Entergy Operations, Inc.; River Bend Station, Unit 1, 29344-29345 [2017-13518]
Download as PDF
29344
Federal Register / Vol. 82, No. 123 / Wednesday, June 28, 2017 / Notices
(2) Before an exemption may be
granted under section 408(a) of the Act
and/or section 4975(c)(2) of the Code,
the Department must find that the
exemption is administratively feasible,
in the interests of the plan and of its
participants and beneficiaries, and
protective of the rights of participants
and beneficiaries of the plan;
(3) The proposed exemptions, if
granted, will be supplemental to, and
not in derogation of, any other
provisions of the Act and/or the Code,
including statutory or administrative
exemptions and transitional rules.
Furthermore, the fact that a transaction
is subject to an administrative or
statutory exemption is not dispositive of
whether the transaction is in fact a
prohibited transaction; and
(4) The proposed exemptions, if
granted, will be subject to the express
condition that the material facts and
representations contained in each
application are true and complete, and
that each application accurately
describes all material terms of the
transaction which is the subject of the
exemption.
Signed at Washington, DC, this 21st day of
June, 2017.
Lyssa E. Hall,
Director, Office of Exemption Determinations,
Employee Benefits Security Administration,
U.S. Department of Labor.
[FR Doc. 2017–13509 Filed 6–27–17; 8:45 am]
BILLING CODE 4510–29–P
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
[Notice: (17–041)]
NASA Astrophysics Advisory
Committee; Meeting.
National Aeronautics and
Space Administration.
ACTION: Notice of meeting.
AGENCY:
In accordance with the
Federal Advisory Committee Act, Public
Law 92–463, as amended, the National
Aeronautics and Space Administration
(NASA) announces a meeting of the
Astrophysics Advisory Committee. This
Committee reports to the Director,
Astrophysics Division, Science Mission
Directorate, NASA Headquarters. The
meeting will be held for the purpose of
soliciting, from the scientific
community and other persons, scientific
and technical information relevant to
program planning.
DATES: Wednesday, July 19, 2017, 8:30
a.m.–5:00 p.m.; and Thursday, July 20,
2017, 8:30 a.m.–5:00 p.m., Eastern
Daylight Time (EDT).
asabaliauskas on DSKBBXCHB2PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:22 Jun 27, 2017
Jkt 241001
On July 19: NASA
Headquarters, Room 6H42, 300 E Street
SW., Washington, DC 20546. On July 20:
Residence Inn Capitol, Senate Room,
333 E Street SW., Washington, DC
20024.
ADDRESSES:
Ms.
KarShelia Henderson, Science Mission
Directorate, NASA Headquarters,
Washington, DC 20546, (202) 358–2355,
fax (202) 358–2779, or khenderson@
nasa.gov.
FOR FURTHER INFORMATION CONTACT:
The
meeting will be open to the public up
to the capacity of the room. The meeting
will be available telephonically and by
WebEx. You must use a touch-tone
phone to participate in this meeting.
Any interested person may dial the USA
toll free conference call number 1–888–
469–3018 or toll number 1–210–234–
0113, passcode 6295733, to participate
in this meeting by telephone on both
days. The WebEx link is https://
nasa.webex.com/; the meeting number
on July 19 is 996 101 861, password is
APAC@1920; and the meeting number
on July 20 is 994 706 096, password is
APAC@1920.
The agenda for the meeting includes
the following topics:
—Astrophysics Division Update
—Updates on Specific Astrophysics
Missions
—Reports from the Program Analysis
Groups
—Reports from Specific Research &
Analysis Programs
The agenda will be posted on the
Astrophysics Advisory committee Web
page: https://science.nasa.gov/
researchers/nac/science-advisorycommittees/apac.
Attendees will be requested to sign a
register and to comply with NASA
Headquarters security requirements,
including the presentation of a valid
picture ID to Security before access to
NASA Headquarters. Due to the Real ID
Act, any attendees with driver’s licenses
issued from non-compliant states must
present a second form of ID. Noncompliant states are: Minnesota and
Missouri. Foreign nationals attending
this meeting will be required to provide
a copy of their passport and visa in
addition to providing the following
information no less than 10 days prior
to the meeting: Full name; gender; date/
place of birth; citizenship; passport
information (number, country,
telephone); visa information (number,
type, expiration date); employer/
affiliation information (name of
institution, address, country,
telephone); title/position of attendee. To
expedite admittance, attendees with
SUPPLEMENTARY INFORMATION:
PO 00000
Frm 00071
Fmt 4703
Sfmt 4703
U.S. citizens and Permanent Residents
(green card holders) can provide full
name and citizenship status 3 working
days in advance. Information should be
sent to Ms. KarShelia Henderson, via
email at khenderson@nasa.gov or by fax
at (202) 358–2779. It is imperative that
the meeting be held on this date to
accommodate the scheduling priorities
of the key participants.
