13, 2017.
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription
(www.ferc.gov/docs-filing/esubscription.asp).
Dated: July 27, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-16746 Filed 8-8-17; 8:45 am]
BILLING CODE 6717-01-P