Federal Register / Vol. 82, No. 126 / Monday, July 3, 2017 / Rules and Regulations
the users of the waterway through our
Local and Broadcast Notices to Mariners
of the change in operating schedule for
the bridge so that vessel operators can
arrange their transits to minimize any
impact caused by the temporary
deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
temporary deviation. This deviation
from the operating regulations is
authorized under 33 CFR 117.35.
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2017–0538]
Drawbridge Operation Regulation;
China Basin, San Francisco, CA
Coast Guard, DHS.
Notice of deviation from
drawbridge regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the 3rd Street
Drawbridge across China Basin, mile
0.0, at San Francisco, CA. The deviation
is necessary to allow participants to
cross the bridge, uninterrupted, during
the San Francisco Marathon. This
deviation allows the bridge to remain in
the closed-to-navigation position during
the deviation period.
DATES: This deviation is effective from
6 a.m. to 2 p.m. on July 23, 2017.
ADDRESSES: The docket for this
deviation [USCG–2017–0538], is
available at https://www.regulations.gov.
Type the docket number in the
‘‘SEARCH’’ box and click ‘‘SEARCH.’’
Click on Open Docket Folder on the line
associated with this deviation.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
deviation, call or email Carl T. Hausner,
Chief, Bridge Section, Eleventh Coast
Guard District; telephone 510–437–
3516; email Carl.T.Hausner@uscg.mil.
SUPPLEMENTARY INFORMATION: The City
of San Francisco has requested a
temporary change to the operation of the
3rd Street Drawbridge, mile 0.0, over
China Basin, at San Francisco, CA. The
drawbridge navigation span provides a
vertical clearance of 3 feet above Mean
High Water in the closed-to-navigation
position. The draw opens on signal if at
least one hour notice is given, as
required by 33 CFR 117.149. Navigation
on the waterway is recreational.
The drawspan will be secured in the
closed-to-navigation position from 6
a.m. to 2 p.m. on July 23, 2017, to allow
participants to cross the bridge,
uninterrupted, during the San Francisco
Marathon. This temporary deviation has
been coordinated with the waterway
users. No objections to the proposed
temporary deviation were raised.
Vessels able to pass through the
bridge in the closed position may do so
at anytime. The bridge will be able to
open for emergencies. There is no
immediate alternate route for vessels to
pass. The Coast Guard will also inform
sradovich on DSK3GMQ082PROD with RULES
SUMMARY:
VerDate Sep<11>2014
17:08 Jun 30, 2017
Jkt 241001
Dated: June 27, 2017.
C.T. Hausner,
District Bridge Chief, Eleventh Coast Guard
District.
[FR Doc. 2017–13923 Filed 6–30–17; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2017–0325]
Drawbridge Operation Regulation;
Quantuck Canal, Westhampton Beach,
NY
Coast Guard, DHS.
Notice of deviation from
drawbridge regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the West Bay
Bridge across the Quantuck Canal, mile
0.1 at Westhampton Beach, New York.
This action is necessary to complete
rehabilitation of the bascule leaves of
the drawbridge. The deviation will
allow the bridge to open only one
bascule span in order to provide passage
for vessels requiring an opening.
DATES: This deviation is effective from
12:01 a.m. on October 2, 2017 to 11:59
p.m. on March 30, 2018.
ADDRESSES: The docket for this
deviation, USCG–2017–0325, is
available at https://www.regulations.gov.
Type the docket number in the
‘‘SEARCH’’ box and click ‘‘SEARCH’’.
Click on Open Docket Folder on the line
associated with this deviation.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
deviation, call or email James M. Moore,
Bridge Management Specialist, First
District Bridge Branch, U.S. Coast
Guard; telephone 212–514–4334, email
james.m.moore2@uscg.mil.
SUPPLEMENTARY INFORMATION: The
Suffolk County Department of Public
SUMMARY:
PO 00000
Frm 00015
Fmt 4700
Sfmt 4700
30735
Works, the owner of the bridge,
requested a temporary deviation in
order to facilitate reconstruction of the
bascule leaves.
The West Bay Bridge across the
Quantuck Canal, mile 0.1, at
Westhampton Beach, New York is a
double-leaf bascule bridge offering
mariners a vertical clearance of 11 feet
at mean high water and 13.3 feet at
mean low water in the closed position.
