Lower Saranac Hydro, LLC ; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 34308-34309 [2017-15432]

Download as PDF 34308 Federal Register / Vol. 82, No. 140 / Monday, July 24, 2017 / Notices was the lack of supporting documentation to substantiate costs reported on the ‘‘Other Federal Agency Cost Submission Form.’’ 11. The cost reports that the Commission determined were clearly documented and supported could be traced to detailed cost-accounting reports, which reconciled to data provided from agency financial systems or other pertinent source documentation. A further breakdown of these costs is included in the Appendix to this notice, along with an explanation of how the Commission determined their reasonableness. Points of Contact 12. If you have any questions regarding this notice, please contact Norman Richardson at (202) 502–6219 or Raven Rodriquez at (202) 502–6276. Dated: July 18, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–15431 Filed 7–21–17; 8:45 am] BILLING CODE 6717–01–P Dated: July 13, 2017. Nathaniel J. Davis, Sr. Deputy Secretary DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [FR Doc. 2017–15424 Filed 7–21–17; 8:45 am] BILLING CODE 6717–01–P Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: mstockstill on DSK30JT082PROD with NOTICES Filings Instituting Proceedings Docket Numbers: RP17–896–000. Applicants: Northern Natural Gas Company. Description: Northern Natural Gas Company submits tariff filing per 154.204: 20170711 Remove Ft. Buford to be effective 8/11/2017. Filed Date: 07/11/2017. Accession Number: 20170711–5099. Comment Date: 5:00 p.m. Eastern Time on Monday, July 24, 2017. Docket Numbers: RP17–897–000. Applicants: Algonquin Gas Transmission, LLC. Description: Algonquin Gas Transmission, LLC submits tariff filing per 154.204: Negotiated Rate and NonConforming—Narragansett—510985 to be effective 7/17/2017. Filed Date: 07/12/2017. Accession Number: 20170712–5196. Comment Date: 5:00 p.m. Eastern Time on Monday, July 24, 2017. Docket Numbers: RP17–899–000. Applicants: OXY USA Inc., Occidental Energy Marketing, Inc., Hess Corporation. VerDate Sep<11>2014 18:13 Jul 21, 2017 Description: Joint Petition for Temporary Waiver of Capacity Release of OXY USA Inc., et al. Filed Date: 07/12/2017. Accession Number: 20170712–5203. Comment Date: 5:00 p.m. Eastern Time on Wednesday, July 19, 2017. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Jkt 241001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3511–023] Lower Saranac Hydro, LLC ; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process a. Type of Filing: Notice of Intent to File License Application and Request to Use the Traditional Licensing Process. b. Project No.: 3511–023. c. Date Filed: May 31, 2017. d. Submitted By: Lower Saranac Hydro, LLC. e. Name of Project: Groveville Hydroelectric Project. f. Location: On Fishkill Creek near the city of Beacon, New York. No federal lands are occupied by the project works or located within the project boundary. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Potential Applicant Contact: Mr. Kevin M. Webb, Hydro Licensing Manager, Lower Saranac Hydro, LLC, 100 Brickstone Square, Suite 300, Andover, MA 01810; (978) 935–6039; email:kevin.webb@enel.com. PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 i. FERC Contact: Chris Millard at (202) 502–8256; or email at christopher.millard@ferc.gov. j. Lower Saranac Hydro, LLC filed a request to use the Traditional Licensing Process on May 31, 2017 and provided public notice of the request on June 7, 2017. In a letter dated July 18, 2017, the Director of the Division of Hydropower Licensing approved Lower Saranac Hydro, LLC’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b) of the MagnusonStevens Fishery Conservation and Management Act and implementing regulations at 50 CFR 600.920. We are also initiating consultation with the New York State Historic Preservation Officer, as required by section 106, National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Lower Saranac Hydro, LLC as the Commission’s non-federal representative for carrying out informal consultation pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. Lower Saranac Hydro, LLC filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the eLibrary link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h. o. The licensee states its unequivocal intent to submit an application for a new license for Project No. 3511–023. Pursuant to 18 CFR 16.8, 16.9, and 16.10, each application for a new license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. E:\FR\FM\24JYN1.SGM 24JYN1 Federal Register / Vol. 82, No. 140 / Monday, July 24, 2017 / Notices All applications for license for this project must be filed by May 31, 2020. p. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: July 18, 2017. Kimberly D. Bose, Secretary. Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on August 11, 2017. Dated: July 17, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–15432 Filed 7–21–17; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2017–15429 Filed 7–21–17; 8:45 am] DEPARTMENT OF ENERGY BILLING CODE 6717–01–P Federal Energy Regulatory Commission DEPARTMENT OF ENERGY [Docket No. OR17–15–000] mstockstill on DSK30JT082PROD with NOTICES Western Refining Conan Gathering, LLC; Notice of Petition for Declaratory Order Take notice that on July 12, 2017, pursuant to Rule 207(a)(2) of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207(a)(2) (2016), Western Refining Conan Gathering, LLC (Western), filed a petition for a declaratory order seeking approval of the tariff rate structure and terms of service for phase I of its proposed Conan Crude Oil Gathering Pipeline System, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the eLibrary link and is available for review in the VerDate Sep<11>2014 18:13 Jul 21, 2017 Jkt 241001 Federal Energy Regulatory Commission [Docket No. CP17–469–000] WBI Energy Transmission, Inc.; Notice of Application Take notice that on June 30, 2017, WBI Energy Transmission, Inc. (WBI), 1250 West Century Avenue, Bismarck, North Dakota 58503, filed in Docket No. CP17–469–000, an application pursuant to sections 7(b) and 7(c) of the Natural Gas Act, requesting authorization for abandonment of its Billy Creek Storage Field, the associated injected and recoverable native cushion gas and associated facilities, as well as to construct, install, modify and/or operate certain pipeline facilities to facilitate the withdrawal of the cushion gas prior to the abandonment of the storage facilities located in Johnson County, Wyoming, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may be viewed on the web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886)208–3676 or TYY, (202) 502–8659. Any questions regarding this Application should be directed to Lori Myerchin, Manager, Regulatory Affairs, WBI Energy Transmission, Inc., 1250 West Century Avenue, Bismarck, North Dakota 58503, (701) 530–1563 (email lori.myerchin@wbienergy.com ). Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 34309 place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. E:\FR\FM\24JYN1.SGM 24JYN1

