Combined Notice of Filings #2, 27812-27813 [2017-12676]
Download as PDF
27812
Federal Register / Vol. 82, No. 116 / Monday, June 19, 2017 / Notices
• Vince Kaminski, Professor in Practice
of Energy, Rice University
• Curtis Moffatt, Deputy General
Counsel and Vice President, Kinder
Morgan
• Joe Bowring, President, Monitoring
Analytics
• Corey Grindal, Senior Vice
President—Gas Supply, Cheniere
Energy
• Tom Haywood, Editor—Natural Gas
Week, Energy Intelligence
• Drew Fossum, Senior Vice President
and General Counsel, Tenaska Inc.
• Joan Dreskin, Vice President and
General Counsel, Interstate Natural
Gas Association of America
5:25 p.m.–5:30 p.m.
Closing Remarks
[FR Doc. 2017–12671 Filed 6–16–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–58–000]
asabaliauskas on DSKBBXCHB2PROD with NOTICES
Transcontinental Gas Pipe Line
Company, LLC; Notice of Schedule for
Environmental Review of the St. James
Supply Project
On February 6, 2017,
Transcontinental Gas Pipe Line
Company, LLC (Transco) filed an
application in Docket No. CP17–58–000
requesting a Certificate of Public
Convenience and Necessity pursuant to
Section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities. The proposed project
is known as the St. James Supply Project
(Project), and would deliver 161,500
dekatherms per day of firm
transportation capacity from Transco’s
existing mainline Compressor Station 65
in St. Helena Parish, Louisiana to the
planned Yuhuang Chemical Plant in St.
James Parish, Louisiana.
On February 21, 2017, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—July 24, 2017.
VerDate Sep<11>2014
17:09 Jun 16, 2017
Jkt 241001
90-day Federal Authorization
Decision Deadline—October 22, 2017.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The St. James Supply Project would
consist of 0.7 mile of 20-inch-diameter
pipeline, one new pig receiver site,1 a
new interconnection to the planned
Yuhuang Chemical Plant site, one new
valve and piping to tie the Old River
Road M&R Station into the existing
Southeast Lateral Pipeline, and piping
and valve modifications at existing
Transco Compressor Stations 63 and 65.
Background
On March 17, 2017, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed St. James Supply Project and
Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries. In response to the NOI, the
Commission received letters from the
Seminole Nation of Oklahoma, the
Quapaw Tribe of Oklahoma, and the
Choctaw Nation of Oklahoma. No
concerns about historic resources were
raised.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the eLibrary
link, select General Search from the
eLibrary menu, enter the selected date
range and Docket Number excluding the
last three digits (i.e., CP17–58), and
follow the instructions. For assistance
with access to eLibrary, the helpline can
be reached at (866) 208–3676, TTY (202)
1 A pig is a tool that the pipeline company inserts
into and pushes through the pipeline for cleaning
the pipeline, conducting internal inspections, or
other purposes.
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
502–8659, or at FERCOnlineSupport@
ferc.gov. The eLibrary link on the FERC
Web site also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
Dated: June 12, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–12661 Filed 6–16–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER17–1774–000.
Applicants: NextEra Energy Bluff
Point, LLC.
Description: Baseline eTariff Filing:
NextEra Energy Bluff Point, LLC
Application for Market-Based Rates to
be effective 8/7/2017.
Filed Date: 6/8/17.
Accession Number: 20170608–5077.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17–1775–000.
Applicants: Arizona Public Service
Company.
Description: § 205(d) Rate Filing: Rate
Schedule No. 265, Amendment No. 1
PV-Morgan 500kV to be effective 8/8/
2016.
Filed Date: 6/8/17.
Accession Number: 20170608–5083.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17–1776–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Bylaws 3.1 and 3.3.2 Revisions (Chair
and Vice Chair Terms) to be effective
8/7/2017.
Filed Date: 6/8/17.
Accession Number: 20170608–5096.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17–1777–000.
Applicants: Midcontinent
Independent System Operator Inc.,
Entergy Services, Inc.