Patricia D. Rausch,
Advisory Committee Management Officer,
National Aeronautics and Space
Administration.
[FR Doc. 2017–13501 Filed 6–27–17; 8:45 am]
BILLING CODE 7510–13–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–458; NRC–2017–0141]
Entergy Operations, Inc.; River Bend
Station, Unit 1
Nuclear Regulatory
Commission.
ACTION: License renewal application;
receipt.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has received an
application for the renewal of operating
license NPF–47, which authorizes
Entergy Operations, Inc. (the applicant)
to operate River Bend Station, Unit 1
(RBS). The renewed license would
authorize the applicant to operate RBS
for an additional 20-year period beyond
the period specified in the current
license. The current operating license
for RBS expires at midnight on August
29, 2025.
DATES: The license renewal application
referenced in this document was
available on June 2, 2017.
ADDRESSES: Please refer to Docket ID
NRC–2017–0141 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2017–0141. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
SUMMARY:
E:\FR\FM\28JNN1.SGM
28JNN1
Federal Register / Vol. 82, No. 123 / Wednesday, June 28, 2017 / Notices
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
license renewal application for RBS is
available in ADAMS under Package
Accession No. ML17153A282.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Emmanuel Sayoc, Office of Nuclear
Reactor Regulation, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
4084; email: Emmanuel.Sayoc@nrc.gov.
The NRC
has received an application from
Entergy Operations, Inc., dated May 25,
2017, filed pursuant to Section 103 of
the Atomic Energy Act of 1954, as
amended, and part 54 of title 10 of the
Code of Federal Regulations, to renew
the operating license for RBS. Renewal
of the license would authorize the
applicant to operate the facility for an
additional 20-year period beyond the
period specified in the current operating
license. The current operating license
for RBS expires at midnight on August
29, 2025. River Bend Station, Unit 1, is
a boiling water reactor designed by
General Electric and is located in St.
Francisville, Louisiana. The
acceptability of the tendered application
for docketing, and other matters,
including an opportunity to request a
hearing, will be the subject of
subsequent Federal Register notices.
A copy of the license renewal
application for the RBS, is also available
to local residents near the site at the
West Feliciana Parish Library at 5114
Burnett Rd., St. Francisville, LA 70775.
asabaliauskas on DSKBBXCHB2PROD with NOTICES
SUPPLEMENTARY INFORMATION:
Dated at Rockville, Maryland, this 19th day
of June, 2017.
For the Nuclear Regulatory Commission.
Sheldon Stuchell,
Chief, Projects Management and Guidance
Branch, Division of License Renewal, Office
of Nuclear Reactor Regulation.
[FR Doc. 2017–13518 Filed 6–27–17; 8:45 am]
BILLING CODE 7590–01–P
VerDate Sep<11>2014
17:22 Jun 27, 2017
Jkt 241001
SUPPLEMENTARY INFORMATION:
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–244; NRC–2017–0124]
Exelon Generation Company, LLC;
R.E. Ginna Nuclear Power Plant; Use of
Optimized ZIRLOTM Fuel Rod Cladding
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to an August 22,
2016, request from Exelon Generation
Company, LLC (Exelon) in order to use
Optimized ZIRLOTM Fuel Rod Cladding
at the R.E. Ginna Nuclear Power Plant
(Ginna).
DATES: The exemption was issued on
June 19, 2017.
ADDRESSES: Please refer to Docket ID
NRC–2017–0124 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2017–0124. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–415–3463;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced (if it is available in
ADAMS) is provided the first time that
it is mentioned in this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: V.
Sreenivas, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington DC 20555–
0001; telephone: 301–415–2597, email:
V.Sreenivas@nrc.gov.
SUMMARY:
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
29345
I. Background
Exelon Generation Company, LLC is
the holder of Renewed Facility
Operating License No. DPR–18, which
authorizes operation of Ginna, a
pressurized-water reactor. The license
provides, among other things, that the
facility is subject to all rules,
regulations, and orders of the NRC now
or hereafter in effect. The facility is
located in Ontario, New York,
approximately 20 miles northeast of
Rochester, New York.
