Lower Saranac Hydro, LLC ; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 34308-34309 [2017-15432]
Download as PDF
34308
Federal Register / Vol. 82, No. 140 / Monday, July 24, 2017 / Notices
was the lack of supporting
documentation to substantiate costs
reported on the ‘‘Other Federal Agency
Cost Submission Form.’’
11. The cost reports that the
Commission determined were clearly
documented and supported could be
traced to detailed cost-accounting
reports, which reconciled to data
provided from agency financial systems
or other pertinent source
documentation. A further breakdown of
these costs is included in the Appendix
to this notice, along with an explanation
of how the Commission determined
their reasonableness.
Points of Contact
12. If you have any questions
regarding this notice, please contact
Norman Richardson at (202) 502–6219
or Raven Rodriquez at (202) 502–6276.
Dated: July 18, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–15431 Filed 7–21–17; 8:45 am]
BILLING CODE 6717–01–P
Dated: July 13, 2017.
Nathaniel J. Davis, Sr.
Deputy Secretary
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[FR Doc. 2017–15424 Filed 7–21–17; 8:45 am]
BILLING CODE 6717–01–P
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
mstockstill on DSK30JT082PROD with NOTICES
Filings Instituting Proceedings
Docket Numbers: RP17–896–000.
Applicants: Northern Natural Gas
Company.
Description: Northern Natural Gas
Company submits tariff filing per
154.204: 20170711 Remove Ft. Buford to
be effective 8/11/2017.
Filed Date: 07/11/2017.
Accession Number: 20170711–5099.
Comment Date: 5:00 p.m. Eastern
Time on Monday, July 24, 2017.
Docket Numbers: RP17–897–000.
Applicants: Algonquin Gas
Transmission, LLC.
Description: Algonquin Gas
Transmission, LLC submits tariff filing
per 154.204: Negotiated Rate and NonConforming—Narragansett—510985 to
be effective 7/17/2017.
Filed Date: 07/12/2017.
Accession Number: 20170712–5196.
Comment Date: 5:00 p.m. Eastern
Time on Monday, July 24, 2017.
Docket Numbers: RP17–899–000.
Applicants: OXY USA Inc.,
Occidental Energy Marketing, Inc., Hess
Corporation.
VerDate Sep<11>2014
18:13 Jul 21, 2017
Description: Joint Petition for
Temporary Waiver of Capacity Release
of OXY USA Inc., et al.
Filed Date: 07/12/2017.
Accession Number: 20170712–5203.
Comment Date: 5:00 p.m. Eastern
Time on Wednesday, July 19, 2017.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Jkt 241001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3511–023]
Lower Saranac Hydro, LLC ; Notice of
Intent To File License Application,
Filing of Pre-Application Document,
and Approving Use of the Traditional
Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 3511–023.
c. Date Filed: May 31, 2017.
d. Submitted By: Lower Saranac
Hydro, LLC.
e. Name of Project: Groveville
Hydroelectric Project.
f. Location: On Fishkill Creek near the
city of Beacon, New York. No federal
lands are occupied by the project works
or located within the project boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Mr.
Kevin M. Webb, Hydro Licensing
Manager, Lower Saranac Hydro, LLC,
100 Brickstone Square, Suite 300,
Andover, MA 01810; (978) 935–6039;
email:kevin.webb@enel.com.
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
i. FERC Contact: Chris Millard at
(202) 502–8256; or email at
christopher.millard@ferc.gov.
j. Lower Saranac Hydro, LLC filed a
request to use the Traditional Licensing
Process on May 31, 2017 and provided
public notice of the request on June 7,
2017. In a letter dated July 18, 2017, the
Director of the Division of Hydropower
Licensing approved Lower Saranac
Hydro, LLC’s request to use the
Traditional Licensing Process.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
New York State Historic Preservation
Officer, as required by section 106,
National Historic Preservation Act, and
the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Lower Saranac Hydro, LLC as the
Commission’s non-federal
representative for carrying out informal
consultation pursuant to section 7 of the
Endangered Species Act and section 106
of the National Historic Preservation
Act.
m. Lower Saranac Hydro, LLC filed a
Pre-Application Document (PAD;
including a proposed process plan and
schedule) with the Commission,
pursuant to 18 CFR 5.6 of the
Commission’s regulations.
n. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the eLibrary link.
Enter the docket number, excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at FERCONlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). A copy is also
available for inspection and
reproduction at the address in
paragraph h.
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 3511–023.
Pursuant to 18 CFR 16.8, 16.9, and
16.10, each application for a new
license and any competing license
applications must be filed with the
Commission at least 24 months prior to
the expiration of the existing license.
E:\FR\FM\24JYN1.SGM
24JYN1
Federal Register / Vol. 82, No. 140 / Monday, July 24, 2017 / Notices
All applications for license for this
project must be filed by May 31, 2020.
p. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: July 18, 2017.