Description: Compliance filing: 2017–
06–08_Filing to implement Entergy
settlement in Docket No. ER16–227 to
be effective 1/1/2016.
Filed Date: 6/8/17.
Accession Number: 20170608–5117.
Comments Due: 5 p.m. ET 6/29/17.
Take notice that the Commission
received the following electric
reliability filings:
Docket Numbers: RR17–5–000.
E:\FR\FM\19JNN1.SGM
19JNN1
Federal Register / Vol. 82, No. 116 / Monday, June 19, 2017 / Notices
Applicants: North American Electric
Reliability Corporation.
Description: Petition of the North
American Electric Reliability
Corporation for Approval of
Amendments to the Western Electricity
Coordinating Council Regional
Reliability Standards Development
Procedures.
Filed Date: 6/8/17.
Accession Number: 20170608–5107.
Comments Due: 5 p.m. ET 6/29/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: June 8, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017–12676 Filed 6–16–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Boulder Canyon Project—Rate Order
No. WAPA–178
Western Area Power
Administration, DOE.
ACTION: Notice of proposed rate-setting
formulas for electric service and
adjustment of fiscal year 2018 base
charge and rates.
AGENCY:
Western Area Power
Administration (WAPA) is proposing to
update the rate-setting formulas for
electric service for the Boulder Canyon
Project (BCP) under proposed Rate
Schedule BCP–F10, and adjust the
annual calculation for the fiscal year
(FY) 2018 base charge and rates. The
expiration of the current base charge
and rates on September 30, 2017, and
beginning of the new 50-year marketing
asabaliauskas on DSKBBXCHB2PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
17:09 Jun 16, 2017
Jkt 241001
period on October 1, 2018, require these
actions.
The current base charge under Rate
Schedule BCP–F9 is not sufficient to
cover all annual costs including
operation and maintenance,
replacements, and interest expense; and
repay investment obligations within the
allowable period. After collaborating
with the BCP contractors, WAPA
proposes an FY 2018 base charge that
includes a one-time $15 million
working capital fund primarily for the
Bureau of Reclamation (Reclamation) for
the new marketing period. The FY 2019
base charge is expected to decrease by
$15 million after the collection of
working capital in FY 2018. The
proposed base charge will provide
sufficient revenue to cover all annual
costs and repay investment obligations
within the allowable period. WAPA will
post proposed Rate Schedule BCP–F10
and a detailed rate package that
identifies the reasons for the base charge
and rates adjustment on its Web site
during the consultation and comment
period. The proposed base charge and
rates are scheduled to become effective
on October 1, 2017, and will remain in
effect through September 30, 2018.
Publication of this Federal Register
notice initiates the formal public
process to implement the proposed ratesetting formulas and the FY 2018 base
charge and rates.
DATES: The consultation and comment
period begins today and will end
September 18, 2017. WAPA will present
a detailed explanation of the proposed
rate-setting formulas and the FY 2018
base charge and rates at a public
information forum that will be held on
July 19, 2017, at 10:00 a.m. Mountain
Standard Time (MST) in Phoenix,
Arizona. WAPA will accept oral and
written comments at a public comment
forum that will be held on August 18,
2017, at 10:00 a.m. MST in Phoenix,
Arizona. WAPA will accept written
comments any time during the
consultation and comment period.
ADDRESSES: The public information
forum and public comment forum will
be held at WAPA’s Desert Southwest
Customer Service Regional Office
located at 615 South 43rd Avenue,
Phoenix, Arizona 85009. Send written
comments to Mr. Ronald E. Moulton,
Regional Manager, Desert Southwest
Customer Service Region, Western Area
Power Administration, P.O. Box 6457,
Phoenix, Arizona 85005–6457, email
moulton@wapa.gov. WAPA will post
information about the rate process, as
well as comments received via letter
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
27813
and email on its Web site at: https://
www.wapa.gov/regions/DSW/Rates/
Pages/boulder-canyon-rates.aspx.
Written comments must be received by
the end of the consultation and
comment period to be considered by
WAPA in its decision process.