Agencies

[Federal Register Volume 82, Number 140 (Monday, July 24, 2017)]
[Notices]
[Pages 34308-34309]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-15432]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3511-023]


Lower Saranac Hydro, LLC ; Notice of Intent To File License 
Application, Filing of Pre-Application Document, and Approving Use of 
the Traditional Licensing Process

    a. Type of Filing: Notice of Intent to File License Application and 
Request to Use the Traditional Licensing Process.
    b. Project No.: 3511-023.
    c. Date Filed: May 31, 2017.
    d. Submitted By: Lower Saranac Hydro, LLC.
    e. Name of Project: Groveville Hydroelectric Project.
    f. Location: On Fishkill Creek near the city of Beacon, New York. 
No federal lands are occupied by the project works or located within 
the project boundary.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Potential Applicant Contact: Mr. Kevin M. Webb, Hydro Licensing 
Manager, Lower Saranac Hydro, LLC, 100 Brickstone Square, Suite 300, 
Andover, MA 01810; (978) 935-6039; email:kevin.webb@enel.com.
    i. FERC Contact: Chris Millard at (202) 502-8256; or email at 
christopher.millard@ferc.gov.
    j. Lower Saranac Hydro, LLC filed a request to use the Traditional 
Licensing Process on May 31, 2017 and provided public notice of the 
request on June 7, 2017. In a letter dated July 18, 2017, the Director 
of the Division of Hydropower Licensing approved Lower Saranac Hydro, 
LLC's request to use the Traditional Licensing Process.
    k. With this notice, we are initiating informal consultation with 
the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 
7 of the Endangered Species Act and the joint agency regulations 
thereunder at 50 CFR, Part 402; and NOAA Fisheries under section 305(b) 
of the Magnuson-Stevens Fishery Conservation and Management Act and 
implementing regulations at 50 CFR 600.920. We are also initiating 
consultation with the New York State Historic Preservation Officer, as 
required by section 106, National Historic Preservation Act, and the 
implementing regulations of the Advisory Council on Historic 
Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Lower Saranac Hydro, LLC as 
the Commission's non-federal representative for carrying out informal 
consultation pursuant to section 7 of the Endangered Species Act and 
section 106 of the National Historic Preservation Act.
    m. Lower Saranac Hydro, LLC filed a Pre-Application Document (PAD; 
including a proposed process plan and schedule) with the Commission, 
pursuant to 18 CFR 5.6 of the Commission's regulations.
    n. A copy of the PAD is available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's Web site 
(https://www.ferc.gov), using the eLibrary link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCONlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at 
the address in paragraph h.
    o. The licensee states its unequivocal intent to submit an 
application for a new license for Project No. 3511-023. Pursuant to 18 
CFR 16.8, 16.9, and 16.10, each application for a new license and any 
competing license applications must be filed with the Commission at 
least 24 months prior to the expiration of the existing license.

[[Page 34309]]

All applications for license for this project must be filed by May 31, 
2020.
    p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

    Dated: July 18, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-15432 Filed 7-21-17; 8:45 am]
 BILLING CODE 6717-01-P