Kimberly D. Bose,
Secretary.
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please
email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: 5:00 p.m. Eastern time
on August 11, 2017.
Dated: July 17, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–15432 Filed 7–21–17; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2017–15429 Filed 7–21–17; 8:45 am]
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. OR17–15–000]
mstockstill on DSK30JT082PROD with NOTICES
Western Refining Conan Gathering,
LLC; Notice of Petition for Declaratory
Order
Take notice that on July 12, 2017,
pursuant to Rule 207(a)(2) of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207(a)(2) (2016),
Western Refining Conan Gathering, LLC
(Western), filed a petition for a
declaratory order seeking approval of
the tariff rate structure and terms of
service for phase I of its proposed Conan
Crude Oil Gathering Pipeline System, as
more fully explained in the petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the eLibrary
link and is available for review in the
VerDate Sep<11>2014
18:13 Jul 21, 2017
Jkt 241001
Federal Energy Regulatory
Commission
[Docket No. CP17–469–000]
WBI Energy Transmission, Inc.; Notice
of Application
Take notice that on June 30, 2017,
WBI Energy Transmission, Inc. (WBI),
1250 West Century Avenue, Bismarck,
North Dakota 58503, filed in Docket No.
CP17–469–000, an application pursuant
to sections 7(b) and 7(c) of the Natural
Gas Act, requesting authorization for
abandonment of its Billy Creek Storage
Field, the associated injected and
recoverable native cushion gas and
associated facilities, as well as to
construct, install, modify and/or operate
certain pipeline facilities to facilitate the
withdrawal of the cushion gas prior to
the abandonment of the storage facilities
located in Johnson County, Wyoming,
all as more fully set forth in the
application which is on file with the
Commission and open to public
inspection. This filing may be viewed
on the web at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC at FERCOnlineSupport@ferc.gov
or call toll-free, (886)208–3676 or TYY,
(202) 502–8659.
Any questions regarding this
Application should be directed to Lori
Myerchin, Manager, Regulatory Affairs,
WBI Energy Transmission, Inc., 1250
West Century Avenue, Bismarck, North
Dakota 58503, (701) 530–1563 (email
lori.myerchin@wbienergy.com ).
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
34309
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
E:\FR\FM\24JYN1.SGM
24JYN1
Agencies
[Federal Register Volume 82, Number 140 (Monday, July 24, 2017)]
[Notices]
[Pages 34308-34309]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-15432]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3511-023]
Lower Saranac Hydro, LLC ; Notice of Intent To File License
Application, Filing of Pre-Application Document, and Approving Use of
the Traditional Licensing Process
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project No.: 3511-023.
c. Date Filed: May 31, 2017.
d. Submitted By: Lower Saranac Hydro, LLC.
e. Name of Project: Groveville Hydroelectric Project.
f. Location: On Fishkill Creek near the city of Beacon, New York.
No federal lands are occupied by the project works or located within
the project boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Mr. Kevin M. Webb, Hydro Licensing
Manager, Lower Saranac Hydro, LLC, 100 Brickstone Square, Suite 300,
Andover, MA 01810; (978) 935-6039; email:kevin.webb@enel.com.
i. FERC Contact: Chris Millard at (202) 502-8256; or email at
christopher.millard@ferc.gov.
j. Lower Saranac Hydro, LLC filed a request to use the Traditional
Licensing Process on May 31, 2017 and provided public notice of the
request on June 7, 2017. In a letter dated July 18, 2017, the Director
of the Division of Hydropower Licensing approved Lower Saranac Hydro,
LLC's request to use the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with
the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section
7 of the Endangered Species Act and the joint agency regulations
thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b)
of the Magnuson-Stevens Fishery Conservation and Management Act and
implementing regulations at 50 CFR 600.920. We are also initiating
consultation with the New York State Historic Preservation Officer, as
required by section 106, National Historic Preservation Act, and the
implementing regulations of the Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating Lower Saranac Hydro, LLC as
the Commission's non-federal representative for carrying out informal
consultation pursuant to section 7 of the Endangered Species Act and
section 106 of the National Historic Preservation Act.
m. Lower Saranac Hydro, LLC filed a Pre-Application Document (PAD;
including a proposed process plan and schedule) with the Commission,
pursuant to 18 CFR 5.6 of the Commission's regulations.
n. A copy of the PAD is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
(https://www.ferc.gov), using the eLibrary link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at
the address in paragraph h.
o. The licensee states its unequivocal intent to submit an
application for a new license for Project No. 3511-023. Pursuant to 18
CFR 16.8, 16.9, and 16.10, each application for a new license and any
competing license applications must be filed with the Commission at
least 24 months prior to the expiration of the existing license.
[[Page 34309]]
All applications for license for this project must be filed by May 31,
2020.
p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: July 18, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-15432 Filed 7-21-17; 8:45 am]
BILLING CODE 6717-01-P