United States (U.S.) citizens who
want to attend a forum must present an
official form of picture identification
(ID) such as a U.S. driver’s license, U.S.
passport, U.S. government ID, or U.S.
military ID. Foreign nationals who want
to attend a forum must contact Mr. Scott
Lund, Rates Manager, at (602) 605–2442
or email slund@wapa.gov 30 days in
advance of a forum to obtain the
necessary clearance.
FOR FURTHER INFORMATION CONTACT: Mr.
Scott Lund, Rates Manager, Desert
Southwest Customer Service Region,
Western Area Power Administration,
P.O. Box 6457, Phoenix, Arizona 85005–
6457, (602) 605–2442, or email slund@
wapa.gov.
SUPPLEMENTARY INFORMATION: BCP’s base
charge and rates for electric service are
calculated annually based on formulas
that are set for a five-year period. Since
BCP begins a new 50-year marketing
period in FY 2018, WAPA is proposing
to update the rate-setting formulas
effective October 1, 2017 through
September 30, 2022. Proposed Rate
Schedule BCP–F10 will update the
existing forecast capacity rate formula to
reflect BCP’s current generating capacity
of 2,074 megawatts. No other changes to
the existing rate-setting formulas are
proposed.
The proposed FY 2018 base charge
and rates for BCP electric service are
designed to recover an annual revenue
requirement that includes operation and
maintenance and replacements costs,
interest expense, investment
repayments, payments to states, and
visitor services expenses. The total costs
are offset by the projected revenue from
water sales, visitor services, ancillary
services, and late fees. The annual
revenue requirement is the base charge
for electric service divided equally
between capacity and energy. The
annual composite rate is the base charge
divided by annual energy sales.
The proposed Rate Schedule BCP–F10
requires updated financial and
hydrology data to calculate the annual
base charge and rates. The proposed
base charge for FY 2018 is $85,094,786
and the proposed composite rate is
24.39 mills/kilowatt-hour. The
following table compares the existing
and proposed base charge and
composite rate:
E:\FR\FM\19JNN1.SGM
19JNN1
Agencies
[Federal Register Volume 82, Number 116 (Monday, June 19, 2017)]
[Notices]
[Pages 27812-27813]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-12676]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #2
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER17-1774-000.
Applicants: NextEra Energy Bluff Point, LLC.
Description: Baseline eTariff Filing: NextEra Energy Bluff Point,
LLC Application for Market-Based Rates to be effective 8/7/2017.
Filed Date: 6/8/17.
Accession Number: 20170608-5077.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17-1775-000.
Applicants: Arizona Public Service Company.
Description: Sec. 205(d) Rate Filing: Rate Schedule No. 265,
Amendment No. 1 PV-Morgan 500kV to be effective 8/8/2016.
Filed Date: 6/8/17.
Accession Number: 20170608-5083.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17-1776-000.
Applicants: Southwest Power Pool, Inc.
Description: Sec. 205(d) Rate Filing: Bylaws 3.1 and 3.3.2
Revisions (Chair and Vice Chair Terms) to be effective 8/7/2017.
Filed Date: 6/8/17.
Accession Number: 20170608-5096.
Comments Due: 5 p.m. ET 6/29/17.
Docket Numbers: ER17-1777-000.
Applicants: Midcontinent Independent System Operator Inc., Entergy
Services, Inc.
Description: Compliance filing: 2017-06-08_Filing to implement
Entergy settlement in Docket No. ER16-227 to be effective 1/1/2016.
Filed Date: 6/8/17.
Accession Number: 20170608-5117.
Comments Due: 5 p.m. ET 6/29/17.
Take notice that the Commission received the following electric
reliability filings:
Docket Numbers: RR17-5-000.
[[Page 27813]]
Applicants: North American Electric Reliability Corporation.
Description: Petition of the North American Electric Reliability
Corporation for Approval of Amendments to the Western Electricity
Coordinating Council Regional Reliability Standards Development
Procedures.
Filed Date: 6/8/17.
Accession Number: 20170608-5107.
Comments Due: 5 p.m. ET 6/29/17.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: June 8, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-12676 Filed 6-16-17; 8:45 am]
BILLING CODE 6717-01-P