Download as PDF sradovich on DSK3GMQ082PROD with NOTICES 29542 Federal Register / Vol. 82, No. 124 / Thursday, June 29, 2017 / Notices Docket Numbers: ER10–3079–013; ER10–3078–004; ER11–3861–014. Applicants: Tyr Energy, LLC, Commonwealth Chesapeake Company, LLC, Empire Generating Co, LLC. Description: Updated Market Power Analysis for the Northeast Region of Tyr Energy, LLC, et al. under ER10–3079, et al. Filed Date: 6/23/17. Accession Number: 20170623–5083. Comments Due: 5 p.m. ET 8/22/17. Docket Numbers: ER10–3145–008; ER10–1728–008; ER10–1800–009; ER10–3116–008; ER10–3120–008; ER10–3128–008; ER10–3136–008; ER11–2036–008; ER11–2701–010; ER13–1544–005; ER16–930–002. Applicants: AES Alamitos, LLC, AES Energy Storage, LLC, AES Huntington Beach, L.L.C., AES Laurel Mountain, LLC, AES ES Tait, LLC, AES Redondo Beach, L.L.C., Indianapolis Power & Light Company, Mountain View Power Partners, LLC, Mountain View Power Partners IV, LLC, The Dayton Power and Light Company, AES Ohio Generation, LLC. Description: Supplement to December 21, 2016 Triennial Market Power Analysis for Northeast Region of AES MBR Affiliates; also filed was an Amended Supplement to December 21, 2016 Triennial Market Power Analysis for Northeast Region of AES MBR Affiliates. Filed Dates: 6/6/17; 6/21/17. Accession Number: 20170606–5163; 20170621–5138. Comments Due: 5 p.m. ET 7/12/17. Docket Numbers: ER17–1888–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2017–06–22_SA 3023 Air LiquideEntergy GIA (Project QF) to be effective 6/22/2017. Filed Date: 6/22/17. Accession Number: 20170622–5153. Comments Due: 5 p.m. ET 7/13/17. Docket Numbers: ER17–1889–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2017–06–22_SA 758 Termination of ATC-Wisconsin River GTIA to be effective 8/22/2017. Filed Date: 6/22/17. Accession Number: 20170622–5156. Comments Due: 5 p.m. ET 7/13/17. Docket Numbers: ER17–1890–000. Applicants: ITC Midwest LLC. Description: § 205(d) Rate Filing: Filing of Joint Use Pole Agreement with Dairyland to be effective 8/22/2017. Filed Date: 6/22/17. Accession Number: 20170622–5176. Comments Due: 5 p.m. ET 7/13/17. VerDate Sep<11>2014 18:29 Jun 28, 2017 Jkt 241001 Docket Numbers: ER17–1891–000. Applicants: Summit Farms Solar, LLC. Description: Compliance filing: Compliance Filing—Addition of Docket No. to MBR Tariff to be effective 6/23/ 2017. Filed Date: 6/22/17. Accession Number: 20170622–5186. Comments Due: 5 p.m. ET 7/13/17. Docket Numbers: ER17–1892–000. Applicants: PacifiCorp. Description: Tariff Cancellation: Termination of PAC Energy Carbon Decommissioning Construct Agmt Rev 2 to be effective 6/26/2017. Filed Date: 6/23/17. Accession Number: 20170623–5094. Comments Due: 5 p.m. ET 7/14/17. Docket Numbers: ER17–1894–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original Service Agreement No. 4730, Queue Position #AC1–039 to be effective 5/31/2017. Filed Date: 6/23/17. Accession Number: 20170623–5110. Comments Due: 5 p.m. ET 7/14/17. Docket Numbers: ER17–1895–000. Applicants: Southwestern Electric Power Company. Description: § 205(d) Rate Filing: SWEPCO-Minden PSA Amendment T&D Losses to be effective 8/1/2016. Filed Date: 6/23/17. Accession Number: 20170623–5111. Comments Due: 5 p.m. ET 7/14/17. Docket Numbers: ER17–1896–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2017–06–23_SA 3022 Trigen-Ameren GIA (Project Trigen) to be effective 6/23/ 2017. Filed Date: 6/23/17. Accession Number: 20170623–5143. Comments Due: 5 p.m. ET 7/14/17. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES17–38–000. Applicants: Midcontinent Independent System Operator, Inc. Description: Application of Midcontinent Independent System Operator, Inc. to Issue Securities Under Section 204 of the Federal Power Act. Filed Date: 6/23/17. Accession Number: 20170623–5099. Comments Due: 5 p.m. ET 7/14/17. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings PO 00000 Frm 00069 Fmt 4703 Sfmt 4703 must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: June 23, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–13597 Filed 6–28–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–463–000] Notice of Request Under Blanket Authorization: Florida Southeast Connection, LLC Take notice that on June 14, 2017, Florida Southeast Connection, LLC (FSC), 700 Universe Boulevard, Juno Beach, Florida 33408, filed in Docket No. CP17–463–000 a prior notice request pursuant to sections 157.205 and 157.208 of the Commission’s regulations under the Natural Gas Act (NGA), and FSC’s blanket certificate issued in Docket No. CP14–554–000, to construct and operate certain natural gas facilities in Okeechobee County, Florida. The facilities will allow FSC to provide up to 400,000 dekatherms (Dth) per day of natural gas to the Okeechobee Clean Energy Center (OCEC), currently under construction by Florida Power & Light Company (FPL) and planned to be in service by mid-2019. FSC proposes to construct and operate an approximately 5.2 mile, 20-inch diameter natural gas pipeline lateral starting at milepost 77.2 of the FSC mainline along US 441 and terminating at the FPL OCEC in Okeechobee County, Florida. Upon completion and start of commercial operation of the project, FSC will add Okeechobee as a delivery point on its system, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the E:\FR\FM\29JNN1.SGM 29JNN1 sradovich on DSK3GMQ082PROD with NOTICES Federal Register / Vol. 82, No. 124 / Thursday, June 29, 2017 / Notices last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Halli Nicoloso, Florida Southeast Connection, LLC, 700 Universe Boulevard, Juno Beach, Florida 33408, by telephone at (561) 304–5708, by facsimile at (412) 553–7781, or by email at halli.nicoloso@ nee.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings VerDate Sep<11>2014 18:29 Jun 28, 2017 Jkt 241001 associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters, will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and seven copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Dated: June 23, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–13599 Filed 6–28–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER17–1884–000] Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization: Wrighter Energy LLC This is a supplemental notice in the above-referenced proceeding of Wrighter Energy LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is July 13, 2017. The Commission encourages electronic submission of protests and PO 00000 Frm 00070 Fmt 4703 Sfmt 4703 29543 interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: June 23, 2017. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2017–13601 Filed 6–28–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2337–077] Notice of Intent To Prepare a Draft and Final Environmental Assessment and Revised Procedural Schedule: PacifiCorp On December 30, 2016, PacifiCorp filed an application for the continued operation of the 7.2-megawatt Prospect No. 3 Hydroelectric Project No. 2337. On March 15, 2017, the Commission issued a Notice of Application Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions (REA Notice). The REA notice included a procedural schedule that included preparation of a single Environmental Assessment (EA). Based on the comments received in response to the REA notice, Commission staff has determined that its analysis of E:\FR\FM\29JNN1.SGM 29JNN1

