Florida Gas Transmission Company, L.L.C.; Notice of Revised Schedule for Environmental Review of the Wekiva Parkway Relocation Project, 37205-37206 [2017-16746]

Download as PDF Federal Register / Vol. 82, No. 152 / Wednesday, August 9, 2017 / Notices Dated: August 3, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–16749 Filed 8–8–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2590–061] sradovich on DSK3GMQ082PROD with NOTICES Consolidated Water Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Amendment of license to change project boundary. b. Project No: 2590–061. c. Date Filed: June 6, 2017. d. Applicant: Consolidated Water Power Company. e. Name of Project: Whiting Hydroelectric Project. f. Location: The project is located on the Wisconsin River in Portage County, Wisconsin. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Thomas J. Witt, Consolidated Water Power Company, 610 High St., P.O. Box 8050, Wisconsin Rapids, WI 54495–8050, (715) 422– 3927. i. FERC Contact: Hillary Berlin, (202) 502–8915, hillary.berlin@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: August 31, 2017. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–2590–061. Comments emailed to Commission staff VerDate Sep<11>2014 17:00 Aug 08, 2017 Jkt 241001 are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: Consolidated Water Power Company (licensee) filed for Commission approval an application to remove 65 acres of land on the east side of the Wisconsin River from the project boundary. These lands were formerly utilized for industrial purposes, and currently serve no project purpose. The licensee will also obtain ownership of 217 acres of land already within the project boundary, 25 of which are located along the eastern shoreline. The licensee will relocate a portion of the Green Circle State Trail from the lands removed from the boundary to a portion of this land along the shoreline. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 37205 Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title COMMENTS, PROTEST, or MOTION TO INTERVENE as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: August 1, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–16750 Filed 8–8–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–79–000] Florida Gas Transmission Company, L.L.C.; Notice of Revised Schedule for Environmental Review of the Wekiva Parkway Relocation Project This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for the Florida Gas Transmission Company, L.L.C. (Florida Gas) Wekiva Parkway Relocation Project. The first notice of schedule, issued on June 7, 2017, identified July 28, 2017 as the EA issuance date. However, due to additional environmental information to be filed by Florida Gas since issuance of the June 7, 2017 Scheduling Notice, the Commission staff requires more time to complete our review. As a result, staff has revised the schedule for issuance of the EA, to allow for time to incorporate supplemental information into the final document. E:\FR\FM\09AUN1.SGM 09AUN1 37206 Federal Register / Vol. 82, No. 152 / Wednesday, August 9, 2017 / Notices Schedule for Environmental Review Issuance of Notice of Availability of EA: September 14, 2017. 90-day Federal Authorization Decision Deadline: December 13, 2017. If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription (www.ferc.gov/docs-filing/ esubscription.asp). Dated: July 27, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–16746 Filed 8–8–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14819–000] sradovich on DSK3GMQ082PROD with NOTICES Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On January 18, 2017, Merchant Hydro Developers, LLC, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Allamuchy Pumped Storage Hydroelectric Project to be located near the town of Budd Lake, New Jersey in Morris County, New Jersey. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) A new upper reservoir with a surface area of 70 acres and a storage capacity of 1,050 acre-feet at a surface elevation of approximately 1,150 feet above mean sea level (msl) created through construction of a new rollercompacted concrete or rock-filled dam; (2) excavating a new lower reservoir with a surface area of 39 acres and a total storage capacity of 1,260 acre-feet at a surface elevation of 780 feet msl; (3) VerDate Sep<11>2014 17:00 Aug 08, 2017 Jkt 241001 a new 1,328-foot-long, 48-inch-diameter penstock connecting the upper and lower reservoirs; (4) a new 150-footlong, 50-foot-wide powerhouse containing two turbine-generator units with a total rated capacity of 32 megawatts; (5) a new transmission line connecting the powerhouse to a nearby electric grid interconnection point with options to evaluate multiple grid interconnection locations; and (6) appurtenant facilities. Possible initial fill water and make-up water would come from the Musconetcong River. The proposed project would have an annual generation of 116,253 megawatt-hours. Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC, 5710 Oak Crest Drive, Doylestown, PA 18902; phone: (267) 254–6107. FERC Contact: Tim Looney; phone: (202) 502–6096. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice.1 Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–14819–000. More information about this project, including a copy of the application, can be viewed or printed on the eLibrary link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14819) in the docket number field to access the document. For assistance, contact FERC Online Support. 1 The Commission is issuing a second notice for this project because some municipalities may not have been notified by the first notice issued on May 25, 2017. PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 Dated: August 3, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–16748 Filed 8–8–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP17–363–002. Applicants: Eastern Shore Natural Gas Company. Description: Eastern Shore Natural Gas Company submits tariff filing per 154.203: Motion to Place Suspended Tariff Sheets into Effect to be effective 8/1/2017. Filed Date: 07/31/2017. Accession Number: 20170731–5263. Comment Date: 5:00 p.m. Eastern Time on Monday, August 14, 2017. Docket Numbers: RP17–927–000. Applicants: Gulf South Pipeline Company, LP. Description: Gulf South Pipeline Company, LP submits tariff filing per 154.204: Cap Rel Neg Rate Agmt (Petrohawk 41455 to Texla 48436) to be effective 8/1/2017. Filed Date: 07/31/2017. Accession Number: 20170731–5101. Comment Date: 5:00 p.m. Eastern Time on Monday, August 14, 2017. Docket Numbers: RP17–928–000. Applicants: Great Lakes Gas Transmission Limited Par. Description: Great Lakes Gas Transmission Limited Partnership SemiAnnual Transporter’s Use Report. Filed Date: 07/31/2017. Accession Number: 20170731–5125. Comment Date: 5:00 p.m. Eastern Time on Monday, August 14, 2017. Docket Numbers: RP17–929–000. Applicants: Dominion Energy Overthrust Pipeline, LLC. Description: Annual Fuel Gas Reimbursement Report for 2017 of Dominion Energy Overthrust Pipeline, LLC. Filed Date: 07/31/2017. Accession Number: 20170731–5126. Comment Date: 5:00 p.m. Eastern Time on Monday, August 14, 2017. Docket Numbers: RP17–930–000. Applicants: Algonquin Gas Transmission, LLC. Description: Algonquin Gas Transmission, LLC submits tariff filing E:\FR\FM\09AUN1.SGM 09AUN1

Agencies

[Federal Register Volume 82, Number 152 (Wednesday, August 9, 2017)]
[Notices]
[Pages 37205-37206]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-16746]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-79-000]


Florida Gas Transmission Company, L.L.C.; Notice of Revised 
Schedule for Environmental Review of the Wekiva Parkway Relocation 
Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for the Florida Gas Transmission Company, L.L.C. 
(Florida Gas) Wekiva Parkway Relocation Project. The first notice of 
schedule, issued on June 7, 2017, identified July 28, 2017 as the EA 
issuance date. However, due to additional environmental information to 
be filed by Florida Gas since issuance of the June 7, 2017 Scheduling 
Notice, the Commission staff requires more time to complete our review. 
As a result, staff has revised the schedule for issuance of the EA, to 
allow for time to incorporate supplemental information into the final 
document.

[[Page 37206]]

Schedule for Environmental Review

    Issuance of Notice of Availability of EA: September 14, 2017.
    90-day Federal Authorization Decision Deadline: December 13, 2017.
    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription 
(www.ferc.gov/docs-filing/esubscription.asp).

    Dated: July 27, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-16746 Filed 8-8-17; 8:45 am]
 BILLING CODE 6717-01-P