Horizontal clearance is 50 feet.
Utilization of a work barge placed
underneath one of the bascule leaves
will reduce horizontal clearance to 25
feet. The existing drawbridge operating
regulations are listed at 33 CFR
117.799(d).
This temporary deviation will allow
the Beach Lane Bridge to open only one
of the two bascule spans for bridge
openings from 12:01 a.m. on October 2,
2017 to 11:59 p.m. on March 30, 2018.
Dual lift span operations will be
available, provided 48 hours of advance
notice is furnished to the owner of the
bridge.
The majority of vessels requiring
bridge openings are sailing vessels and
yachts transiting the waterway.
Discussion with the proprietor of the
Modern Yachts Marina located in the
vicinity of the bridge confirms typical
recreational traffic will continue to be
able to proceed through the navigation
opening of the bridge during one-leaf
operations. Moreover, the bulk of
recreational traffic that utilizes the
waterway is largely seasonal in nature,
peaking during the late spring, summer
and early autumn months. Little to no
recreational traffic transits the Quantuck
Canal throughout the winter. Small
scale tug/barge combinations
occasionally transit the Quantuck Canal,
but such commercial craft are generally
limited in size. Mariners concur that the
requirement to provide the bridge owner
48 hours of advance notice for dual lift
span operations will not impede overall
operations.
Vessels that can pass under the bridge
without an opening may do so at all
times. The bridge will be able to open
for emergencies and there is an alternate
route for vessels unable to pass through
the bridge when in the closed position.
The Coast Guard will also inform the
users of the waterways through our
Local and Broadcast Notices to Mariners
of the change in operating schedule for
the bridge so vessel operators can
arrange their transits to minimize any
impact caused by this temporary
deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
E:\FR\FM\03JYR1.SGM
03JYR1
Agencies
[Federal Register Volume 82, Number 126 (Monday, July 3, 2017)]
[Rules and Regulations]
[Page 30735]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-13923]
[[Page 30735]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2017-0538]
Drawbridge Operation Regulation; China Basin, San Francisco, CA
AGENCY: Coast Guard, DHS.
ACTION: Notice of deviation from drawbridge regulation.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the 3rd Street Drawbridge across China
Basin, mile 0.0, at San Francisco, CA. The deviation is necessary to
allow participants to cross the bridge, uninterrupted, during the San
Francisco Marathon. This deviation allows the bridge to remain in the
closed-to-navigation position during the deviation period.
DATES: This deviation is effective from 6 a.m. to 2 p.m. on July 23,
2017.
ADDRESSES: The docket for this deviation [USCG-2017-0538], is available
at https://www.regulations.gov. Type the docket number in the ``SEARCH''
box and click ``SEARCH.'' Click on Open Docket Folder on the line
associated with this deviation.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, call or email Carl T. Hausner, Chief, Bridge
Section, Eleventh Coast Guard District; telephone 510-437-3516; email
Carl.T.Hausner@uscg.mil.
SUPPLEMENTARY INFORMATION: The City of San Francisco has requested a
temporary change to the operation of the 3rd Street Drawbridge, mile
0.0, over China Basin, at San Francisco, CA. The drawbridge navigation
span provides a vertical clearance of 3 feet above Mean High Water in
the closed-to-navigation position. The draw opens on signal if at least
one hour notice is given, as required by 33 CFR 117.149. Navigation on
the waterway is recreational.
The drawspan will be secured in the closed-to-navigation position
from 6 a.m. to 2 p.m. on July 23, 2017, to allow participants to cross
the bridge, uninterrupted, during the San Francisco Marathon. This
temporary deviation has been coordinated with the waterway users. No
objections to the proposed temporary deviation were raised.
Vessels able to pass through the bridge in the closed position may
do so at anytime. The bridge will be able to open for emergencies.
There is no immediate alternate route for vessels to pass. The Coast
Guard will also inform the users of the waterway through our Local and
Broadcast Notices to Mariners of the change in operating schedule for
the bridge so that vessel operators can arrange their transits to
minimize any impact caused by the temporary deviation.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately at the end of the effective
period of this temporary deviation. This deviation from the operating
regulations is authorized under 33 CFR 117.35.
Dated: June 27, 2017.
C.T. Hausner,
District Bridge Chief, Eleventh Coast Guard District.