Agencies

[Federal Register Volume 82, Number 124 (Thursday, June 29, 2017)]
[Notices]
[Pages 29542-29543]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-13599]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-463-000]


Notice of Request Under Blanket Authorization: Florida Southeast 
Connection, LLC

    Take notice that on June 14, 2017, Florida Southeast Connection, 
LLC (FSC), 700 Universe Boulevard, Juno Beach, Florida 33408, filed in 
Docket No. CP17-463-000 a prior notice request pursuant to sections 
157.205 and 157.208 of the Commission's regulations under the Natural 
Gas Act (NGA), and FSC's blanket certificate issued in Docket No. CP14-
554-000, to construct and operate certain natural gas facilities in 
Okeechobee County, Florida. The facilities will allow FSC to provide up 
to 400,000 dekatherms (Dth) per day of natural gas to the Okeechobee 
Clean Energy Center (OCEC), currently under construction by Florida 
Power & Light Company (FPL) and planned to be in service by mid-2019.
    FSC proposes to construct and operate an approximately 5.2 mile, 
20-inch diameter natural gas pipeline lateral starting at milepost 77.2 
of the FSC mainline along US 441 and terminating at the FPL OCEC in 
Okeechobee County, Florida. Upon completion and start of commercial 
operation of the project, FSC will add Okeechobee as a delivery point 
on its system, all as more fully set forth in the application which is 
on file with the Commission and open to public inspection. The filing 
may also be viewed on the web at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the

[[Page 29543]]

last three digits in the docket number field to access the document. 
For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Any questions concerning this application may be directed to Halli 
Nicoloso, Florida Southeast Connection, LLC, 700 Universe Boulevard, 
Juno Beach, Florida 33408, by telephone at (561) 304-5708, by facsimile 
at (412) 553-7781, or by email at halli.nicoloso@nee.com.
    Any person or the Commission's staff may, within 60 days after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefore, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the allowed time for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to section 7 of the NGA.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters, will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and seven copies of the protest or intervention to 
the Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426.

    Dated: June 23, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-13599 Filed 6-28-17; 8:45 am]
BILLING CODE 6717-01-P