II. Request/Action
Pursuant to § 50.12 of title 10 of the
Code of Federal Regulations (10 CFR),
‘‘Specific exemptions,’’ the licensee
requested, by letter dated August 22,
2016 (ADAMS Accession No.
ML16236A300), an exemption from
§ 50.46, ‘‘Acceptance criteria for
emergency core cooling systems [ECCS]
for light-water nuclear power reactors,’’
and 10 CFR part 50, appendix K, ‘‘ECCS
Evaluation Models,’’ to allow the use of
Optimized ZIRLOTM fuel rod cladding.
The regulations in § 50.46 contain
acceptance criteria for the ECCS for
reactors fueled with zircaloy or
ZIRLOTM fuel rod cladding material. In
addition, 10 CFR part 50, appendix K,
requires that the Baker-Just equation be
used to predict the rates of energy
release, hydrogen concentration, and
cladding oxidation from the metal/water
reaction. The Baker-Just equation
assumes the use of a zirconium alloy
different than Optimized ZIRLOTM
material. Therefore, an exemption to
§ 50.46 and 10 CFR part 50, appendix K
is required to support the use of
Optimized ZIRLOTM fuel rod cladding at
Ginna.
The exemption request relates solely
to the specific types of cladding material
specified in these regulations (i.e., fuel
rods with Zircaloy or ZIRLO® cladding).
This request will provide for the
application of the acceptance criteria of
§ 50.46 and appendix K to 10 CFR part
50 to fuel assembly designs utilizing
Optimized ZIRLOTM fuel rod cladding.
The NRC staff prepared a separate safety
evaluation fully addressing Exelon’s
application for a related license
amendment.
III. Discussion
Pursuant to § 50.12, the Commission
may, upon application by any interested
person or upon its own initiative, grant
exemptions from the requirements of 10
CFR part 50 when: (1) The exemptions
are authorized by law, will not present
an undue risk to public health or safety,
and are consistent with the common
E:\FR\FM\28JNN1.SGM
28JNN1
Agencies
[Federal Register Volume 82, Number 123 (Wednesday, June 28, 2017)]
[Notices]
[Pages 29344-29345]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-13518]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-458; NRC-2017-0141]
Entergy Operations, Inc.; River Bend Station, Unit 1
AGENCY: Nuclear Regulatory Commission.
ACTION: License renewal application; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has received an
application for the renewal of operating license NPF-47, which
authorizes Entergy Operations, Inc. (the applicant) to operate River
Bend Station, Unit 1 (RBS). The renewed license would authorize the
applicant to operate RBS for an additional 20-year period beyond the
period specified in the current license. The current operating license
for RBS expires at midnight on August 29, 2025.
DATES: The license renewal application referenced in this document was
available on June 2, 2017.
ADDRESSES: Please refer to Docket ID NRC-2017-0141 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2017-0141. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
[[Page 29345]]
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The
license renewal application for RBS is available in ADAMS under Package
Accession No. ML17153A282.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Emmanuel Sayoc, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-4084; email: Emmanuel.Sayoc@nrc.gov.
SUPPLEMENTARY INFORMATION: The NRC has received an application from
Entergy Operations, Inc., dated May 25, 2017, filed pursuant to Section
103 of the Atomic Energy Act of 1954, as amended, and part 54 of title
10 of the Code of Federal Regulations, to renew the operating license
for RBS. Renewal of the license would authorize the applicant to
operate the facility for an additional 20-year period beyond the period
specified in the current operating license. The current operating
license for RBS expires at midnight on August 29, 2025. River Bend
Station, Unit 1, is a boiling water reactor designed by General
Electric and is located in St. Francisville, Louisiana. The
acceptability of the tendered application for docketing, and other
matters, including an opportunity to request a hearing, will be the
subject of subsequent Federal Register notices.
A copy of the license renewal application for the RBS, is also
available to local residents near the site at the West Feliciana Parish
Library at 5114 Burnett Rd., St. Francisville, LA 70775.
Dated at Rockville, Maryland, this 19th day of June, 2017.
For the Nuclear Regulatory Commission.
Sheldon Stuchell,
Chief, Projects Management and Guidance Branch, Division of License
Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2017-13518 Filed 6-27-17; 8:45 am]